Unit |
Power |
Down |
Reason or Comment |
Change in report(*) |
Number of Scrams(#) |
BEAVER VALLEY 1 |
0 |
05/01/1999 |
SURVEILLANCE OUTAGE - SHUTDOWN DUE TO PROBLEMS WITH THE MAIN TURBINE SEAL OI |
|
|
BEAVER VALLEY 2 |
100 |
|
|
|
|
CALVERT CLIFFS 1 |
100 |
|
|
|
|
CALVERT CLIFFS 2 |
0 |
03/12/1999 |
EXITING REFUELING OUTAGE |
|
|
FITZPATRICK 1 |
100 |
|
|
|
|
GINNA 1 |
100 |
|
REACTOR POWER DECREASED FROM 97% TO 94% ON 05/05/99 DUE TO A 1.2-SECOND TURB |
* |
|
HOPE CREEK 1 |
100 |
|
|
|
|
INDIAN POINT 2 |
99 |
|
MAXIMUM OPERATING POWER DUE TO STEAM FLOW DEMAND - TURBINE THROTTLE VALVES F |
|
|
INDIAN POINT 3 |
100 |
|
|
|
|
LIMERICK 1 |
100 |
|
|
|
|
LIMERICK 2 |
0 |
04/16/1999 |
REFUELING OUTAGE - FUEL SHUFFLE ON HOLD - PERFORMING CONTROL ROD DRIVE MAINT |
* |
|
MILLSTONE 2 |
0 |
02/20/1996 |
EXITING REFUELING OUTAGE - PLANT STARTUP ON HOLD DUE TO RESTRAINING ORDER BY |
|
|
MILLSTONE 3 |
0 |
05/01/1999 |
ENTERING REFUELING OUTAGE |
|
|
NINE MILE POINT 1 |
0 |
04/11/1999 |
REFUELING OUTAGE - DEFUELED |
|
|
NINE MILE POINT 2 |
32 |
|
HOLDING POWER AT THIS LEVEL TO TROUBLESHOOT RECIRCULATION FLOW CONTROL VALVE |
* |
|
OYSTER CREEK 1 |
100 |
|
|
|
|
PEACH BOTTOM 2 |
100 |
|
|
|
|
PEACH BOTTOM 3 |
100 |
|
|
|
|
PILGRIM 1 |
80 |
|
HOLDING POWER AT THIS LEVEL DUE TO AN INOPERABLE MAIN STEAM ISOLATION VALVE |
|
|
SALEM 1 |
100 |
|
|
|
|
SALEM 2 |
0 |
04/03/1999 |
REFUELING OUTAGE - VESSEL HEAD TENSIONING IN PROGRESS |
* |
|
SEABROOK 1 |
0 |
03/27/1999 |
REFUELING OUTAGE - BUBBLE DRAWN IN PRESSURIZER |
* |
|
SUSQUEHANNA 1 |
100 |
|
|
|
|
SUSQUEHANNA 2 |
95 |
|
HOLDING POWER AT THIS LEVEL IN PREPARATION FOR A PLANNED FORCED MAINTENANCE |
* |
|
THREE MILE ISLAND 1 |
100 |
|
|
|
|
VERMONT YANKEE 1 |
100 |
|
|
|
|
Unit |
Power |
Down |
Reason or Comment |
Change in report(*) |
Number of Scrams(#) |
BROWNS FERRY 1 |
0 |
03/03/1985 |
DEFUELED |
|
|
BROWNS FERRY 2 |
0 |
04/11/1999 |
EXITING REFUELING OUTAGE - NEAR POINT OF CRITICALITY |
* |
|
BROWNS FERRY 3 |
100 |
|
|
|
|
BRUNSWICK 1 |
100 |
|
|
|
|
BRUNSWICK 2 |
0 |
04/16/1999 |
REFUELING OUTAGE - FUEL RELOAD IN PROGRESS |
|
|
CATAWBA 1 |
0 |
04/21/1999 |
REFUELING OUTAGE - DEFUELED |
|
|
CATAWBA 2 |
0 |
05/03/1999 |
TS REQUIRED SHUTDOWN FROM 9% POWER ON 05/05/99 DUE TO BIOLOGICAL FOULING IN |
* |
|
CRYSTAL RIVER 3 |
85 |
|
HOLDING POWER AT THIS LEVEL TO PERFORM CIRCULATING PUMP MAINTENANCE |
|
|
FARLEY 1 |
100 |
|
|
|
|
FARLEY 2 |
49 |
|
OPERATING AT REDUCED POWER TO AVOID COASTDOWN DURING PEAK DEMAND PERIOD |
* |
|
HARRIS 1 |
100 |
|
|
|
|
HATCH 1 |
53 |
|
HOLDING POWER AT THIS LEVEL TO REPAIR A CIRCULATING WATER PUMP |
* |
|
HATCH 2 |
0 |
05/05/1999 |
AUTOMATIC REACTOR SCRAM FROM 98% MAXIMUM OPERATING POWER DUE TO A GENERATOR |
* |
1 |
MCGUIRE 1 |
100 |
|
|
|
|
MCGUIRE 2 |
100 |
|
|
|
|
NORTH ANNA 1 |
100 |
|
|
|
|
NORTH ANNA 2 |
100 |
|
|
|
|
OCONEE 1 |
100 |
|
|
|
|
OCONEE 2 |
100 |
|
|
|
|
OCONEE 3 |
100 |
|
|
|
|
ROBINSON 2 |
100 |
|
|
|
|
SAINT LUCIE 1 |
100 |
|
|
|
|
SAINT LUCIE 2 |
100 |
|
|
|
|
SEQUOYAH 1 |
100 |
|
|
|
|
SEQUOYAH 2 |
0 |
04/18/1999 |
EXITING REFUELING OUTAGE |
|
|
SUMMER 1 |
0 |
04/03/1999 |
EXITING REFUELING OUTAGE |
|
|
SURRY 1 |
100 |
|
|
|
|
SURRY 2 |
0 |
04/18/1999 |
REFUELING OUTAGE - DEFUELED |
|
|
TURKEY POINT 3 |
100 |
|
|
|
|
TURKEY POINT 4 |
100 |
|
|
|
|
VOGTLE 1 |
100 |
|
|
|
|
VOGTLE 2 |
100 |
|
|
|
|
WATTS BAR 1 |
100 |
|
|
|
|