REQUEST |
APPROVAL DATE |
CHANGE REQUEST TITLE |
M-48-01-01 |
01/02/2002 |
Add Tri Party Agreement Milestone Series M-48 |
M-45-02-01 |
02/11/2002 |
Realign completion date for Tri Party Agreement Target Milestone M-45-55-T02 |
M-23-02-01 |
02/26/2002 |
Modifications to the M-23-23 Milestone, that are necessary to ensure effective integration between Tri-Party Agreement milestone language, completion schedules for Contract No. DE-AC27-99RL14047 and ORP directives |
M-16-01-05 |
04/30/2002 |
Establish date for completion of all 100 Area remedial actions (Tri-Party Agreement Milestone M-016-00F) |
M-16-01-06 |
04/30/2002 |
Establish date for completion of all 300 Area remedial actions |
M-93-01-02 |
04/30/2002 |
Modification to the Tri-Party Agreement M-93 series milestones. Complete final disposition of all 100 Area surplus production reactor buildings |
M-094-01-01 |
04/30/2002 |
Establish date for final disposition of all 300 Area surplus facilities under the M-094 series milestones |
P-06-02-01 |
05/21/2002 |
Quality assurance sections of the Tri-Party Agreement |
M-62-01-03 |
06/03/2002 |
Modification of Hanford Federal Facility Agreement and Consent Order (HFFACO) requirements M-62-06, M-62-07, M-62-10 & M-62-11, in order to resolve inconsistencies between HFFACO requirements, completion schedules within the U. S. Department Of Energys (DOE) Contract No. DE-AC27-01RV14136 and DOEs Office of River Protection (ORP) baseline schedule |
M-90-01-03 |
06/03/2002 |
Modification of Hanford Federal Facility Agreement and Consent Order (HFFACO) M90 series requirements in order to resolve inconsistencies between HFFACO requirements, completion schedules within the U. S. Department Of Energys (DOE) Contract No. DE-AC27-01RV14136, and DOEs Office of River Protection (ORP) baseline schedule |
M-20-01-01 |
06/03/2002 |
Modification of Hanford Federal Facility Agreement and Consent Order (HFFACO) hazardous waste facility Part B Permit requirements M-20-56 and M-20-57 (Immobilized Low-Activity Waste Disposal and High-Level Waste (HLW) Canister Storage Building (CSB)) in order to resolve inconsistencies between HFFACO requirements, completion schedules within the U.S. Department Of Energys (DOE) Contract No. D-AC27-01RV14136, and DOES Office Of River Protection (ORP) Baseline Schedule |
M-20-02-01 |
06/05/2002 |
Modify Tri-Party Agreement milestone series M-020 in accordance with the Central Plateau Agreement In Principle |
M-16-02-01 |
06/05/2002 |
Modification of the M-016 series milestones |
M-13-02-01 |
06/05/2002 |
Modification of Central Plateau 200 Area Non-Tank Farm remedial action work plans (M-013 series milestones) |
M-15-02-01 |
06/05/2002 |
Modify Tri-Party Agreement milestone series M-015 in accordance with the Central Plateau Agreement in Principle |
M-34-02-01 |
06/11/2002 |
Measurements of the amount of Spent Nuclear Fuel removed from the K West Basin, as specified by: M-34-18A, M-34-27-T01, and M-34-28 |
M-16-02-02 |
07/11/2002 |
Modify In-Situ REDOX Manipulation (ISRM), Phase III Barrier Emplacement Interim Milestone M-16-27C |
M-15-01-04 |
07/12/2002 |
Interim milestones for 200-MW-1 miscellaneous waste group operable unit RI/FS work plan |
M-34-02-02 |
07/23/2002 |
M-34-17 - Deletion of requirement for initiation of sludge containerization |
M-15-01-03 |
09/11/2002 |
Establish interim milestones for 200-LW-1 300 Area and 200 Area Laboratory Waste Group Operable Units RI/FS |
M-24-02-01 |
09/24/2002 |
Establish Tri-Party Agreement Interim Milestone M-024-56 for CY 2002 Resource Conservation and Recovery Act (RCRA) well installation |
M-83-01-03 |
10/29/2002 |
Establish Hanford Federal Facility Agreement and Consent Order (HFFACO) Milestones and a target date for the Plutonium Finishing Plant (PFP) transition and selected disposition activities |
M-45-02-04 |
10/30/2002 |
Realign completion date for Tri-Party Agreement (TPA) Target M-045-55-T03 |
M-16-02-04 |
11/13/2002 |
Additional extraction well for 100-KR-4 pump-and-treat system |
M-46-02-01 |
11/25/2002 |
Modification of Hanford Federal Facility Agreement and Consent Order (HFFACO) Milestone M-4801I in order to allow coordinated review of the need for additional tank storage space, including review of DOEs Single-Shell Tank Retrieval Sequence And Double-Shell Tank Space Evaluation (RPP-8554 Rev 1). |
M-45-02-05 |
12/17/2002 |
Modification of Hanford Federal Facility Agreement and Consent Order (HFFACO) M-045-05D in order to allow necessary time to finalize M-45-02-03 Change Request which when finalized completes the requirements of M-045-05D |