On this page
Application Information:
The following links on this page are to documents in Adobe Portable Document
Format (PDF). See our Plugins, Viewers, and
Other Tools page for more information. For successful viewing of PDF documents on our site please be sure to use the latest version of Adobe.
License Renewal Review Schedule*
* These schedules reflect work plans that are subject to change. Early
completion of a milestone may affect the target date of future milestones.
Subsequent meetings and comment periods may change based on the revised
schedule. This work plan will be updated on a periodic basis. Please see
the NRC Public Meetings
Page or contact the listed PM for the latest
information on meetings and status.
Milestones |
Schedule Date |
Actual Date |
Receive License Renewal Application |
06/17/02 |
06/17/02 |
FRN Published for Receipt & Acceptability |
07/18/02 |
02/12/02 |
FRN Published for Acceptance/Rejection/ Opportunity for Hearing of LRA |
08/19/02 |
08/16/02 |
FRN Published for Intent/Environmental Scoping Mtg |
08/25/02 |
08/22/02 |
Deadline for Filing Hearing Requests and Petitions
for Intervention |
09/19/02 |
09/19/02 |
Scoping and Screening Methodology Audit Complete |
09/20/02 |
09/20/02 |
Environmental Scoping Meeting |
09/25/02 |
09/25/02 |
Environmental Scoping Period Ends |
10/25/02 |
10/25/02 |
Environmental RAIs Issued |
12/02/02 |
10/23/02 |
Environmental RAI Responses Received |
01/20/03 |
01/20/03 |
Safety RAIs Issued |
02/11/03 |
02/11/03 |
Scoping Inspection Complete |
04/04/03 |
04/04/03 |
Safety RAI Responses Received |
04/28/03 |
04/28/03 |
Draft Supplemental Environmental Impact Statement Issued |
05/16/03 |
05/05/03 |
FRN Published for Availability/Comment on Draft SEIS |
05/16/03 |
05/14/03 |
Public Mtg to Discus Draft SEIS |
06/25/03 |
06/25/03 |
End of Draft SEIS Comment Period |
07/30/03 |
07/30/03 |
Aging Management Review Inspection Complete |
07/03 |
06/27/03 |
SER with Open Items Issued |
08/25/03 |
08/25/03 |
Optional Final Inspection Complete |
09/10/03 |
09/10/03 |
ACRS Subcommittee Mtg on SER with Open Items |
09/30/03 |
09/30/03 |
SER Open Item Responses Received |
11/07/03 |
11/07/03 |
Final SEIS Issued |
12/31/03 |
12/12/03 |
FRN Published for Availability of Final SEIS |
01/02/04 |
12/15/03 |
SER Issued |
01/21/04 |
01/20/04 |
Regional Administrator's Letter Issued |
02/03/04 |
12/17/03 |
ACRS Full Committee Mtg on SER |
03/04/04 |
03/04/04 |
ACRS Letter Issued |
03/04 |
03/18/04 |
Staff Recommendations to Director, NRR |
04/12/04 |
04/09/04 |
Decision - Director, NRR (license issued) |
04/19/04 |
04/19/04 |
Environmental Impact Statement
NUREG-1437, "Generic Environmental Impact Statement for License Renewal
of Nuclear Plants,"
Supplement 13, Regarding H.B. Robinson Steam Electric Plant, Unit No. 2, was
published December 2003
This supplement documents the NRC staff's review of the environmental
issues at Robinson, Unit 2 in support of Carolina Power and Light Company's
(CP&L) application for license renewal of that facility. The supplement
was prepared in accordance with 10 CFR 51.71. This supplemental environmental
impact statement includes the staff's analysis that considers and weighs
the environmental effects of the proposed action, the environmental impacts
of alternatives to the proposed action, and alternatives available for
reducing or avoiding adverse impacts. It also includes the staff's recommendation
regarding the proposed actions.
Safety Evaluation Report
The NRC staff reviewed the Robinson license renewal application for compliance
with the requirements of Title 10 of the Code of Federal Regulations,
Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power
Plants," and prepared this report to document its findings. The
document was first issued in August 2003, as "Safety Evaluation Report
with Open Items Related to the License Renewal of H.B. Robinson, Unit
2". The report is available in ADAMS under accession number ML032370382.
In March 2004, the report "Safety Evaluation Report - Related to
the License Renewal of the H. B. Robinson Steam Electric Plant, Unit 2," was
issued as NUREG-1785.
The report is also available in ADAMS under accession number ML040200981.
Public Involvement
The public is encouraged to participate in the reactor license renewal
process through public meetings, and public comment periods on rules,
renewal guidance, and other documents. The
Reactor License Renewal Public Involvement page provides general information
to help the public participate.
Date |
Description |
03/04/04 |
Meeting with Carolina Power & Light to discuss issues
related to the Safety Evaluation Report (SER) for the Robinson
Nuclear Plant, License Renewal Application
|
09/30/03 |
Meeting with Carolina Power & Light to discuss issues
related to the Safety Evaluation Report (SER) with open items
for the Robinson Nuclear Plant, License Renewal Application
|
06/27/03 |
Meeting with Carolina Power & Light to present the results
of the NRC's second regional inspection (Aging Management Review)
of the company's license renewal program at Robinson.
|
06/25/03 |
Meeting with Carolina Power & Light to discuss the Draft
Environmental Impact Statement (EIS) for the Robinson Nuclear
Plant License Renewal Application.
|
05/20/03 05/21/03 |
Meeting with Carolina Power & Light to discuss and clarify
the final requests for additional information (RAI) response.
|
04/04/03 |
Meeting with Carolina Power & Light to present the results
of the NRC's first regional inspection (Scoping and Screening)
of the company's license renewal program at Robinson.
|
01/08/03 01/09/03 |
Meeting with Carolina Power & Light to discuss draft request
for additional information (RAI) for the Robinson Nuclear Plant
License Renewal Application.
|
12/17/02 12/18/02 12/19/02 |
Meeting with the Carolina Power & Light to discuss draft
requests for addition information for the Safety Evaluation Report
of the Robinson Nuclear Plant License Renewal Application.
|
10/23/02 10/24/02 |
Meeting with the Carolina Power & Light to discuss the
review tools provided by the applicant for the Robinson Nuclear
Plant License Renewal Application.
|
10/23/02 |
Meeting with the Carolina Power & Light to discuss the
electrical area of the Robinson Nuclear Plant License Renewal
Application.
|
09/25/02 |
Meeting to discuss the Environmental Scoping Process for the
Robinson Nuclear Plant License Renewal Application.
|
09/20/02 |
Meeting with the Carolina Power & Light to discuss the
results of the NRC's initial inspection (Scoping Methodology)
of the Company's license renewal program at Robinson Nuclear Plant.
|
07/18/02 |
Meeting with the Carolina Power & Light to
provide the Nuclear Regulatory Commission (NRC) staff with an
overview of the Robinson Nuclear Plant License Renewal Application.
|
|