ADVISORY COMMITTEE ON REACTOR SAFEGUARDS
SEVERE ACCIDENT MANAGEMENT SUBCOMMITTEE MEETING
CEOG PASS MODIFICATIONS/CONTROL ROOM HABITABILITY ISSUES
SEPTEMBER 16-17, 1999
ROCKVILLE, MARYLAND

PRESENTATION SCHEDULE




 

Contact: P. Boehnert: 301/415-8065



September 16, 1999



TOPIC                		   SPEAKER    			   TIME

                                                  

I.   Introduction                  T. Kress, ACRS              	1:00 p.m.



II.  Combustion Engineering Owners                         	1:15p.m.-5:00 p.m.

     Group Proposed Modifications

     to PASS Requirements



     A. CE Owners Group            R. Snider, ABB,

        Presentation                  et al.



     B. NRC Staff Presentation     J. O'Brien, NRR,

                                   et al.



III. Subcommittee Caucus                               		5:00 - 5:15 p.m.



     . Follow-on Issues

     . Future Actions

     . Decision to Bring Matter

         to ACRS for Review



IV. Recess                                             		5:15 p.m. 



September 17, 1999



V.  Reconvene                                     		8:30 a.m.



VI. NRC Staff Actions Related      J. Hayes, NRR       		8:40 - 10:00 a.m.

    To Control Room Habitability



     . Issue Identification

     . Staff Position(s)

     . Actions Underway/Planned

     . Schedule Milestones



                    	  BREAK               			10:00 - 10:15 a.m.



VII. Nuclear HVAC Utility Group    R. Campbell (TVA)        	10:15 - 11:00 a.m. 

     (NHUG)



     . Introduction

     . NHUG Charter and Activities

     . Control Room Integrity Actions

     . Conclusions/Recommendations



VIII. Control Room Leak Testing

      A. Vendor Leak Testing       P. Lagus (Lagus          	11:00 - 12:00 p.m.

	 Activities		   Technologies)



      . Tracer Gas Testing



                                 LUNCH            		12:00 - 1:00 p.m.



      B. Utility Leak Testing  	   D. Adams (Comm. Ed.)     	1:00 - 2:30 p.m

	 Program		   et al.

      . Test Results and 

	Utilization



                                   BREAK               		2:30 - 2:45 p.m.







IX.  NEI Presentation              K. Cozens, NEI      		2:45 - 3:30 p.m



     . NEI Report: "Control Room

       Habitability Assessment Guidance"



X. Subcommittee Caucus                                 		3:30 - 3:45 p.m.



     . Follow-on Issues

     . Future Actions

     . Decision to Bring Matter

       to ACRS for Review



XI. Adjourn                                            		3:45 p.m.