Morning Report for December 8, 1999

                       Headquarters Daily Report

                         DECEMBER 08, 1999

***************************************************************************
                    REPORT             NEGATIVE            NO INPUT
                    ATTACHED           INPUT RECEIVED      RECEIVED

HEADQUARTERS                           X                   
REGION I            X                                      
REGION II                              X                   
REGION III          X                                      
REGION IV                              X                   
PRIORITY ATTENTION REQUIRED  MORNING REPORT - REGION I  DEC. 08, 1999

Licensee/Facility:                     Notification:

Northeast Utilities                    MR Number: 1-99-0047
Millstone 1 2 3                        Date: 12/08/99
Waterford,Connecticut                  SRI PC                             
Dockets: 50-245,50-336,50-423
BWR/GE-3,PWR/CE,PWR/W-4-LP            

Subject: MANAGEMENT CHANGES                                              

Discussion:

Mr. Dave Amerine, Vice President of Engineering Services, announced that 
he would be leaving Millstone to accept a new position as Chief Operating
Officer at Morris-Knudson Westinghouse Government Services. Mr. Ray      
Necci, Vice President of Nuclear Oversight and Regulatory Affairs, will  
succeed Mr. Amerine. Mr. Steve Scace, Director of Nuclear Oversight, will
add Regulatory Affairs to his responsibilities, and become the Director  
of Nuclear Oversight and Regulatory Affairs.                             

Regional Action:

This Is For Informational Purposes Only.                                 

Contact:  Richard Urban              (610)337-5271
          James Linville             (610)337-5129
_
REGION III  MORNING REPORT     PAGE  2          DECEMBER  8, 1999

Licensee/Facility:                     Notification:

Michigan Electric Co.                  MR Number: 3-99-0099
Cook 2                                 Date: 12/06/99
Bridgman,Michigan                      SRI VIA TELECON                    
Dockets: 50-316
PWR/W-4-LP                            

Subject: RESTART SCHEDULE CHANGES AT DC COOK                             

Discussion:

The licensee announced today the following revised dates for Unit 2      
return to power. Core re-load will begin February 11, 2000. The licensee 
plans to take the unit critical on March 10, 2000. The licensee          
anticipates that full power will be achieved on March 20, 2000.          
Contributing to the approximate 1 month delay in the unit restart        
schedule were delays in the completion of several modifications,         
motor-operated valve testing and repair, and bulk work activities.       

Regional Action:

Information only.                                                        

Contact:  D. PASSEHL                 (630)829-9872
_