Morning Report for October 27, 1999

                       Headquarters Daily Report

                         OCTOBER 27, 1999

***************************************************************************
                    REPORT             NEGATIVE            NO INPUT
                    ATTACHED           INPUT RECEIVED      RECEIVED

HEADQUARTERS                           X                   
REGION I                               X                   
REGION II                              X                   
REGION III          X                                      
REGION IV                              X                   
PRIORITY ATTENTION REQUIRED  MORNING REPORT - REGION III  OCTOBER 27, 1999

Licensee/Facility:                     Notification:

Commonwealth Edison Co.                MR Number: 3-99-0088
Dresden 2                              Date: 10/27/99
Morris,Illinois                        E-Mail from RIO                    
Dockets: 50-237
BWR/GE-3                              

Subject: Plant Startup Following Refueling Outage                        

Discussion:

On October 27, 1999, Dresden station personnel synchronized the Unit 2   
main generator to the electrical grid, ending a planned refueling outage.
The outage officially commenced on October 1, 1999. Following completion 
of planned outage activities, operators commenced a reactor startup on   
October 26, 1999; the reactor was made critical later that day and the   
main generator synchronized the next day. The outage duration of 25 days 
and 12 hours sets a ComEd record for the shortest duration refueling     
outage. Major activities accomplished during the outage included: noble  
metals injection, oscillating power range monitor modification           
installation, chemical cleaning of the main condenser, 2A reactor        
recirculation pump motor replacement, overhaul of the 2B low pressure    
turbine, main generator hydrogen seal replacement, and bulk outage work. 

Regional Action:

The resident inspection staff monitored portions of the startup and power
ascension activities. The residents monitored the plant outage           
activities.                                                              

Contact:  M. Ring                    (630)829-9703