Oconee 1, 2 & 3 - Docket Nos. 050-00269; 050-00270; 050-00287

NRC Action Number(s) and
Facility Name
Action Type
(Severity) &
Civil Penalty
(if any)
Date
Issued
Description
EA-06-294
Oconee 3
NOV
(White)
02/13/2007 On February 13, 2007, a Notice of Violation was issued for a violation associated with a WHITE significance determination process (SDP) finding involving the identification of foreign material in the Unit 3 A and B train reactor building emergency sump (RBES) suction lines during the end-of-cycle 22 refueling outage. Specifically, some time prior to and for the duration of Oconee Unit 3 operating cycle 22, adequate foreign material exclusion controls had not been implemented resulting in the discovery of foreign material in the A and B train RBES suction lines. The violation was cited against Technical Specification 5.4.1, “Procedures,” and Section 9.e of the referenced Regulatory Guide 1.33 for the failure to comply with Nuclear System Directive 104, “Material Condition/Housekeeping, Cleanliness/Foreign Material Exclusion, and Seismic Concerns,” for the failure to maintain the Unit 3 RBES free of foreign material.
EA-06-199
Oconee 1, 2, 3
NOV
(White)
11/22/2006 On November 22, 2006, a Notice of Violation was issued for a violation associated with a WHITE significance determination process finding involving the failure to effectively control maintenance activities and the failure to assess and manage the risk associated with removing an access cover in the south wall of the standby shutdown facility (SSF) to facilitate installation of temporary electrical power cables. The violation was cited against technical specifications because of an inadequate procedure and 10 CFR 50.65(a)(4) because of the licensee’s failure to adequately assess and manage the increase in risk from maintenance activities.
EA-04-115
Oconee 1, 2, 3
NOV
(White)

09/24/2004 On September 24, 2004, a Notice of Violation was issued for a violation associated with a White SDP finding involving inconsistent fire response procedures that could result in the failure to maintain pressurizer level within the required indicating range. The violation cited the licensee’s inadequate fire response procedures.
EA-04-018
Oconee 1, 2, 3
NOVCP
(SL III)

$60,000
04/08/2004 On April 8, 2004, a Notice of Violation and Proposed Imposition of Civil Penalty in the amount of $60,000 was issued for a Severity Level III violation involving the failure to adhere to the requirements of 10 CFR 50.59, in that the licensee made changes to the Oconee facility as described in the Updated Final Safety Analysis Report and referenced analyses that involved unreviewed safety questions without obtaining prior NRC approval. In this case, the licensee revised an analysis for high energy line break accidents, which permitted the facility to initiate emergency feedwater up to 30 minutes and initiate high pressure injection up to eight hours after a high energy line break accident instead of 15 minutes and one hour as was discussed in the Updated Final Safety Analysis Report.
EA-03-145
Oconee 1, 2, 3
NOV
(White)
12/30/2003 On December 30, 2003, a Notice of Violation was issued for a violation associated with a White SDP finding involving the inability of the pressurizer to perform its intended safety function under certain scenarios. The violation cited the licensee’s failure to identify and correct this condition adverse to safety.
EA-02-243
Oconee 3
NOV
(White)
02/07/2003 On February 7, 2003, a Notice of Violation was issued for a violation associated with a White SDP finding involving the possible loss of high pressure injection (HPI) pump function during a postulated high energy line break/tornado event recovery. The violation cited the licensee's failure to properly implement the vendor's written instructions for attaching the electrical connectors on the pre-staged Unit 3 HPI pump emergency power supply cable from the auxiliary service water (ASW) switchgear.
EA-02-048
Oconee 1, 2 & 3
NOV
(White)
08/02/2002 On August 2, 2002, a Notice of Violation was issued for a violation associated with a white SDP finding involving containment integrity upon a possible loss of reactor decay heat removal. The violation cited the licensee's failure to establish adequate procedures to assure that containment closure would be achieved prior to the time at which a core uncovery and fission product release could result from a loss of shutdown cooling.
EA-02-034
Oconee 1, 2 & 3
NOV
(White)
07/26/2002 On July 26, 2002, a Notice of Violation was issued for a violation associated with a white SDP finding involving the vulnerability to flooding in the Oconee Unit 1 auxiliary building from a potential rupture of the high pressure service water (HPSW) system piping. The violation cited the licensee's failure to take prompt corrective action for the lack of mitigation capabilities for an auxiliary building flood, a condition adverse to quality.
EA-01-125
Oconee 1, 2 & 3
NOV
(White)
07/18/2001 On July 18, 2001, a Notice of Violation was issued for a violation associated with a White SDP finding. The violation involved inadequate procedures for aligning the station auxiliary service water pump to mitigate a tornado and the licensee's failure to take prompt corrective action for this adverse condition even though the licensee had identified the condition approximately one year earlier.
EA-00-137
Oconee 1, 2 & 3
NOV
(White)
11/09/2000 On November 9, 2000, a Notice of Violation was issued for a violation associated with a White SDP finding. The violation involved the failure to adequately establish design control measures involving the high pressure injection system using the spent fuel pool as a suction source following a tornado.
EA-98-268
Oconee 1, 2 & 3
NOV
(SL II)
08/05/1998 Failure to implement the requirements of 10 CFR 50, Appendix B, Criterion III, to incorporate design basis requirements into drawings and procedures; and failure to maintain technical specification equipment in an operable condition.
EA-97-297 & EA-97-298
Oconee 1, 2 & 3

 

NOVCP
(SL III)

$330,000
08/27/1997 Cracks in HP injection line and failure of HPI pump.
EA-96-019
Oconee 1, 2 & 3
NOVCP
(SL III)

$ 50,000
03/05/1996 Failure to provide adequate procedures to control fuel assembly movement in the spent fuel pool.
To top of page

Oregon State University - Docket No. 050-00243

NRC Action Number(s) and
Facility Name
Action Type
(Severity) &
Civil Penalty
(if any)
Date
Issued
Description
EA-98-320
Oregon State University Research Reactor
NOVCP
(SL III)
07/31/1998 Due to authorized wiring mod of reactor control panel, reactor
scram functions were disabled.
To top of page

Oyster Creek - Docket No. 050-00219

NRC Action Number(s) and
Facility Name
Action Type
(Severity) &
Civil Penalty
(if any)
Date
Issued
Description
EA-05-199
Oyster Creek
NOV
(White)
01/09/2005 On January 9, 2006, a Notice of Violation was issued for a violation of 10 CFR 50.54(q), 10 CFR 50.47(b)(4), and the Oyster Creek Generating Station Emergency Plan. This finding was associated with a White Significance Determination Process (SDP) finding involving the licensee's failure to properly utilize the Emergency Plan emergency action level (EAL) matrix during an actual event. Specifically, operators did not recognize that plant parameters met the EAL thresholds for declaring an Unusual Event and a subsequent Alert. Since an Alert was not declared, licensee personnel did not activate their emergency response organization to assist operators in mitigating the event. Additionally, State and local agencies, who rely on information provided by the facility licensee, might not have been able to take initial offsite response measures in as timely a manner had the event degraded further.
EA-04-213
Oyster Creek
NOV
(White)
03/1/2005 On March 1, 2005, a Notice of Violation was issued for violations associated with a White SDP finding involving untimely actions to change an Emergency Action Level threshold value used to declare a General Emergency or a Site Area Emergency and revise supporting emergency procedures. The violations cited the licensee's failure to maintain an emergency classification and action level scheme and the failure to properly implement the configuration change process in accordance with the Technical Specifications.
EA-04-033
Oyster Creek
NOV
(White)

03/15/2004 On March 15, 2004, a Notice of Violation was issued for a violation associated with a White SDP finding involving a power cable insulation breakdown that resulted in a loss of the 4kV emergency bus and forced a plant shutdown. The violation cited the licensee’s failure to identify and take prompt and appropriate corrective actions for a significant condition adverse to quality involving power cables.
EA-98-220
Oyster Creek
NOVCP
(SL III)

$ 55,000
06/15/1998 Inoperability of automatic depressurization valves as well as design errors and apparent qualification concerns that contributed to the inoperability.
EA-97-617
Oyster Creek
NOV
(SL III)
02/08/1998 Equipment downgrading.
EA-97-421
Oyster Creek
NOV
(SL III)
11/17/1997 Multiple examples of design control and corrective action violations involving electrical distribution.
To top of page