Morning Report for February 3, 2000

                       Headquarters Daily Report

                         FEBRUARY 03, 2000

***************************************************************************
                    REPORT             NEGATIVE            NO INPUT
                    ATTACHED           INPUT RECEIVED      RECEIVED

HEADQUARTERS                           X                   
REGION I            X                   
REGION II           X                                      
REGION III                             X                   
REGION IV                              X                   
PRIORITY ATTENTION REQUIRED  MORNING REPORT - REGION I  FEB. 03, 2000

Licensee/Facility:                     Notification:

Connecticut Yankee Atomic Power Co.    MR Number: 1-00-0001
Haddam Neck 1                          Date: 02/03/00
Hartford,Connecticut                                                      
Dockets: 50-213
PWR/W-4-LP                            

Subject: STAND-DOWN AT HADDAM NECK TO IMPROVE WORKER AWARENESS           

Discussion:

On February 2, 2000, Bechtel, the Decommissioning Operations Contractor  
for the Haddam Neck facility, stopped decommissioning work activities    
controlled by radiation work permits to conduct a review of work         
practices.  The work stoppage was in response to four incidents in the   
last few days in which workers proceeded with decommissioning activities 
before appropriate health physics clearances had been received. The      
licensee stated that this equipment removal work was not conducted       
consistent with management expectations.  Although most of these         
incidents are of minor safety significance, one event caused an unplanned
uptake of radioactive material resulting in a very low internal exposure 
to one individual.  As of today (February 3) Bechtel has conducted an all
hands meeting to review the work practices and has conducted feedback    
sessions with its foremen and work crews.  Work will not resume until    
worker feedback is evaluated and Bechtel has developed a corrective      
action plan.  Connecticut Yankee management will review the corrective   
action plan prior to authorizing resumption of work activities.   Most   
work is anticipated to resume by next week.                              
                                                                         
The licensee provided a courtesy notification to the NRC and also plans  
to highlight their actions in their daily newsletter.  NRC informed the  
State of Connecticut.  A State representative was present onsite and     
observed the licensee's initial response to the internal contamination   
incident.                                                                

Regional Action:

NRC will review this matter as part of its routine inspection program    
scheduled for next week.                                                 

Contact:  Ronald R. Bellamy          (610)337-5200
          John Wray                  (610)337-5268
_
REGION II  MORNING REPORT     PAGE  2          FEBRUARY  3, 2000

Licensee/Facility:                     Notification:

Georgia Power Co.                      MR Number: 2-00-0007
Vogtle 1 2                             Date: 02/03/00
Waynesboro,Georgia                                                        
Dockets: 50-424,50-425
PWR/W-4-LP,PWR/W-4-LP                 

Subject: MANAGEMENT CHANGES AT SOUTHERN NUCLEAR OPERATING COMPANY, INC.  

Discussion:

Southern Nuclear Operating Company, Inc. (SNC) announced the following   
management changes at Plant Vogtle:  Steve Chesnut, Assistant General    
Manager, Operations, has been selected for a position, as a loaned       
employee to the Institute of Nuclear Power Operations. George Frederick, 
Manager, Operations, will replace Mr. Chesnut as Assistant General       
Manager, Operations.  Sonny Bargeron, Unit 2 Superintendent, will replace
Mr. Frederick as Manager, Operations.                                    
                                                                         
These changes were effective on January 22, 2000.                        

Regional Action:

For information only.                                                    

Contact:  C. Rapp                    (404)562-4674