DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP01-390-000]
Egan Hub Partners, L.P.; Notice of Request Under Blanket
Authorization
June 25, 2001.
Take notice that on June 18, 2001, Egan Hub Partners, L.P. (Egan
Hub), 5400 Westheimer Court, Houston, Texas 77056, filed a request with
the Commission in Docket No. CP01-390-000, pursuant to Sections 157.205
and 157.208 of the Commission's Regulations under the Natural Gas Act
(NGA), for authorization to construct and operate facilities under Egan
Hub's blanket certificate, issued in Docket No. CP96-199-000, in Acadia
and Evangeline Parishes, Louisiana to interconnect with the mainline
systems of Texas Eastern Transmission, LP (Texas Eastern) and Florida
Gas Transmission Company (Florida Gas), all as more fully set forth in
the request on file with the Commission and open to public inspection.
This filing may be viewed on the web at http://www.ferc.fed.us/online/
rims.htm (call 202-208-2222 for assistance).
Specifically, Egan Hub requests authorization to: (i) construct,
own, operate, and maintain a new 21.34-mile, 24-inch diameter pipeline
that will originate at the existing Egan Hub storage facilities in
Acadia Parish, Louisiana and terminate at a proposed interconnect with
Texas Eastern in Evangeline Parish; (ii) construct and own a new meter
and regulator station and interconnect facilities at an interconnection
with Texas Eastern in Evangeline Parish; and (iii) construct and own a
new meter and regulator station and interconnect facilities at an
interconnection with Florida Gas in Acadia Parish. The Texas Eastern
M&R Station and Florida Gas M&R Station will be located on property
owned by Egan Hub and will be operated and maintained by Texas Eastern
and Florida Gas, respectively, pursuant to their Operation and
Maintenance Agreements with Egan Hub. The
[[Page 34627]]
estimated cost of the proposed facilities is approximately $17.7
million.
Egan Hub states that its proposed project will not adversely affect
the rates or service of its existing customers. Egan Hub is not
proposing any change its currently authorized market based rate
authority, and contends that the proposed project will not lead to Egan
Hub exercising market power. Egan Hub also states that the proposed
project will provide its customers increased transportation options and
greater access to markets and supplies.
Any questions regarding the application may be directed to S.E.
Tillman, Director of Regulatory Affairs, Egan Hub Partners, L.P., Post
Office Box 1642, Houston, Texas 77251-1642, or telephone (713) 627-5113
or FAX (713) 627-5947.
Any person or the Commission's staff may, within 45 days after the
Commission has issued this notice, file pursuant to Rule 214 of the
Commission's Procedural Rules (18 CFR 385.214) a motion to intervene or
notice of intervention and pursuant to Section 157.205 of the
Regulations under the NGA (18 CFR 157.205) a protest to the request. If
no protest is filed within the allowed time, the proposed activity
shall be deemed to be authorized effective the day after the time
allowed for filing a protest. If a protest is filed and not withdrawn
within 30 days after the time allowed for filing a protest, the instant
request shall be treated as an application for authorization pursuant
to Section 7 of the NGA. Comments, protests and interventions may be
filed electronically via the internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's web site
at http://www.ferc.fed.us/efi/doorbell.htm.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 01-16417 Filed 6-28-01; 8:45 am]