Prairie Island Nuclear Generating Plant, Units 1 and 2 - License Renewal Application
|
Milestones | Schedule Date | Actual Date |
---|---|---|
Receive License Renewal (LR) Application |
4/15/08 |
4/15/08 |
Federal Register Notice (FRN) Published- Receipt & Availability |
05/31/08 |
05/06/08 |
FRN Published - Acceptability/Opportunity for Hearing |
06/13/08 |
06/17/08 |
FRN Published - Notice of Intent to Conduct Environmental Scoping |
06/17/08 |
07/22/08 |
Public Meeting - Process Overview and Environmental Scoping | 07/30/08 |
07/30/08 |
On-site Audit - Scoping & Screening Methodology |
08/04/08 |
08/04/08 |
Deadline for Filing Hearing Requests and Petitions for Intervention |
08/13/08 |
08/18/08 |
On-site Audit - Environmental |
08/18/08 |
|
Environmental Scoping Period Ends |
09/22/08 |
|
On-site Audit - Aging Management |
09/08/08 |
|
Environmental Requests for Additional Information (RAIs) Issued |
09/24/08 |
|
Environmental RAIs - Response Received |
10/24/08 |
|
Safety RAIs - Issued |
11/15/08 |
|
Safety RAI - Responses Received |
12/14/08 |
|
Inspection - Regional |
TBD |
|
Public Exit Meeting - Regional Inspections |
TBD |
|
Draft Supplemental Environmental Impact Statement (SEIS) - Issued |
03/11/09 |
|
EPA FRN Published - Availability / Comment on draft SEIS |
03/20/09 |
|
End of draft SEIS Comment Period |
06/05/09 |
|
Public Meeting - draft SEIS |
04/22/09 |
|
Safety Evaluation Report (SER) with Open Items - Issued |
05/15/09 |
|
Inspection - Final Optional |
TBD |
|
ACRS Subcommittee Meeting on SER with Open Items |
07/09 |
|
SER with Open Items - Responses Received |
07/15/09 |
|
SER - Issued | ||
Final SEIS - Issued | ||
EPA FRN Published - Availability of Final SEIS | ||
ACRS Full Committee Meeting on SER | ||
Decision Director NRR - Approval (22 months if no hearing) | ||
Commission decision (if hearing is granted - 30 months) |
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
Prairie Island Nuclear Generating Plant Project Managers | |
---|---|
License Renewal | Rick Plasse |
Lead Power Plant | Mac Chawla |