TRAINING: |
No special training requirements have been identified for any
documents issued with this change notice. |
|
REMARKS: |
IMC 0350 |
(Staff Guidelines For Restart Approval) is revised to clarify
the relationship of the Case Specific Checklist (CSC) to the Restart Action
Plan, and the use of the generic examples in Appendix A to develop the CSC.
These examples are based on CSCs for previous restart approvals. They should
be evaluated for applicability to the plant in question, and only be included
in the CSC when they must be resolved before restart. |
IP 71707 |
(Plant Operations) has been revised to delete the requirement that the resident
inspector document whether or not INPO evaluation and accreditations reports
were generally consistent with NRC evaluations. The inspector will now document
that an INPO review was completed. |
IP 90712 |
(In-Office Review of Written Reports of Nonroutine Events at Power Reactor
Facilities) |
IP 92700 |
(Onsite Followup of Written Reports of Nonroutine Events at Power Reactor
Facilities) |
These two inspection procedures have been revised in response
to a security event at Millstone and the subsequent Office of the Inspector
General investigation into how the region handled the event, Although management
concluded staff actions were consistent with NRC guidance, documentation of
staff activities was incomplete. Region I issued staff guidance incorporating
lessons learned, which has been incorporated into these revisions. |
|
DISTRIBUTION: |
Standard |