Milestone |
Schedule |
Actual |
Receive License Renewal (LR) Application |
4/30/07 |
4/30/07 |
Federal Register Notice (FRN) Published - Receipt &
Availability |
5/14/07 |
5/11/07 |
Public Meeting - LR Overview |
6/27/07 |
6/27/07 |
FRN Published - Notice of Acceptability/Opportunity for
Hearing |
8/1/07 |
8/1/07 |
FRN Published - Notice of Intent to Conduct Environmental
Scoping |
8/10/07 |
8/10/07 |
Audit - Aging Management Programs (AMPs/TLAAs) |
8/27-31/07 |
8/27-31/07 |
Audit - Environmental |
9/10-13/07
9/24-27/07 |
9/10-13/07 |
Public Meeting - Environmental Scoping |
9/19/07 |
9/19/07 |
Audit - Scoping & Screening Methodology |
10/9-12/07 |
10/9-12/07 |
Environmental Scoping Period Ends |
10/12/07 |
10/12/07 |
Audit - Aging Management Reviews (AMRs) |
10/22-26/07 |
10/22-26/07 |
Audit - 3rd AMP/TLAA/AMR |
11/27-29/07 |
11/27-29/07 |
Deadline for Filing Hearing Requests and Petitions for
Intervention |
11/30/07 |
11/30/07 |
Environmental Requests for Additional Information (RAIs)
Issued |
12/10/07 |
12/05/07 |
Environmental RAIs - Response Received |
1/14/08 |
1/5/08-3/07/08 |
Inspection - Scoping Screening/AMP |
1/28-2/1/08
2/11-15/08 |
1/28-2/1/08
2/11-15/08 |
Audit - 4th Optional AMP/TLAA/AMR |
2/19-21/08 |
2/19-21/08 |
Safety RAIs - Issued |
3/28/08 |
5/28/08 |
Safety RAI - Responses Received |
4/28/08 |
6/26/08 |
Entergy Commitment to install SBO/Appendix R Diesel Generator for
Unit 2 |
4/30/08 |
4/30/08 |
Inspection - Scoping Screening/AMP - Exit Meeting |
6/18/08 |
6/18/08 |
Draft Supplemental Environment Impact Statement (SEIS) Issued |
12/12/08 |
|
FRN Published - Availability/Comment on draft SEIS |
12/19/08 |
|
Safety Evaluation Report (SER) with Open Item(s) - Issued |
1/5/09 |
|
Public Meeting - draft SEIS |
2/09 |
|
ACRS Subcommittee Meeting on SER with Open Item(s) |
3/09 |
|
SER Open Item(s) - Response(s) Received |
3/2/09 |
|
End of Draft SEIS Comment Period |
3/4/09 |
|
Inspection - Final Optional |
TBD |
|
SER - Issued |
7/27/09 |
|
ACRS Full Committee Meeting on SER |
9/09 |
|
Final SEIS - Issued (based on anticipated comments) |
2/12/10 |
|
FRN Published - Availability of Final SEIS |
2/19/10 |
|
Commission Decision (hearing pending) |
TBD |
|