Unit |
Power |
Down |
Reason or Comment |
Change in report (*) |
Number of Scrams (#) |
Browns Ferry 1 |
100 |
|
1 OF 7 500 KV TRANSMISSION LINES OOS FOR MAINTENANCE AND LIMESTONE INTERBANK TIE LINE OOS. |
|
|
Browns Ferry 2 |
100 |
|
1 OF 7 500 KV TRANSMISSION LINES OOS FOR MAINTENANCE AND LIMESTONE INTERBANK TIE LINE OOS. |
|
|
Browns Ferry 3 |
100 |
|
1 OF 7 500 KV TRANSMISSION LINES OOS FOR MAINTENANCE AND LIMESTONE INTERBANK TIE LINE OOS. |
|
|
Brunswick 1 |
100 |
|
|
|
|
Brunswick 2 |
71 |
|
PERFORMING ROD SEQUENCE EXCHANGE, MAINTENANCE AND SURVEILLANCES |
* |
|
Catawba 1 |
100 |
|
|
|
|
Catawba 2 |
75 |
|
HOLDING POWER FOR VOLTAGE REGULATOR TESTING |
* |
|
Crystal River 3 |
0 |
11/02/2007 |
REFUELING OUTAGE - DEFUELED |
|
|
Farley 1 |
100 |
|
|
* |
|
Farley 2 |
100 |
|
|
|
|
Harris 1 |
100 |
|
|
|
|
Hatch 1 |
96 |
|
ROD PATTERN ADJUSTMENT |
* |
|
Hatch 2 |
100 |
|
|
|
|
McGuire 1 |
100 |
|
|
|
|
McGuire 2 |
100 |
|
|
|
|
North Anna 1 |
100 |
|
|
|
|
North Anna 2 |
100 |
|
|
|
|
Oconee 1 |
100 |
|
|
|
|
Oconee 2 |
100 |
|
|
|
|
Oconee 3 |
0 |
10/26/2007 |
DEFUELED |
|
|
Robinson 2 |
100 |
|
|
|
|
Saint Lucie 1 |
100 |
|
|
|
|
Saint Lucie 2 |
0 |
09/30/2007 |
DEFUELED |
|
|
Sequoyah 1 |
14 |
|
TROUBLESHOOTING GENERATOR EXCITATION |
* |
|
Sequoyah 2 |
100 |
|
|
|
|
Summer |
100 |
|
|
* |
|
Surry 1 |
0 |
10/20/2007 |
REFUELING OUTAGE |
* |
|
Surry 2 |
100 |
|
|
|
|
Turkey Point 3 |
100 |
|
|
|
|
Turkey Point 4 |
100 |
|
|
|
|
Vogtle 1 |
97 |
|
100% ELECTRICAL CAPABILITY |
* |
|
Vogtle 2 |
98 |
|
100% ELECTRICAL CAPABILITY |
|
|
Watts Bar 1 |
100 |
|
|
|
|
Unit |
Power |
Down |
Reason or Comment |
Change in report (*) |
Number of Scrams (#) |
Braidwood 1 |
99 |
|
TROUBLESHOOTING 1B MAIN FEED PUMP CONTROLLER |
* |
|
Braidwood 2 |
100 |
|
|
|
|
Byron 1 |
100 |
|
|
|
|
Byron 2 |
100 |
|
|
|
|
Clinton |
97 |
|
100% ELECTRICAL CAPABILITY |
|
|
D.C. Cook 1 |
100 |
|
|
|
|
D.C. Cook 2 |
100 |
|
|
|
|
Davis-Besse |
97 |
|
DOWNPOWER DUE TO MTC TESTING |
* |
|
Dresden 2 |
0 |
10/28/2007 |
ROD PULL IN PROGRESS |
* |
|
Dresden 3 |
99 |
|
100% ELECTRICAL CAPABILITY |
|
|
Duane Arnold |
98 |
|
100% ELECTRICAL CAPABILITY |
|
|
Fermi 2 |
8 |
|
STARTUP IN PROGRESS |
* |
|
Kewaunee |
100 |
|
|
|
|
La Salle 1 |
79 |
|
DOWNPOWER DUE TO CONTROL ROD TESTING. UTILITY PLANS TO POWER UP FOLLOWING TESTING. COASTDOWN TO REFUELING OUTAGE |
* |
|
La Salle 2 |
100 |
|
|
|
|
Monticello |
100 |
|
|
|
|
Palisades |
100 |
|
|
|
|
Perry 1 |
100 |
|
|
|
|
Point Beach 1 |
96 |
|
HOLDING POWER FOR CROSS-OVER STEAM DUMP TESTING |
* |
|
Point Beach 2 |
100 |
|
|
|
|
Prairie Island 1 |
100 |
|
|
|
|
Prairie Island 2 |
100 |
|
|
|
|
Quad Cities 1 |
97 |
|
100% ELECTRICAL CAPABILITY |
|
|
Quad Cities 2 |
97 |
|
100% ELECTRICAL CAPABILITY |
* |
|