Klondike III Wind Project |
|
|
![](https://webarchive.library.unt.edu/eot2008/20081015100324im_/http://www.oregon.gov/images/spacer.gif) |
|
|
Facility:
A wind energy facility with a peak generating capacity of up to 375 megawatts.
Location: Sherman County
Status:
175 wind turbines with a combined peak generating capacity of approximately 298 megawatts are in operation. An additional 2.3-MW turbine is under construction.
Certificate Holder:
Klondike Wind Power III, LLC
Contact:
Jesse Gronner
Klondike Wind Power III, LLC
c/o PPM Energy, Inc.
1125 NW Couch St., Suite 700
Portland, OR 97209
503-796-7045
Department of Energy Staff: John White
Original site certificate signed: July 12, 2006
Current site certificate: Third Amended Site Certificate (effective November 27, 2007)
History:
- February 17, 2005: Applicant submitted a request for expedited review.
- March 28, 2005: Department of Energy approved expedited review.
- May 13, 2005: Application received.
- February 6, 2006: Application completed (date of filing).
- April 18, 2006: Department of Energy issued a draft proposed order.
- May 31, 2006: Department of Energy issued a proposed order.
- June 13, 2006: Department of Energy issued a supplemental proposed order.
- June 30, 2006: Council approved a site certificate.
- July 31, 2006: Request for Amendment #1 received.
- October 2, 2006: Department of Energy issued a proposed order on Amendment #1.
- October 23, 2006: Start of construction.
- November 3, 2006: Council approved Amendment #1.
- November 8, 2006: Effective date of First Amended Site Certificate.
- April 12, 2007: Request for Amendment #2 received.
- June 19, 2007: Department of Energy issued a proposed order on Amendment #2.
- June 25, 2007: Request for Amendment #3 received.
- July 27, 2007: Council approved Amendment #2.
- August 1, 2007: Effective date of Second Amended Site Certificate.
- October 11, 2007: Department of Energy issued a proposed order on Amendment #3.
- October 22, 2007: Start of commercial operation (123 Phase 1 turbines).
- November 16, 2007: Council approved Amendment #3.
- November 27, 2007: Effective date of Third Amended Site Certificate.
- March 17, 2008: Start of commercial operation of the Mitsubishi 2.4-MW turbine (Phase 1).
- June 21, 2008: Start of commercial operation of Phase 2 (51 turbines).
Documents:
|
|
|
|