THURSDAY, FEBRUARY 5,
2004, CONFERENCE ROOM T-2B3, TWO WHITE FLINT NORTH, ROCKVILLE, MARYLAND |
|
1) |
8:30 - 8:35 A.M. |
Opening Remarks by the ACRS Chairman
(Open) |
|
|
1.1) Opening Statement (MVB/JTL/SD) |
|
|
1.2) Items of current interest (MVB/SD) |
|
|
|
2) |
8:35 - 10:30 A.M. |
ESBWR Design - Thermal-Hydraulic Issues (Open/Closed)
(GBW/RC) |
|
2.1) Remarks by the Subcommittee Chairman |
|
2.2) Briefing by and discussions with representatives of the NRC staff
on the use of the TRAC-G computer code to perform analyses of the Economic
Simplified Boiling Water Reactor (ESBWR) design. |
|
|
|
[NOTE: A portion of this session may be closed to discuss
General Electric proprietary information applicable to this matter.] |
|
10:30 - 10:45 A.M. |
***BREAK*** |
3) |
10:45 - 11:45 A.M. |
South Texas Project Cause Investigation of the Reactor Vessel Bottom
Mounted Penetration Leakage (Open) (JDS/MWW) |
|
|
3.1) Remarks by the Subcommittee Chairman |
|
|
3.2) Briefing by and discussions with representatives of the NRC staff
regarding the South Texas Project investigation of the
cause of the leakage from reactor vessel bottom mounted penetration. |
|
|
|
|
|
Representatives of the nuclear industry may provide their views, as appropriate. |
|
11:45 - 12:45 P.M. |
***LUNCH*** |
4) |
12:45 - 2:45 P.M. |
Resolution of Certain Items Identified by the ACRS in NUREG-1740
Related to the Differing Professional Opinion (DPO) on Steam Generator Tube
Integrity (Open) (FPF/GBW/BPJ) |
|
|
4.1) Remarks by the Subcommittee Chairman |
|
|
4.2) Briefing by and discussions with representatives of the NRC staff
regarding the staff’s resolution of certain items identified by the
ACRS in NUREG-1740, “Voltage-Based Alternative Repair Criteria,”
related to the DPO on steam generator tube integrity, as well as the status
of resolution of the remaining items. |
|
2:45 - 3:00 P.M. |
***BREAK*** |
5) |
3:00 - 4:00 P.M. |
Evaluation of the Effectiveness (Quality) of the NRC Safety Research
Programs (Open) (DAP/SD/HPN)
Discussion of a proposed approach for the ACRS evaluation of the effectiveness
(quality) of the NRC Safety Research Programs. |
|
|
|
|
|
Representatives of the NRC staff may participate, as appropriate. |
|
|
|
6) |
4:00 - 7:00 P.M. |
Preparation of ACRS Reports (Open) |
|
|
6.1) ESBWR Design - Thermal-Hydraulic Issues (GBW/RC) |
|
|
6.2) Resolution of Certain Items Identified in NUREG-1740 Related to DPO
on Steam Generator Tube Integrity (FPF/GBW/BPJ) |
|
|
6.3) NRC Safety Research Program Report (DAP/SD/HPN) |
FRIDAY, FEBRUARY 5,
2004, CONFERENCE ROOM T-2B3, TWO WHITE FLINT NORTH, ROCKVILLE, MARYLAND |
|
|
|
7) |
8:30 - 8:35 A.M. |
Opening Remarks by the ACRS Chairman
(Open) (MVB/JTL/SD) |
|
|
|
8) |
8:35 - 12:30 P.M. |
ACRS Report on the NRC Safety Research Program (Open) (DAP/SD/HPN) |
|
|
8.1) Remarks by the Subcommittee Chairman |
|
|
8.2) Discussion of the draft ACRS report to the Commission on the NRC
Safety Research Program. |
|
12:30 - 1:30 P.M. |
***LUNCH*** |
9) |
1:30 - 2:00 P.M. |
Subcommittee Report - ACR-700 Design (Open) (TSK/MME)
Report by and discussions with the Chairman of the ACRS Subcommittee on
Future Plant Designs regarding the Subcommittee’s review of the design
features of the ACR-700 design and related matters. |
|
|
|
10) |
2:00 - 3:00 P.M. |
Future ACRS Activities/Report of the Planning and Procedures Subcommittee
(Open) (MVB/JTL/SD) |
|
|
10.1) Discussion of the recommendations of the Planning and Procedures
Subcommittee regarding items proposed for consideration by the full Committee
during future ACRS meetings. |
|
|
10.2) Report of the Planning and Procedures Subcommittee on matters related
to the conduct of ACRS business, including anticipated workload and member
assignments. |
|
|
|
11) |
3:00 - 3:15 P.M. |
Reconciliation of ACRS Comments and Recommendations (Open) (MVB,
et al./SD, et al.)
Discussion of the responses from the NRC Executive Director for Operations
to comments and recommendations included in recent ACRS reports and letters. |
|
3:15 - 3:30 P.M. |
***BREAK*** |
12) |
3:30 - 7:00 P.M. |
Preparation of ACRS Reports (Open)
Discussion of the proposed ACRS reports on: |
|
|
12.1) ESBWR Design - Thermal-Hydraulic Issues (GBW/RC) |
|
|
12.2) Resolution of Certain Items Identified in NUREG-1740 Related to
DPO on Steam Generator Tube Integrity (FPF/GBW/BPJ) |
|
|
12.3) NRC Safety Research Program Report (DAP/SD/HPN) |
SATURDAY,
FEBRUARY 7, 2004, CONFERENCE ROOM T-2B3, TWO WHITE FLINT NORTH, ROCKVILLE,
MARYLAND |
13) |
8:30 - 12:00 Noon |
Preparation of ACRS Reports (Open)
The Committee will continue discussion of the proposed ACRS reports listed
under Item 12. |
|
|
|
14) |
12:00 - 12:30 P.M. |
Miscellaneous (Open) (MVB/JTL)
Discussion of matters related to the conduct of Committee activities and
matters and specific issues that were not completed during previous meetings,
as time and availability of information permit. |