[Federal Register: August 16, 2002 (Volume 67, Number 159)]
[Notices]               
[Page 53581-53582]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr16au02-84]                         

-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY

[ER-FRL-6632-1]

 
Environmental Impact Statements; Notice of Availability

    Responsible Agency: Office of Federal Activities, General 
Information (202) 564-7167 or www.epa.gov/compliance/nepa Weekly 
receipt of Environmental Impact Statements Filed August 5, 2002 Through 
August 9, 2002 Pursuant to 40 CFR 1506.9.
    EIS No. 020339, DRAFT EIS, AFS, MN, Holmes/Chipmunk Timber Sale 
Project, Implementation, Superior National Forest, LaCroix Ranger 
District, Saint Louis County, MN, Comment Period Ends: September 30, 
2002, Contact: John Galazen (218) 666-0020.
    EIS No. 020340, DRAFT EIS, AFS, AZ, Kachina Village Forest Health 
Project, Implementation, Improving Forest Health and Reducing Wildfire 
Potential on National Forest System Land in the Coconino National 
Forest, Mormon Lake Ranger District, Coconino County, AZ, Comment 
Period Ends: September 30, 2002, Contact: Tammy Randall-Parker (928) 
774-1147.
    This document is available on the Internet at: http://
www.fs.fed.us/r3/coconino/nepa.
    EIS No. 020341, FINAL EIS, DOE, WA, OR, Wallula Power Project and 
Wallula-McNary Transmission Line Project, Construction and Operation, 
1300 megawatt(MW) Natural Gas Fired Combustion Gas Turbine Facility and 
a new 500-kilovolt(kV) Transmission Line and Upgrade of the McNary 
Substation, US COE Section 10 and 404 Permits, Walla-Walla Co., WA and 
Umatilla Co., OR, Wait Period Ends: September 16, 2002, Contact: Donald 
L. Rose (503) 230-3796.
    This document is available on the Internet at: http://
www.efsec.wa.gov.
    EIS No. 020342, FINAL EIS, FRC, ID, Four Mid-Snake River 
Hydroelectric Projects, Applications for New License for the Existing 
Projects: Shoshane Falls-FERC No. 2778, Upper Salmon Falls-FERC No. 
2777, Lower Salmon Falls-FERC No. 2061 and Bliss-FERC No. 1975, Snake 
River, ID, Wait Period Ends: September 16, 2002, Contact: John Blair 
(202) 219-2845.
    This document is available on the Internet at: http://
www.rimsweb1.ferc.gov.
    EIS No. 020343, DRAFT EIS, SFW, CA, Natomas Basin Habitat 
Conservation Plan, Issuance of Incidental Take Permit and the Adoption 
of an Implementing Agreement or Agreements, Natomas Basin, Sacramento 
and Sutter Counties, CA, Comment Period Ends: September 30, 2002, 
Contact: Vicki Campbell (916) 414-6600.
    EIS No. 020344, FINAL EIS, AFS, NM, Viveash Fire Timber Salvage 
Project, Proposal to Harvest a Portion of the Fire-Killed Trees, Pecos/
Las Vegas Ranger District, Santa Fe National Forest, NM, Wait Period 
Ends: September 16, 2002, Contact: Chris Napp (505) 757-6121.
    This document is available on the Internet at: http://
www.fs.fed.us/r3/sfe/.
    EIS No. 020345, DRAFT EIS, COE, KS, Kansas Highway 10 (commonly 
known as South Lawrence Trafficway) Relocation, Issuance or Denial of 
Section 404 Permit Request, Lawrence City, Douglas County, KS, Comment 
Period Ends: September 30, 2002, Contact: Robert J. Smith (816) 983-
3656.
    EIS No. 020346, DRAFT EIS, EPA, LA, Marrero-Lafitte Waterline 
Modification of the Memorandum of Agreement (MOA) between USEPA and 
Jefferson Parrish, LA, Approval or Denial, Jefferson Parrish, LA, 
Comment Period Ends: September 30, 2002, Contact: Robert D. Lawrence 
(215) 655-8150.
    EIS No. 020347, DRAFT EIS, SFW, CA, Aquatic Habitat Conservation 
Plan and Candidate Conservation Agreement with Assurances to Conserve 
Habitat for and Mitigate Impacts on Six Aquatic Species, USFWS 
Enhancement of Survival Permit and an USMFS

[[Page 53582]]

Incidental Take Permit Issuance, Humboldt and Del Norte Counties, CA, 
Comment Period Ends: November 19, 2002, Contact: Amedee Brickey (707) 
822-8136.
    This document is available on the Internet at: http://
www.swr.nmfs.noaa.gov/.

Amended Notices

    EIS No. 020248, DRAFT EIS, COE, CA, Bolinas Lagoon Ecosystem 
Restoration, Proposal to Removal up to 1.5 Million Cubic Yard of 
Sediment from the bottom of Lagoon to Allow Restoration of Tidal 
Movement and Eventual Restoration of Tidal Habitat, Marin County, CA, 
Comment Period Ends: October 1, 2002, Contact: Roger Golden (415) 977-
8703. Revision of FR Notice Published on 7/19/2002: CEQ Comment Period 
Ending 8/15/2002 has been extended to 10/1/2002.
    EIS No. 020304, FINAL EIS, NOA, CA, San Francisco Bay National 
Estuarine Research Reserve, Proposes to Designate Three Sites: China 
Camp State Park, Brown's Island Regional Parks District, and Rush Ranch 
Open Space Preserve, Contra Costa, Marin and Solano Counties, CA, Wait 
Period Ends: August 26, 2002, Contact: Laurie McGilvray--ext 15 (301) 
713-3132.
    Revision of FR Notice Published on 7/19/2002: CEQ Wait Period 
Ending on 8/19/2002 has been Extended to 8/26/2002.

    Dated: August 13, 2002.
Joseph C. Montgomery,
Director, NEPA Compliance Division, Office of Federal Activities.
[FR Doc. 02-20862 filed 8-15-02; 8:45 am]
BILLING CODE 6560-50-P