                         JUNE 02, 2000

***************************************************************************
                    REPORT             NEGATIVE            NO INPUT
                    ATTACHED           INPUT RECEIVED      RECEIVED

HEADQUARTERS                           X                   
REGION I            X                                      
REGION II                              X                   
REGION III                             X                   
REGION IV                              X                   
PRIORITY ATTENTION REQUIRED  MORNING REPORT - REGION I  JUNE  2, 2000

Licensee/Facility:                     Notification:

Maine Yankee Atomic Power Co.          MR Number: 1-00-0008
Maine Yankee 1                         Date: 06/02/00
Wiscasset,Maine                                                           
Dockets: 50-309
PWR/CE                                

Subject: MAINE YANKEE LOADS TWO STEAM GENERATORS ONTO BARGE IN           
         PREPARATION FOR SHIPMENT TO GTS DURATEK IN MEMPHIS, TN          


Discussion:

On June 1, 2000, Maine Yankee completed the transport and loading of     
steam generators Nos. 1 and 3 onto a barge in preparation for shipment to
and processing of the components at the GTS DURATEK facility in Memphis, 
TN.  Maine Yankee's health physics staff maintained appropriate access   
controls during the transport and the barge loading was completed without
incident.  In preparation for the shipment, Maine Yankee drained the     
steam generators, sealed all penetrations, and applied a weather         
resistant protective coating to the external surfaces.  Final            
preparations for shipment will include installation of structural        
supports, shielding, tie-downs and personnel barriers.  Maine Yankee's   
transportation plan requires each barge and tow service tug to be        
inspected and surveyed by a qualified marine inspection contractor prior 
to transport.  Each steam generator transport package is estimated to    
weigh approximately 500 tons.  Maine Yankee requested and received       
approval from the United States Coast Guard (USCG) to establish a Marine 
Safety Zone for the transport, which restricts access in a 200-yard      
radial area around the barge to authorized persons, vehicles, or vessels.
The anticipated water transit route is approximately 2,750 miles,        
starting at the plant's barge slip and ending at the Port of Memphis     
Facility.  Barge shipment of steam generators 1 and 3 is scheduled to    
begin in early to mid-June 2000, followed by barge shipment of steam     
generator No. 2 and the reactor pressurizer scheduled to begin in        
late-June 2000.                                                          
                                                                         
Representatives from Maine's Department of Environmental Protection have 
also been involved in monitoring preparations for shipment of the steam  
generators and the pressurizer.  The USCG will monitor the water transit 
phase of the steam generator shipment.                                   

Regional Action:

NRC staff reviewed preparations for shipment, observed barge loading, and
will continue to review preparations for shipment.                       

Contact:  R. Bellamy                 (610)337-5200
          M. Roberts                 (610)337-5094