Unit |
Power |
Down |
Reason or Comment |
Change in report(*) |
Number of Scrams(#) |
BEAVER VALLEY 1 |
60 |
|
HOLDING POWER AT THIS LEVEL TO PERFORM PLANNED MAINTENANCE ON A FEEDWATER PU |
|
|
BEAVER VALLEY 2 |
100 |
|
|
|
|
CALVERT CLIFFS 1 |
0 |
05/10/1999 |
MAINTENANCE OUTAGE - PREPARING TO ENTER MODE 3 |
* |
|
CALVERT CLIFFS 2 |
100 |
|
|
|
|
FITZPATRICK 1 |
100 |
|
|
|
|
GINNA 1 |
99 |
|
OPERATING AT REDUCED LOAD DUE TO DELTA-T SETPOINT ISSUES |
* |
|
HOPE CREEK 1 |
100 |
|
|
|
|
INDIAN POINT 2 |
99 |
|
MAXIMUM OPERATING POWER DUE TO STEAM FLOW DEMAND - TURBINE THROTTLE VALVES F |
|
|
INDIAN POINT 3 |
100 |
|
|
|
|
LIMERICK 1 |
100 |
|
|
|
|
LIMERICK 2 |
0 |
04/16/1999 |
REFUELING OUTAGE - REACTOR REASSEMBLY IN PROGRESS |
* |
|
MILLSTONE 2 |
46 |
|
INCREASING POWER TO 49% FOR AN NRC HOLD |
* |
|
MILLSTONE 3 |
0 |
05/01/1999 |
REFUELING OUTAGE - FUEL OFFLOAD SUSPENDED DUE TO PROBLEMS WITH SIGMA MACHINE |
|
|
NINE MILE POINT 1 |
0 |
04/11/1999 |
REFUELING OUTAGE - DEFUELED |
|
|
NINE MILE POINT 2 |
100 |
|
|
|
|
OYSTER CREEK 1 |
85 |
|
INCREASING POWER AFTER REDUCING TO 65% POWER TO PERFORM PLANNED MAINTENANCE |
* |
|
PEACH BOTTOM 2 |
100 |
|
|
* |
|
PEACH BOTTOM 3 |
100 |
|
|
|
|
PILGRIM 1 |
0 |
05/08/1999 |
REFUELING OUTAGE - FUEL OFFLOAD AND FUEL SHUFFLE IN PROGRESS |
|
|
SALEM 1 |
100 |
|
|
|
|
SALEM 2 |
0 |
04/03/1999 |
REFUELING OUTAGE |
|
|
SEABROOK 1 |
60 |
|
INCREASING POWER AFTER EXITING A REFUELING OUTAGE |
* |
|
SUSQUEHANNA 1 |
100 |
|
|
|
|
SUSQUEHANNA 2 |
100 |
|
|
|
|
THREE MILE ISLAND 1 |
100 |
|
|
|
|
VERMONT YANKEE 1 |
100 |
|
|
|
|