May 17, 2006
MEMORANDUM TO: |
Luis A. Reyes
Executive Director for Operations |
FROM: |
Annette L. Vietti-Cook, Secretary /RA/ |
SUBJECT: |
STAFF REQUIREMENTS - SECY-06-0065 - OFFICE OF THE
INSPECTOR GENERAL RECOMMENDATIONS ON
DECOMMISSIONING FUNDING ASSURANCE |
The Commission has approved the staff recommendation that no changes are needed at this
time with regard to verification of trust balances by trustees or requirements for specific
investment restrictions on decommissioning trust funds. The staff should provide to the
Commission a more detailed discussion of decommissioning trust fund balance and investment
oversight activities conducted by the Federal Energy Regulatory Commission, State Public
Utility Commissions, and other organizations, as appropriate. If necessary and agreeable to the
aforementioned organizations, the staff should hold a public workshop with these organizations
to collect this information. The staff should provide a discussion of these oversight activities
along with recommendations for further Commission action, if appropriate, no later than the next
Commission paper summarizing decommissioning funding status reports for nuclear power
reactors.
In the future (circa 2011) when more cost return information is available, NRR should review the
formula used for decommissioning funding requirements and adjust it, if necessary.
cc: |
Chairman Diaz
Commissioner McGaffigan
Commissioner Merrifield
Commissioner Jaczko
Commissioner Lyons
OGC
CFO
OCA
OPA
Office Directors, Regions, ACRS, ACNW, ASLBP (via E-Mail)
PDR |
|