Bellefonte Units 3 & 4
Callaway Unit 2
Calvert Cliffs Unit 3
Comanche Peak Units 3 & 4
Fermi Unit 3
Grand Gulf Unit 3
Levy County Units 1 & 2
North Anna Unit 3
River Bend Station Unit 3
Shearon Harris Units 2 & 3
South Texas Project Units 3 & 4
Victoria County Station Units 1 & 2
Virgil C. Summer Units 2 & 3
Vogtle Units 3 & 4
William States Lee III Units 1 & 2

Shearon Harris Nuclear Site, Units 2 and 3 Application

Shearon Harris Nuclear Site
Who:   Progress Energy (PE)

What:   Application for a combined license (COL) for two Westinghouse Advanced Passive 1000 (AP1000) Pressurized Water Reactors (PWR) designated as Harris Units 2 & 3.

When:   February 19, 2008 (date of application submittal)

Where:   PE's Harris site near New Hill in Wake County, North Carolina

On this page:

The following links on this page are to documents in our Agencywide Documents Access and Management System (ADAMS). ADAMS documents are provided in either Adobe Portable Document Format (PDF) or Tagged Image File Format (TIFF). To obtain free viewers for displaying these formats, see our Plugins, Viewers, and Other Tools. If you have problems with viewing or printing documents from ADAMS, please contact the Public Document Room staff.

Reference Documents

To top of page

Applicant Documents

Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.

PE's transmittal letter for Shearon Harris Nuclear Station Units 2 & 3 COLA (February 18, 2008)

  • Part 0 – Cover Letter, Affidavits, etc
  • Part 1 – Administrative and Financial Information
  • Part 2 – Final Safety Analysis Report (FSAR)
  • Part 3 – Environmental Report
  • Part 4 – Technical Specifications
  • Part 5 – Emergency Plan
  • Part 6 – [Not Used. Reserved for applicants requesting Limited Work Authorization (LWA)]
  • Part 7 – Departure and Exemption Requests
  • Part 8 – [This Part contains safeguards information which is with-held from public availability]
  • Part 9 – [This Part contains other information which is with-held from public availability]
  • Part 10 – Licensee Conditions and Inspection, Tests, Analyses and Acceptance Criteria (ITTAC)

To top of page

Application Review Schedule

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 02/19/08 - A
Acceptance Review
Acceptance Review Start
02/20/08 - A
Docketing Decision Letter Issued/Acceptance Review Complete
04/17/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
05/16/08 - A
Safety Review
Phase 1 –Requests for Additional Information (RAIs) Issued to Applicant
11/26/08 - T
Phase 2 – SER with Open Items issued
07/22/09 - T
Phase 3 – ACRS Review of SER with Open Items Complete
01/07/10 - T
Phase 4 – Advanced SER with no Open Items Issued
10/31/10 - T
Phase 5 – ACRS Review of SER with no Open Items Complete
02/28/11- T
Phase 6 – Final SER Issued
04/30/11 - T
Environmental Review
Phase 1 – Environmental impact statement (EIS) summary report issued
11/20/08 - T
Phase 2 – Draft EIS issued to EPA
06/26/09 - T
Phase 3 – Response to public comments on draft EIS issued
11/30/09 - T
Phase 4 – Final EIS issued to EPA
05/31/10 - T
Hearing
Commission or ASLB hold mandatory hearing
 
License
Commission decision on issuance of COL application
 

Information on Federal Register Notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found at NRC’s Website on Hearing Opportunities.

To top of page

NRC Documents

To top of page

Requests for Additional Information

Category RAI Date RAI Letter No. and Subject Applicant Response
Safety 08/01/08 RAI Letter No. 01 SRP Section 02.03.02  
08/12/08 RAI Letter No. 02 SRP Section 02.03.03  
08/13/08 RAI Letter No. 03 SRP Section 02.03.04  
08/13/08 RAI Letter No. 04 SRP Section 02.03.05  
08/18/08 RAI Letter No. 05 SRP Section 02.03.01  
08/18/08 RAI Letter No. 06 SRP Section 02.02.03  
08/21/08 RAI Letter No. 07 SRP Section 02.02.01 & 02.02.02  
09/16/08 RAI Letter No. 08 SRP Section 07.05  
09/17/08 RAI Letter No. 09 SRP Section 02.04.03  
09/18/08 RAI Letter No. 10 SRP Section 02.04.12  
09/22/08 RAI Letter No. 11 SRP Section 9.2.5  
09/22/08 RAI Letter No. 12 SRP Section 9.3.3  
09/22/08 RAI Letter No. 13 SRP Section 9.5.1  
09/22/08 RAI Letter No. 14 SRP Section 9.2.1  
09/23/08 RAI Letter No. 15 SRP Section 06.04  
09/24/08 RAI Letter No. 16 SRP Section 19  

To top of page

Public Meetings

Date Description
06/10/08 Harris Public Scoping Meeting
03/06/08 Harris S-COLA Orientation
09/18/07 Public Outreach

To top of page

Contacts

Contacts for the Shearon Harris Nuclear Site COL Application
Safety Project Manager Manny Comar
Sr. Environmental Project Manager Donald Palmrose
Environmental Project Manager Bruce Olson