Morning Report for December 6, 1999

                       Headquarters Daily Report

                         DECEMBER 06, 1999

***************************************************************************
                    REPORT             NEGATIVE            NO INPUT
                    ATTACHED           INPUT RECEIVED      RECEIVED

HEADQUARTERS                           X                   
REGION I            X                                      
REGION II                              X                   
REGION III                             X                   
REGION IV                              X                   
PRIORITY ATTENTION REQUIRED  MORNING REPORT - REGION I  DEC. 06, 1999

Licensee/Facility:                     Notification:

Duquesne Light Co.                     MR Number: 1-99-0046
Beaver Valley 1 2                      Date: 12/06/99
Shippingport,Pennsylvania                                                 
Dockets: 50-334,50-412
PWR/W-3-LP,PWR/W-3-LP                 

Subject: FIRSTENERGY/DUQUESNE LIGHT COMPANY ASSET TRANSFER               

Discussion:

The proposed asset transfer between FirstEnergy Corporation and Duquesne 
Light Company was closed and became effective Friday afternoon, December 
3, 1999.  Conforming license amendments were issued that afternoon for   
Beaver Valley Power Station, Units 1 and 2 (BVPS).  These license        
amendments were follow-ups to the Orders issued on September 30, 1999,   
pursuant to 10 CFR 50.80, approving the associated license transfers.    
Highlights of the license transfers included:                            
                                                                         
-  Duquesne Light's interests in BVPS have been transferred to           
Pennsylvania Power.  As a result, FirstEnergy subsidiaries now own 100   
percent of BVPS.                                                         
                                                                         
-  Operating authority of BVPS has been transferred from Duquesne Light  
Company to FirstEnergy Nuclear Operating Company.                        
                                                                         
The asset transfer agreement, which was submitted for staff approval on  
May 5, 1999, resulted in the transfer of Duquesne Light's partial        
interests in 1,436 MW at eight generating units (both fossil and nuclear)
to FirstEnergy subsidiaries in exchange for 1,328 MW at three fossil     
power plants.                                                            

Regional Action:

The resident inspector is on site monitoring licensee activities.        

Contact:  Peter Eselgroth            (610)337-5234
          David Kern                 (724)643-2000