Home > Electronic Reading Room > Document Collections > Enforcement Documents > Notices of Enforcement Discretion > Power
Reactor Licensees > 00-6-008
NOED-00-6-008 - FitzPatrick (Power Authority
of the State of New York)
September 5, 2000
Mr. James Knubel
Chief Nuclear Officer
Power Authority of the State of New York
123 Main Street
White Plains, NY 10601
SUBJECT: |
NOTICE OF ENFORCEMENT DISCRETION FOR THE POWER AUTHORITY OF THE
STATE OF NEW YORK (PASNY) REGARDING THE FITZPATRICK NUCLEAR POWER
PLANT (TAC NO. MA9823, NOED NO. 00-6-008) |
Dear Mr. Knubel:
By letter dated August 28, 2000, you requested that the Nuclear Regulatory
Commission (NRC) exercise discretion not to enforce compliance with the
actions required in Technical Specifications (TSs) 3.0.D and 4.0.D. Your
letter documented information previously discussed with the NRC in a telephone
conference on August 27, 2000, at 9:10 p.m. The principal NRC staff members
who participated in that telephone conference included:
NRC, Office of Nuclear Reactor Regulation
E. Adensam, Director, Project Directorate I, Division of Licensing Project
Management
J. Strosnider, Director, Division of Engineering (DE)
B. Marcus, Electrical and Instrumentation and Controls Branch, DE
T. Tjader, Technical Specifications Branch, Division of Regulatory Improvement
Programs
NRC Region I (RI)
G. Meyer, Chief, Branch 3, RI
R. Crlenjak, Deputy Director, Division of Reactor Projects
R. Skokowski, RI
W. Lanning, Director, Division of Reactor Safety
Principal members of your staff participating were:
PASNY
D. Poulin, Licensing
J. Hoddy, Licensing
M. Abramski, Licensing
You stated at approximately 9:30 p.m. on August 27, 2000, that if the
plant had continued a controlled shutdown, PASNY would not have been in
compliance with TSs 3.0.D and 4.0.D which require entry into the startup
mode with all Limiting Conditions for Operations (LCOs) and surveillance
requirements associated with the LCOs being met. You requested that a
Notice of Enforcement Discretion (NOED) be issued pursuant to the NRC's
policy regarding exercise of discretion for an operating facility, set
out in Section VII.c of the "General Statement of Policy and Procedures
for NRC Enforcement Actions," (Enforcement Policy) NUREG-1600, and be
effective for the period of time it takes for the mode switch to be moved
from the run mode to the startup mode to the time all control rods are
manually inserted on August 27, 2000. This letter documents our telephone
conversation on August 27, 2000, at approximately 10:00 p.m. when we orally
issued this NOED. We understand that the condition causing the need for
this NOED was corrected, causing you to exit from the non-compliance on
August 27, 2000, soon after the telephone conversation in the time required
to change the mode switch from the run mode to the startup mode to the
time all control rods were manually inserted.
You stated that on August 27, 2000, at approximately 9:30 a.m. a controlled
shutdown was initiated due to a leak on a hydraulic control oil fitting
on the electro-hydraulic control (EHC) system for the main turbine and
a steam leak at the weld joint on the instrument line for the A reactor
feed pump. However, the following reactor protection system (RPS) trip
functions were considered inoperable because surveillance requirements
had not been satisfied:
- intermediate range monitor (IRM) high flux
- IRM inoperative
- average power range monitor (APRM neutron flux-startup)
To continue shutdown through the transition from the run mode to the
startup mode, the plant would not be in compliance with TSs 3.0.D and
4.0.D because the above RPS trip functions were inoperable. They were
inoperable because the surveillance requirements for these trip functions
specified in TS Table 4.1-1 and required in the refuel and startup modes,
had not been satisfied and could not be satisfied since the test equipment
to calibrate the instruments was offsite. Thus your staff estimated that
testing could not be completed until approximately 7:00 p.m. on August
28, 2000. It was your belief that compliance with TSs 3.0.D and 4.0.D
would have resulted in either:
- maintaining the plant in the run mode for an additional 18-hour period
to complete the surveillance testing required to satisfy the surveillance
requirements in TS Table 4.1-1 or,
- manually scramming the reactor and imparting a transient demand on
the EHC system.
Both options were considered undesirable because (1) it was prudent to
transition from the run mode to the startup mode as expeditiously as possible
because the time to complete failure of the EHC hydraulic control oil
pressure boundary was unknown, and (2) manually scramming the reactor
would adversely affect the degraded EHC system and, therefore, pose a
significant challenge to the main condenser as a heat sink.
The NRC staff has considered your response to each of the attributes
delineated in Section C.4 of Part 9900 of the NRC Inspection Manual
and verifies the following:
-
The TSs or other license conditions that will be violated.
-
You have requested a NOED granting permission to depart from the
requirements of TSs 3.0.D and 4.0.D (TS 4.0.D was not discussed
during the telecon on August 27, 2000, although the scope of the
discussion covered TS 4.0.D) and transition from the run mode to
the startup mode with the RPS trip functions for the intermediate
IRM high flux, IRM inoperative, and APRM neutron flux-startup inoperable.
-
The circumstances surrounding the situation, including root causes,
the need for prompt action, and identification of any relevant historical
events.
-
The circumstances surrounding the situation are discussed above.
The apparent root causes for the lack of calibrated equipment onsite
to support required surveillance testing are under investigation.
-
The safety basis for the request, including an evaluation of the
safety significance and potential consequences of the proposed course
of action. This evaluation should include at least a qualitative risk
assessment derived from the licensee's probabilistic risk analysis.
-
The safety bases for the request for the NOED are:
-
LCO 3.0.4 of the Improved Technical Specifications (ITS ), which
was submitted by letter dated March 19, 1999, and is currently
under NRC review, is similar to TS 3.0.D of the FitzPatrick TSs
with modifications that would preclude the situation addressed
in the request for the NOED. The ITS follows the guidance of the
boiling-water reactor Standard Technical Specifications.
-
You provided a quantitative assessment of risk for: (1) a turbine
trip with power conversion (turbine bypass valves/main condenser)
available and a loss of feedwater and (2) a turbine trip with
a loss-of-power conversion system (turbine bypass valves/main
condenser) and a loss of feedwater. You determined that operation
in the configuration you requested under the NOED resulted in
a reduction in risk. You also concluded that any increase in risk
due to transitioning modes with the inoperable trip functions
was acceptable based on the permission of this action in the ITS.
-
The basis for the licensee's conclusion that the noncompliance will
not be of potential detriment to the public health and safety and
that no significant hazards consideration is involved.
-
You represented that: (1) ITS LCO 3.0.4 is functionally equivalent
to the NOED version of TSs 3.0.D and 4.0.D as revised; and (2) the
change in ITS is considered an administrative change meeting the
intent of the current technical specifications, and is covered by
the generic no significant hazards evaluation for the ITS. The NRC
staff finds this acceptable because the intent of the TS was never
to preclude a normal plant shutdown as clarified in ITS Section
3.0.4.
-
The basis for the licensee's conclusion that the noncompliance will
not involve adverse consequences to the environment.
-
The nature of the noncompliance is such that none of the affected
plant equipment physically interfaces with the environment; therefore,
there is no environmental impact.
-
Any proposed compensatory measures.
-
No compensatory measures are required.
-
The justification for the duration of the noncompliance.
-
The request for the NOED is to allow transitioning from the run
mode to the startup mode with the RPS trip functions for the intermediate
IRM high flux, IRM inoperative, and APRM neutron flux-startup inoperable.
The duration of the non-compliance was, therefore, from the time
the mode switch was moved from the run mode to the startup mode
to the time all control rods were inserted. The basis for the request
was to allow a controlled shutdown by manually inserting the control
rods rather than manually scramming the reactor.
-
A statement that the request has been approved by the facility organization
that normally reviews safety issues (Plant Onsite Review Committee
(PORC), or its equivalent).
-
The FitzPatrick PORC has approved the request and recommended to
the Site Executive Officer approval of the request for the NOED.
-
The request must specifically address how one of the NOED criteria
for appropriate plant conditions specified in Section B is satisfied.
-
You have indicated that the NOED applies to Criterion B.2.1.a of
the NRC Inspection Manual, Part 9900. The NOED is intended
to avoid undesirable transients as a result of forcing compliance
with the license condition and, thus, minimize potential safety
consequences and operational risks.
- If a follow-up license amendment is required, the NOED request must
include marked-up TS pages showing the proposed TS changes. The actual
license amendment request must follow within 48 hours.
-
You indicated that a follow-up request for a license amendment
providing TS sections equivalent to the ITS would be submitted within
48 hours of the verbal request for the NOED. A request for amendment,
dated August 29, 2000, has been received.
- For NOEDs involving severe weather or other natural event, acceptability
of any increased radiological risk to the public and the overall public
benefit.
-
This NOED does not involve severe weather or other natural events.
On the basis of the staff's evaluation of your request, we have concluded
that the NOED was warranted because we are clearly satisfied that this
action involves minimal or no safety impact, is consistent with the enforcement
policy and the staff guidance, and has no adverse impact on public health
and safety. Therefore, it is our intention to exercise discretion not
to enforce compliance with TSs 3.0.D and 4.0.D for the period from August
27, 2000, at 10:00 p.m. until issuance of a license amendment, which was
submitted by letter dated August 29, 2000. You actually exited the conditions
requiring the NOED on August 27, 2000, shortly after 10:00 p.m. The requested
amendment was not provided under exigent circumstances with justification
for the exigency and, therefore, you need to supplement the amendment
request with the necessary justification. The staff plans to complete
its review and issue the license amendment within 4 weeks of the issuance
of the NOED.
As stated in the Enforcement Policy, action will be taken, to the extent
that violations were involved, for the root cause that led to the noncompliance
for which this NOED was necessary.
|
Sincerely,
/RA/
Elinor G. Adensam, Director
Project Directorate I
Division of Licensing Project Management
Office of Nuclear Reactor Regulation
|
Docket No. 50-333
James A. FitzPatrick Nuclear Power Plant
cc:
Mr. Gerald C. Goldstein
Assistant General Counsel
Power Authority of the State of New York
1633 Broadway
New York, NY 10019
Mr. F. William Valentino, President
New York State Energy, Research, and Development Authority
Corporate Plaza West
286 Washington Avenue Extension
Albany, NY 12203-6399
Resident Inspector's Office
U. S. Nuclear Regulatory Commission
P.O. Box 136
Lycoming, NY 13093
Mr. Richard L. Patch, Director
Quality Assurance
Power Authority of the State of New York
123 Main Street
White Plains, NY 10601
Mr. Harry P. Salmon, Jr.
Vice President - Engineering
Power Authority of the State of New York
123 Main Street
White Plains, NY 10601
Mr. Gerard Goering
28112 Bayview Drive
Red Wing, MN 55066
Ms. Charlene D. Faison
Director Nuclear Licensing
Power Authority of the State of New York
123 Main Street
White Plains, NY 10601
Mr. James Gagliardo
Safety Review Committee
708 Castlewood Avenue
Arlington, TX 76012
Supervisor
Town of Scriba
Route 8, Box 382
Oswego, NY 13126
Mr. Arthur Zaremba, Licensing Manager
James A. FitzPatrick Nuclear Power Plant
P.O. Box 41
Lycoming, NY 13093
Mr. Eugene W. Zeltmann
President and Chief Operating Officer
Power Authority of the State of New York
30 South Pearl Street
Albany, NY 12207-3425
Mr. Paul Eddy
New York State Dept. of Public Service
3 Empire State Plaza, 10th Floor
Albany, NY 12223
Charles Donaldson, Esquire
Assistant Attorney General
New York Department of Law
120 Broadway
New York, NY 10271
Michael J. Colomb
Site Executive Officer
James A. FitzPatrick Nuclear Power Plant
P.O. Box 41
Lycoming, NY 13093
Regional Administrator, Region I
U.S. Nuclear Regulatory Commission
475 Allendale Road
King of Prussia, PA 19406
Oswego County Administrator Jack Tierney
46 East Bridge Street
Oswego, New York 13126
|