Figure B-1. Task Timeline for Project Planning for Web-based Surveys
Task Timeline for Project Planning |
Preparation/Planning |
Week 1 |
Week 2 |
Week 3 |
Week 4 |
Week 5 |
Week 6 |
Getting Started – Ch. 2 |
Determine available resources, project scope, and schedule |
X |
|
|
|
|
|
|
Decide whether to use an outside vendor (and select vendor) |
X |
|
|
|
|
|
|
Form a project team |
X |
|
|
|
|
|
|
Determining Your Data Collection Methods – Ch. 3 |
Decide how surveys will be returned (optional) |
|
X |
|
|
|
|
|
Establish a point of contact in the nursing home |
|
X |
|
|
|
|
|
Establishing Data Collection Procedures – Ch. 4 |
Decide whether to track response through identifiers |
|
X |
|
|
|
|
|
Assemble survey materials (develop and print materials) |
|
|
← |
→ |
|
|
|
Publicize and promote the survey |
|
|
|
← |
— |
— |
→ |
Send prenotification E-mail |
|
|
|
X |
|
|
|
* Track responses and calculate preliminary response rates |
|
|
|
|
|
← |
→ |
* Distribute first reminder (a few days after invitation) |
|
|
|
|
X |
|
|
* Distribute second reminder |
|
|
|
|
|
X |
|
* Distribute third reminder/close out data collection |
|
|
|
|
|
|
X |
* End of data collection.
Return to Document