Unit |
Power |
Down |
Reason or Comment |
Change in report(*) |
Number of Scrams(#) |
BEAVER VALLEY 1 |
0 |
03/07/2003 |
Intermediate Shut REFUELING OUTAGE - DEFUELED |
|
|
BEAVER VALLEY 2 |
100 |
|
|
|
|
CALVERT CLIFFS 1 |
100 |
|
|
|
|
CALVERT CLIFFS 2 |
0 |
02/14/2003 |
Refueling REFUELING OUTAGE - DEFUELED |
|
|
FITZPATRICK 1 |
100 |
|
|
|
|
GINNA 1 |
100 |
|
|
|
|
HOPE CREEK 1 |
99 |
|
Power Operation COASTDOWN TO REFUELING OUTAGE |
|
|
INDIAN POINT 2 |
100 |
|
|
|
|
INDIAN POINT 3 |
0 |
03/28/2003 |
Cold Shutdown REFUELING OUTAGE |
* |
|
LIMERICK 1 |
100 |
|
|
|
|
LIMERICK 2 |
100 |
|
|
|
|
MILLSTONE 2 |
100 |
|
|
* |
|
MILLSTONE 3 |
100 |
|
|
|
|
NINE MILE POINT 1 |
0 |
03/14/2003 |
Refueling REFUELING OUTAGE |
|
|
NINE MILE POINT 2 |
100 |
|
|
|
|
OYSTER CREEK 1 |
77 |
|
Power Operation INCREASING POWER - CRD MAINTENANCE IN PROGRESS |
* |
|
PEACH BOTTOM 2 |
100 |
|
|
|
|
PEACH BOTTOM 3 |
100 |
|
|
|
|
PILGRIM 1 |
100 |
|
|
|
|
SALEM 1 |
47 |
|
Power Operation REDUCING POWER - CIRCULATING PUMP OUTAGE |
* |
|
SALEM 2 |
0 |
03/29/2003 |
Hot Standby MANUAL REACTOR TRIP DUE TO LOSS OF SECONDARY CIRC WATER PUMPS - SEE EVENT #39713 |
* |
1 |
SEABROOK 1 |
100 |
|
|
|
|
SUSQUEHANNA 1 |
100 |
|
|
|
|
SUSQUEHANNA 2 |
0 |
03/07/2003 |
Refueling REFUELING OUTAGE |
|
|
THREE MILE ISLAND 1 |
100 |
|
|
|
|
VERMONT YANKEE 1 |
77 |
|
Power Operation REDUCED POWER FOR GRID STABILITY DUE TO BREAKER PROBLEMS IN 345KV SWITCHYARD |
* |
|
Unit |
Power |
Down |
Reason or Comment |
Change in report(*) |
Number of Scrams(#) |
BROWNS FERRY 1 |
0 |
03/03/1985 |
Cold Shutdown DEFUELED |
|
|
BROWNS FERRY 2 |
82 |
|
Power Operation INCREASING POWER |
* |
|
BROWNS FERRY 3 |
65 |
|
Power Operation REDUCED POWER FOR WATERBOX CLEANING AND SURVEILLANCE TESTING |
* |
|
BRUNSWICK 1 |
94 |
|
Power Operation 100% ELECTRICAL POWER |
|
|
BRUNSWICK 2 |
0 |
03/07/2003 |
Cold Shutdown REFUELING OUTAGE |
|
|
CATAWBA 1 |
100 |
|
|
|
|
CATAWBA 2 |
72 |
|
Power Operation INCREASING POWER |
* |
|
CRYSTAL RIVER 3 |
100 |
|
|
|
|
FARLEY 1 |
0 |
03/28/2003 |
Cold Shutdown REFUELING OUTAGE |
* |
|
FARLEY 2 |
100 |
|
|
|
|
HARRIS 1 |
100 |
|
|
|
|
HATCH 1 |
100 |
|
|
|
|
HATCH 2 |
17 |
|
Power Operation STARTUP IN PROGRESS - PREPARING TO SYNC GENERATOR TO GRID |
* |
|
MCGUIRE 1 |
100 |
|
|
|
|
MCGUIRE 2 |
100 |
|
|
|
|
NORTH ANNA 1 |
0 |
02/22/2003 |
Refueling REFUELING OUTAGE - DEFUELED |
|
|
NORTH ANNA 2 |
100 |
|
|
|
|
OCONEE 1 |
52 |
|
Power Operation HOLDING POWER FOR NI CAL |
* |
|
OCONEE 2 |
100 |
|
|
|
|
OCONEE 3 |
98 |
|
Power Operation COASTDOWN TO REFUELING OUTAGE |
* |
|
ROBINSON 2 |
100 |
|
|
|
|
SAINT LUCIE 1 |
100 |
|
|
|
|
SAINT LUCIE 2 |
100 |
|
|
|
|
SEQUOYAH 1 |
0 |
03/16/2003 |
Refueling REFUELING OUTAGE - DEFUELED |
|
|
SEQUOYAH 2 |
2 |
|
Startup MAKING PREPARATIONS FOR POWER ASCENSION |
* |
|
SUMMER 1 |
100 |
|
|
|
|
SURRY 1 |
100 |
|
|
|
|
SURRY 2 |
100 |
|
|
|
|
TURKEY POINT 3 |
52 |
|
Power Operation INCREASING POWER |
* |
|
TURKEY POINT 4 |
100 |
|
|
|
|
VOGTLE 1 |
100 |
|
|
|
|
VOGTLE 2 |
100 |
|
|
|
|
WATTS BAR 1 |
100 |
|
|
|
|
Unit |
Power |
Down |
Reason or Comment |
Change in report(*) |
Number of Scrams(#) |
BRAIDWOOD 1 |
94 |
|
Power Operation COASTDOWN TO REFUELING OUTAGE |
* |
|
BRAIDWOOD 2 |
100 |
|
|
|
|
BYRON 1 |
100 |
|
|
|
|
BYRON 2 |
100 |
|
|
|
|
CLINTON 1 |
91 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
|
|
COOK 1 |
100 |
|
|
|
|
COOK 2 |
100 |
|
|
|
|
DAVIS BESSE 1 |
0 |
02/15/2002 |
Cold Shutdown REFUELING OUTAGE |
|
|
DRESDEN 2 |
97 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
|
|
DRESDEN 3 |
13 |
|
Power Operation CURRENTLY REINERTING - GENERATOR OFFLINE |
* |
|
DUANE ARNOLD 1 |
0 |
03/23/2003 |
Cold Shutdown REFUELING OUTAGE |
|
|
FERMI 2 |
0 |
03/28/2003 |
Cold Shutdown REFUELING OUTAGE |
* |
|
KEWAUNEE 1 |
100 |
|
|
|
|
LASALLE 1 |
100 |
|
|
|
|
LASALLE 2 |
100 |
|
|
|
|
MONTICELLO 1 |
100 |
|
|
|
|
PALISADES 1 |
0 |
03/16/2003 |
Refueling REFUELING OUTAGE |
|
|
PERRY 1 |
83 |
|
Power Operation COASTDOWN TO REFUELING OUTAGE |
|
|
POINT BEACH 1 |
100 |
|
|
|
|
POINT BEACH 2 |
100 |
|
|
|
|
PRAIRIE ISLAND 1 |
100 |
|
|
|
|
PRAIRIE ISLAND 2 |
100 |
|
|
|
|
QUAD CITIES 1 |
98 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
|
|
QUAD CITIES 2 |
97 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
* |
|
Unit |
Power |
Down |
Reason or Comment |
Change in report(*) |
Number of Scrams(#) |
ARKANSAS NUCLEAR 1 |
100 |
|
|
|
|
ARKANSAS NUCLEAR 2 |
100 |
|
|
|
|
CALLAWAY 1 |
0 |
03/22/2003 |
Cold Shutdown MAINTENANCE OUTAGE |
|
|
COLUMBIA GENERATING |
100 |
|
|
|
|
COMANCHE PEAK 1 |
57 |
|
Power Operation HOLDING POWER FOR MAINTENANCE |
|
|
COMANCHE PEAK 2 |
100 |
|
|
|
|
COOPER 1 |
0 |
02/23/2003 |
Refueling REFUELING OUTAGE |
|
|
DIABLO CANYON 1 |
100 |
|
|
|
|
DIABLO CANYON 2 |
2 |
|
Startup MAKING PREPARATIONS FOR STARTUP |
* |
|
FT CALHOUN 1 |
100 |
|
|
|
|
GRAND GULF 1 |
100 |
|
|
|
|
PALO VERDE 1 |
0 |
03/27/2003 |
Cold Shutdown MANUAL REACTOR TRIP DUE TO CONDENSER TUBE RUPTURE - SEE EVENT #39705 |
|
|
PALO VERDE 2 |
98 |
|
Power Operation RCS T hot Temperature Limited |
|
|
PALO VERDE 3 |
0 |
03/28/2003 |
Hot Shutdown REFUELING OUTAGE |
* |
|
RIVER BEND 1 |
0 |
03/16/2003 |
Refueling REFUELING OUTAGE |
|
|
SAN ONOFRE 2 |
100 |
|
|
|
|
SAN ONOFRE 3 |
100 |
|
|
|
|
SOUTH TEXAS 1 |
0 |
03/25/2003 |
Cold Shutdown REFUELING OUTAGE |
|
|
SOUTH TEXAS 2 |
100 |
|
|
|
|
WATERFORD 3 |
100 |
|
|
|
|
WOLF CREEK 1 |
100 |
|
|
|
|