Unit |
Power |
Down |
Reason or Comment |
Change in report(*) |
Number of Scrams(#) |
BRAIDWOOD 1 |
100 |
|
|
|
|
BRAIDWOOD 2 |
100 |
|
|
|
|
BYRON 1 |
100 |
|
|
|
|
BYRON 2 |
100 |
|
|
|
|
CLINTON 1 |
93 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
|
|
COOK 1 |
100 |
|
|
|
|
COOK 2 |
0 |
04/23/2003 |
Cold Shutdown REFUELING OUTAGE |
|
|
DAVIS BESSE 1 |
0 |
02/15/2002 |
Cold Shutdown REFUELING OUTAGE |
|
|
DRESDEN 2 |
96 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
* |
|
DRESDEN 3 |
0 |
06/11/2003 |
Cold Shutdown SHUTDOWN TO FIX GENERATOR HYDROGEN LEAK |
|
|
DUANE ARNOLD 1 |
94 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
|
|
FERMI 2 |
100 |
|
|
|
|
KEWAUNEE 1 |
100 |
|
|
|
|
LASALLE 1 |
100 |
|
|
|
|
LASALLE 2 |
100 |
|
|
|
|
MONTICELLO 1 |
0 |
06/14/2003 |
Cold Shutdown MAINTENANCE OUTAGE |
* |
|
PALISADES 1 |
100 |
|
|
|
|
PERRY 1 |
100 |
|
|
|
|
POINT BEACH 1 |
70 |
|
Power Operation INCREASING POWER AFTER TURBINE STOP VALVE TESTING |
* |
|
POINT BEACH 2 |
100 |
|
|
|
|
PRAIRIE ISLAND 1 |
100 |
|
|
|
|
PRAIRIE ISLAND 2 |
100 |
|
|
|
|
QUAD CITIES 1 |
97 |
|
Power Operation INCREASING POWER AFTER MAINTENANCE |
* |
|
QUAD CITIES 2 |
0 |
06/10/2003 |
Refueling REFUELING OUTAGE |
|
|