skip navigation links 
 
 Search Options 
Index | Site Map | FAQ | Facility Info | Reading Rm | New | Help | Glossary | Contact Us blue spacer  
secondary page banner Return to NRC Home Page
Plant Applications for License Renewal
Arkansas Nuclear One,
Unit 1
Arkansas Nuclear One,
Unit 2
Beaver Valley
Browns Ferry
Brunswick
Calvert Cliffs
D.C. Cook
Dresden and Quad Cities
Edwin I. Hatch
Farley
FitzPatrick
Fort Calhoun
Ginna
Harris
Indian Point
Kewaunee
McGuire and Catawba
Millstone
Monticello
Nine Mile Point,
Units 1 and 2
North Anna and Surry
Oconee
Oyster Creek
Palisades
Peach Bottom
Pilgrim
Point Beach
Prairie Island, Units 1 and 2
Robinson
St. Lucie
Summer
Susquehanna
Three Mile Island, Unit 1
Turkey Point
Vermont Yankee
Vogtle
Wolf Creek

Turkey Point Nuclear Plant, Units 3 & 4 - License Renewal Application

Renewed License Issued 06/06/02

Turkey Point Nuclear Plant Picture

On this page:

Application Information:

The following links on this page are to documents in Adobe Portable Document Format (PDF). See our Plugins, Viewers, and Other Tools page for more information. For successful viewing of PDF documents on our site please be sure to use the latest version of Adobe.

(To top of page)

License Renewal Review Schedule

Milestones Schedule Date Actual Date
Receive License Renewal Application 09/11/00 09/11/00
FRN Published for Receipt & Acceptability 09/26/00 09/26/00
FRN Published for Acceptance/Rejection/ Opportunity for Hearing of LRA 10/17/00 10/17/00
FRN Published for Intent/Environmental Scoping Mtg 10/20/00 10/24/00
Scoping and Screening Methodology Audit Complete 11/16/00 11/16/00
Deadline for Filing Hearing Requests and Petitions for Intervention 11/17/00 11/13/00
Environmental Scoping Meeting 12/06/00 12/06/00
Environmental Scoping Period Ends 12/22/00 12/22/00
Environmental RAIs Issued 01/31/01 01/31/01
Safety RAIs Issued 02/05/01 02/02/01
Environmental RAI Responses Received 03/30/01 03/30/01
Safety RAI Responses Received 04/23/01 04/19/01
Scoping Inspection Complete 06/08/01 05/25/01
Draft Supplemental Environmental Impact Statement Issued 07/17/01 06/12/01
FRN Published for Availability/Comment on Draft SEIS 07/17/01 06/12/01
SER with Open Items Issued 08/17/01 08/17/01
Public Mtg to Discus Draft SEIS 08/24/01 07/17/01
End of Draft SEIS Comment Period 09/06/01 09/06/01
Aging Management Review Inspection Complete 09/14/01 09/14/01
ACRS Subcommittee Mtg on SER with Open Items 09/25/01 09/25/01
ACRS Full Committee Mtg on SER with Open Items 10/04/01 10/05/01
SER Open Item Responses Received 11/16/01 11/07/01
Final SEIS Issued 01/29/02 01/11/02
FRN Published for Availability of Final SEIS 01/29/02 01/11/02
Optional Final Inspection Complete 01/15/02 01/15/02
SER Issued 02/28/02 02/27/02
Regional Administrator's Letter Issued 03/08/02 02/01/02
ACRS Subcommittee Mtg on SER 03/13/02 03/13/02
ACRS Full Committee Mtg on SER 04/11/02 04/11/02
ACRS Letter Issued 04/30/02 04/23/02
Commission Paper with Staff Recommendations 05/17/02 05/17/02
Commission Decision 07/17/02 07/17/02

(To top of page)

Environmental Impact Statement

NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants," Supplement 5, Regarding Turkey Point Nuclear Plant, Units 3 & 4, was published January 2002.

This supplement documents the NRC staff's review of the environmental issues at the Turkey Point Nuclear Plant, Units 3 & 4 in support of Florida Power and Light Company's application for license renewal of that facility. The supplement was prepared in accordance with 10 CFR 51.71. This supplemental environmental impact statement includes the staff's analysis that considers and weighs the environmental effects of the proposed action, the environmental impacts of alternatives to the proposed action, and alternatives available for reducing or avoiding adverse impacts. It also includes the staff's recommendation regarding the proposed actions.

(To top of page)

Safety Evaluation Report

The NRC staff reviewed the Turkey Pointlicense renewal application for compliance with the requirements of Title 10 of the Code of Federal Regulations, Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," and prepared this report to document its findings. The document was first issued in August 2001, as "Safety Evaluation Report with Open Items Related to the License Renewal of Turkey Point Nuclear Plant, Units 3 & 4." The report is available in ADAMS under accession number ML012320135.

In April 2002, the "Safety Evaluation Report Related to the License Renewal of Turkey Point Nuclear Plant, Units3 & 4" was issued as NUREG-1759and later supplement in May 2002 as NUREG-1759, Supplement 1.