EA-06-112
Quad Cities 1 & 2 |
NOV
(White) |
06/29/2006 |
On June 29, 2006, a Notice of Violation associated with a White
SDP finding was issued for a finding involving the failure to establish
measures to ensure that the Unit 1 electromatic relief valves (ERVs)
remained suitable for operation prior to implementing an extended
power uprate (EPU) in November 2002. This resulted in multiple ERVs
becoming inoperable and unavailable due to being subjected to significantly
higher vibration levels during Unit 1 operation at EPU power levels. |
EA-98-231
Quad Cities 1 & 2 |
NOVCP
(SL II)
$88,000
|
09/11/1998 |
This action is based on one Severity Level II problem involving
very significant inadequacies in ComEd's capability to shut down the
Quad Cities facility and maintain the units in a safe shutdown condition
following a postulated design basis fire. |
EA-97-591
Quad Cities 1 & 2 |
NOVCP
(SL III)
$330,000 |
03/12/1998 |
Licensee used critical heat to perform code required leak
testing and licensee lived with a failed inner o-ring in the RV for
over one year. |
EA-97-466
Quad Cities 1 & 2 |
NOVCP
(SL III)
$ 55,000 |
03/03/1998 |
Maintenance rule violation. |
EA-96-530 & EA-96-531
Quad Cities 1 & 2 |
NOVCP
(SL III)
$ 50,000 |
06/24/1997 |
Failure to maintain secondary containment as safety related. |
EA-96-114
Quad Cities 1 & 2 |
NOVCP
(SL III)
$ 50,000 |
06/13/1996 |
Corner rooms structural steel in a condition outside of FSAR
caused by failure to account for modifications in the original design
calculations. |