Milestones | Schedule Date | Actual Date |
---|---|---|
Receive License Renewal (LR) Application | 06/29/07 | 06/29/07 |
FRN Published - Acceptability and Opportunity for Hearing | 08/21/07 | 08/21/07 |
Public Meeting - LR Overview | 08/21/07 | 08/21/07 |
FRN Published - Notice of Intent to Conduct Environmental Scoping | 08/27/07 | 08/27/07 |
Audit - Scoping & Screening Methodology | 09/17/07 | 09/17/07 |
Public Meeting - Environmental Scoping | 09/27/07 | 09/27/07 |
Audit – Environmental | 10/15/07 | 10/15/07 |
Audit - Aging Management Programs (AMPs/TLAAs) | 10/15/07 | 10/15/07 |
Deadline for Filing Hearing Requests and Petitions for Intervention | 10/22/07 | 10/22/07 |
Environmental Scoping Period Ends | 10/24/07 | 10/24/07 |
Environmental Requests for Additional Information (RAIs) Issued | 11/26/07 | N/A |
Audit - Aging Management Reviews (AMRs) | 12/10/07 | 12/10/07 |
Safety RAIs – Issued | 12/14/07 | 12/14/07 |
Environmental RAIs – Response Received | 01/02/08 | N/A |
Audit - 3rd Optional AMP/TLAA/AMR | 01/14/08 | N/A |
Safety RAI - Responses Received | 01/18/08 | 01/18/08 |
Draft Supplemental Environmental Impact Statement (SEIS) - Issued | 04/22/08 | 04/22/08 |
EPA FRN Published - Availability / Comment on draft SEIS | 05/02/08 | 05/02/08 |
Inspection - Regional | 05/19-23/08 & 06/02-06/08 |
|
Public Exit Meeting - Regional Inspections | TBD | |
Public Meeting - Draft SEIS | 06/05/08 | 06/03/08 |
End of draft SEIS Comment Period | 07/16/08 | 07/16/08 |
Inspection - Final Optional | TBD | |
Safety Evaluation Report (SER) with Open Items - Issued | 09/12/08 | |
ACRS Subcommittee Meeting on SER with Open Items | 11/08 | |
SER with Open Items - Responses Received | 12/10/08 | |
Final SEIS – Issued | 12/30/08 | |
EPA FRN Published - Availability of Final SEIS | 01/02/09 | |
SER – Issued | 01/19/09 | |
ACRS Full Committee Meeting on SER | 04/09 | |
Staff Recommendation to Director, NRR | 05/01/09 | |
Decision Director NRR - Approval (23 months if no hearing)) | 06/01/09 | |
Commission decision (if hearing is granted - 31 months) | 01/22/10 |
NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Vogtle Electric Generating Plant, Units 1 and 2 (NUREG-1437, Supplement 34) Draft Report for Comment," was published in April 2008. This supplement documents the NRC staff's review of the environmental issues at Vogtle Electric Generating Plant, Units 1 and 2 regarding the Southern Nuclear Operating Comapny application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the Staff's analysis that considers and weighs the environmental effects of the proposed action (license renewal), the environmental impacts of alternatives to the proposed action, and potential mitigative measures for reducing or avoiding adverse impacts. It also includes the Staff's recommendation regarding the proposed action.
The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.
Vogtle PMs | |
---|---|
License Renewal | Donnie J. Ashley |
Environmental | J. P. Leous |
Lead Power Plant | Richard Jervey |
Privacy Policy |
Site Disclaimer |