Unit |
Power |
Down |
Reason or Comment |
Change in report(*) |
Number of Scrams(#) |
BRAIDWOOD 1 |
100 |
|
|
|
|
BRAIDWOOD 2 |
100 |
|
|
|
|
BYRON 1 |
100 |
|
|
|
|
BYRON 2 |
100 |
|
|
|
|
CLINTON 1 |
91 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
|
|
COOK 1 |
60 |
|
Power Operation REDUCING POWER TO ADD OIL TO AN RCP |
* |
|
COOK 2 |
100 |
|
|
|
|
DAVIS BESSE 1 |
0 |
02/15/2002 |
Refueling REFUELING OUTAGE - DEFUELED |
|
|
DRESDEN 2 |
95 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
|
|
DRESDEN 3 |
97 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
|
|
DUANE ARNOLD 1 |
94 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
|
|
FERMI 2 |
63 |
|
Power Operation INCREASING POWER |
* |
|
KEWAUNEE 1 |
100 |
|
|
|
|
LASALLE 1 |
100 |
|
|
|
|
LASALLE 2 |
76 |
|
Power Operation CONTROL ROD TESTING, TAKING A HEATER OUT OF SERVICE |
* |
|
MONTICELLO 1 |
100 |
|
|
|
|
PALISADES 1 |
100 |
|
|
|
|
PERRY 1 |
100 |
|
|
|
|
POINT BEACH 1 |
100 |
|
|
|
|
POINT BEACH 2 |
100 |
|
|
|
|
PRAIRIE ISLAND 1 |
100 |
|
|
|
|
PRAIRIE ISLAND 2 |
100 |
|
|
|
|
QUAD CITIES 1 |
97 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
|
|
QUAD CITIES 2 |
97 |
|
Power Operation 100% ELECTRICAL CAPABILITY |
|
|