Unit |
Power |
Down |
Reason or Comment |
Change in report (*) |
Number of Scrams (#) |
Arkansas Nuclear 1 |
100 |
|
|
|
|
Arkansas Nuclear 2 |
100 |
|
|
|
|
Callaway |
100 |
|
|
|
|
Columbia Generating Station |
66 |
|
INCREASING POWER TO 100% - RECIRC PUMP CONTROLLER PROBLEM - RECIRC PUMPS IN MANUAL |
* |
|
Comanche Peak 1 |
100 |
|
|
|
|
Comanche Peak 2 |
100 |
|
|
|
|
Cooper |
100 |
|
|
|
|
Diablo Canyon 1 |
100 |
|
230KV MORRO BAY-MIDWAY LINE OOS TIL MID MARCH - SITE CURRENTLY EXPERIENCING ADVERSE WEATHER |
* |
|
Diablo Canyon 2 |
99 |
|
COASTDOWN TO REFUELING OUTAGE - 230KV MORRO BAY-MIDWAY LINE OOS TIL MID MARCH - SITE CURRENTLY EXPERIENCING ADVERSE WEATHER |
* |
|
Fort Calhoun |
97 |
|
HOLDING POWER TO STABILIZE PLANT FOR MODERATOR TEMPERATURE COEFFICIENT TESTING |
* |
|
Grand Gulf 1 |
100 |
|
|
|
|
Palo Verde 1 |
100 |
|
PLANNED MAINTENANCE ON THE STARTUP TRANSFORMER - ESTIMATED COMPLETION 2/2/08. |
|
|
Palo Verde 2 |
100 |
|
PLANNED MAINTENANCE ON THE STARTUP TRANSFORMER - ESTIMATED COMPLETION 2/2/08. |
|
|
Palo Verde 3 |
100 |
|
PLANNED MAINTENANCE ON THE STARTUP TRANSFORMER - ESTIMATED COMPLETION 2/2/08. |
|
|
River Bend 1 |
0 |
01/06/2008 |
DEFUELED |
|
|
San Onofre 2 |
97 |
|
ADMINISTRATIVE LIMIT BASED ON STEAM GENERATOR LIMITATIONS |
* |
|
San Onofre 3 |
100 |
|
|
|
|
South Texas 1 |
100 |
|
|
|
|
South Texas 2 |
100 |
|
|
|
|
Waterford 3 |
100 |
|
|
|
|
Wolf Creek 1 |
100 |
|
|
|
|