GL79061 

                               UNITED STATES 
                       NUCLEAR REGULATORY COMMISSION 
                          WASHINGTON, D. C. 20555 

                             November 9, 1979 

               TO ALL PENDING CONSTRUCTION PERMIT APPLICANTS 

Gentlemen: 

SUBJECT: DISCUSSION OF LESSONS LEARNED SHORT TERM REQUIREMENTS 

On October 10, 1979, you received a letter which defined a set of "short 
term" requirements resulting from the NRC staff investigations of the TMI 
accident. Since the letter was issued, the staff has further defined these 
requirements. 

Enclosure 1 provides the additional clarifications of the NRC staff 
requirements as provided to licensees of operating reactors. Enclosure 2 
provides a list of modifications to these clarifications to make them 
applicable to duplicants for operating licenses, applicants for construction
permits and licensees of plants under construction. It should be noted that 
the intent of these requirements and the purpose of our letter of October 
10, 1979 have not changed. 

If you have any questions regarding these actions, please contact the NRC 
Project Manager for your facility. 

                                        Sincerely, 



                                        D. B. Vassallo, Acting Director 
                                        Division of Project Management 
                                        Office of Nuclear Reactor Regulation

Enclosure:
Discussion of TMI Lessons Learned 
Short Term Requirements

ccs:
Service List 


                             UNDER CP REVIEW 

1.   Pilgrim                            Boston Edison 

2.   Greenwood                          Detroit Edison 

3.   Perkins                            Duke Power 

4.   Allens Creek                       Houston Lighting & Power 

5.   New England                        New England Power & Light 

6.   Montague                           Northeast Nuclear Energy 

7.   New Haven                          NY State Electric & Gas 

8.   Erie                               Ohio Edison 

9.   Pebble Springs                     Portland General Electric 

10.  Clinch River                       Project Management Corp. /TVA 

11.  Black Fox                          Public Service of Oklahoma 

12.  Skagit                             Puget Sound Power & Light 

13.  Davis Besse 2/3                    Toledo Edison 

14.  Haven                              Wisconsin Electric Power 

15.  Greene County                      Power Authority of the State of NY 

16.  FNP                                Offshore Power 


                        CONSTRUCTION PERMIT APPLICATION 

                         Pressurized Water Reactors 

                              50-452/453 

                              50-471 

                              50-488/489/490 

                              50-500/501 

                              50-502 

                              50-514/515 

                              50-568/569 

                              50-580/581 

                              50-596/597 

                              50-537 

                              50-549 

                              50-437 


                     CONSTRUCTION PERMIT APPLICATION 

                          Boiling Water Reactors 

                              50-466 

                              50-496/497 

                              50-522/523 

                              50-556/557