PIV Credentials Report
Homeland Security Presidential Directive 12 (HSPD-12)
Last Updated: September 2, 2008
Updated Date: | Number of Employees requiring PIV credentials* | Number of Employees requiring a NACI (or at least equivalent) that have not previously undergone a background check* | Number of Employees requiring a NACI (or at least equivalent) with background investigation in process* |
Number of Employees with completed/ adjudicated NACI (or equivalent background investigation)* | Total Number of PIV credentials Issued to Employees* |
Mar/2007 | 3048 | 190 | N/A | N/A | 3 |
Jun/2007 | 3048 | 199 | N/A | N/A | 3 |
Sep/2007 | 3097 | 124 | N/A | N/A | 3 |
Dec/2007 | 3091 | 800 | 800 | 2300 | 9 |
Mar/2008 | 3040 | 400 | 400 | 2700 | 60 |
Jun/2008 | 2595 | 22 | 22 | 3078 | 505 |
Sep/2008 | 1819 | 8 | 8 | 3092 | 1281 |
Updated Date: | Number of Contractors requiring PIV credentials | Number of Contractors requiring NACI (or at least equivalent) that have not previously undergone a background check | Number of Contractors requiring a NACI (or at least equivalent) with background investigation in process |
Number of Contractors with completed/ adjudicated NACI (or equivalent background investigation) | Total Number of PIV credentials Issued to Contractors |
Mar/2007 | 0 | 275 | N/A | N/A | 0 |
Jun/2007 | 0 | 221 | N/A | N/A | 0 |
Sep/2007 | 0 | 218 | N/A | N/A | 0 |
Dec/2007 | 0 | 200 | 200 | 1800 | 0 |
Mar/2008 | 0 | 86 | 86 | 1914 | 0 |
Jun/2008 | 0 | 0 | 0 | 2000 | 0 |
Sep/2008 | 0 | 0 | 0 | 2000 | 0 |
Updated Date: | Number of other individuals (e.g. guest researchers) requiring PIV credentials | Number of other individuals (e.g. guest researchers) requiring NACI (or at least equivalent) that have not previously undergone a background check | Number of other individuals requiring a NACI (or at least equivalent) with background investigation in process |
Number of other individuals with completed/ adjudicated NACI (or equivalent background investigation) | Total Number of PIV credentials issued to individuals other than employees or contractors (e.g. guest researchers) |
Mar/2007 | 0 | 89 | N/A | N/A | 0 |
Jun/2007 | 0 | 129 | N/A | N/A | 0 |
Sep/2007 | 0 | 104 | N/A | N/A | 0 |
Dec/2007 | 0 | 0 | 0 | 2500 | 0 |
Mar/2008 | 0 | 0 | 0 | 2500 | 0 |
Jun/2008 | 0 | 0 | 0 | 2500 | 0 |
Sep/2008 | 0 | 0 | 0 | 2500 | 0 |
Implementation Plan Summary | |||||
Planned Date of Full Implementation: Oct 27, 2008 | Planned Total Number of NACIs to be verified/completed for current employees and contractors by Oct 27, 2008: 7600 |
|
Next Major Milestone: Oct 27, 2008 - Goal to have 100% of NARA Federal Employees issued PIV Credentials. |