Headquarters Daily Report
REGION I
Pilgrim Manual Reactor Shutdown.
Licensee/Facility:
ENTERGY NUCLEAR GENERATION COMPANY
Pilgrim 1
PLYMOUTH, Massachusetts
Dockets: 05000293
[1] GE-3
License No:
|
Notification:
MR Number: 1-2007-0008
Date: 03/17/2007
Call from Licensee
|
Discussion:
On March 17, 2007, the Pilgrim reactor was manually shutdown due to increasing unidentified drywell leakage.
Upon drywell entry, a steam leak was identified from the packing of a 6-inch reactor water cleanup valve. The
valve was repacked and will be tested during plant heatup/pressurization. Startup commenced at approximately
6:00 a.m. on March 19, 2007.
Accession Numbers:
Accession No |
Accession Date |
ML070780524 |
03/19/2007 |
Contacts:
Name |
Office Abbrev |
Phone No |
E-Mail |
POWELL, RAYMOND J |
R1 |
(610) 337-6967 |
RJP@nrc.gov |
|