Office of Administrative Law Judges 50 Fremont Street, Suite 2100
San Francisco, CA 94105
(415) 744-6577 (415) 744-6569
(FAX)
January 28, 2000
CASE NUMBER: 1999-ERA-0020
In the Matter of:
LEE REID,
Complainant,
v.
SCIENTECH, INC.,
Respondent.
Appearances:
Dean C. Brandstetter,
For the Complainant
Bradley J. Williams and Lee Radford,
For the Respondent
Before: Henry B. Lasky
Administrative Law Judge
RECOMMENDED DECISION AND ORDER
This matter arises under the employee protection
provisions of the Energy Reorganization Act of 1974, as amended in 1992 (ERA), 42 U.S.C. § 5851
et seq. Complainant Lee Reid was employed as a radiation protection supervisor for Scientech, Inc.
(Scientech) from July 20, 1998, to October 1, 1998, at which time Complainant was terminated from his
employment. On March 22, 1999, Complainant filed his complaint against Scientech alleging that his
termination was retaliatory and unlawful under the ERA. In a letter dated May 19, 1999, the Department of
Labor notified Scientech that the evidence supported the complaint that violations occurred and ordered
specified remedies. Thereafter, Scientech requested a
[Page 2]
formal hearing on May 25, 1999. On June 10, 1999,the matter was assigned to the undersigned administrative law judge and a notice of hearing was issued. The
hearing was ultimately conducted on December 7 and 8, 1999, in Rigby, Idaho. At the time of hearing.
Complainant's Exhibits (hereinafter referred to as "CX") 1 through 6, 8 through 11, and 13
through 32 were admitted. Respondent's Exhibits (hereinafter referred to as "RX") 1 through 23,
25, and 27 through 41 were also admitted at the hearing.
The matter was submitted subject to an order requiring the
parties to file proposed findings of fact and conclusion of law on or before January 20, 2000, and the waiver
by the parties of any time requirements to the contrary for the issuance of a recommended decision and order.
Proposed Findings of Fact and Conclusions of Law were received from the parties within the time required,
and based upon the evidence introduced at trial, the testimony of the witnesses, and having considered the
arguments made in post-trial submissions of Complainant and Respondent, I make the following findings of
fact, conclusions of law, and recommended decision and order.
I.
FINDINGS OF FACT
A. Background
Scientech, Inc. is a corporation which conducts waste
remediation and management for the Department of Energy. TR 206. In 1998, Versar, Inc. (Versar) was hired
to clean up buildings located on Norton Air Force Base (Norton AFB), in San Bernardino, California. These
buildings were used by the United States Air Force (USAF or Air Force) for several years as repair facilities
for aircraft instrumentation. TR 31-32. While repairing the aircraft instrumentation, air force personnel used
radioactive radium dye and paint to mark the instruments, which, over time, was spilled and splattered
throughout the buildings. TR 31-32. Before the Air Force could turn Norton AFB over to San Bernardino
County, the radioactive material had to be removed. TR 32-34. Scientech was a subcontractor of Versar, and
was primarily responsible for characterizing the nature and extent of the radium contamination in the
buildings. CX 25 (Work Plan, page 6 of 39). Any work performed by Scientech employees on the Norton
AFB project had to comply with Nuclear Regulatory Commission rules. TR 101.
B. Complainant's Evidence
1. Testimony of Lee Reid
Complainant Lee Reid has been in the radiology industry
for approximately 34 years. Transcript (hereinafter referred to as "TR") 88. He is
qualified under the American National Standards Institute (ANSI), and has received a radiological control
[Page 3]
technician (RCT) certificate. TR 89-90; see CX 13 (providing Complainant's resume). On June 1,
1998, Complainant applied for a position with Scientech, and later received a job offer. TR 90-91.
Complainant was hired to work for Scientech on a project located at Nellis Air Force Base (Nellis AFB) in
Las Vegas, Nevada. TR 90-91. While working on the Nellis AFB project, Jeff Bradford, a Scientech
manager, asked Complainant to participate in another project at Norton AFB in San Bernardino, California.
TR 92-93. Complainant began working at Norton AFB on July 20, 1998, and believed that the job would end
in February 1999. TR 93-94.
Before Complainant arrived at Norton AFB, he reviewed
a work plan given to him by Scientech. TR 96. According to the plan, Complainant had the power to stop any
work activities that were unsafe or dangerous. TR 96; CX 25 (Health & Safety Plan, page 2 of 31). The plan
further instructed employees to report conditions or situations that were unsafe to the Versar Project Manager
(Mark Stockwell) or the Site Manager. CX 25 (Health & Safety Plan, page 2 of 31). Based on the
information provided in the work plan, Complainant believed that he was required to report any problems to
Mark Stockwell, and not his immediate supervisor, Steve Lopez. TR 96-97.
On September 30, 1998, Complainant testified that Mark
Stockwell, the Versar Project Manager, asked him to find out why Mr. Lopez needed to borrow a chisel and
hammer. TR 119. A few minutes later, Scientech employee Mark Sassar approached Complainant with
samples which Mr. Sassar said had been taken by Mr. Lopez. TR 119. Complainant learned that the samples
had been taken from storage drums located in the vestibule area of one of the buildings being surveyed by
Scientech. TR 119-120. In addition, Mr. Sassar informed Complainant that Mr. Lopez had not worn the
appropriate personal protection gear that was required before a sampling could be taken. TR 130-131.
Complainant testified that there were several signs posted in the vestibule area which alerted a person that an
RWP (radioactive work permit) was required before entry. TR 120-121; see CX 24 (providing a copy
of the posting). An RWP establishes the level of training that the worker must have acquired before he or she
is allowed to enter the area. TR 121. Complainant testified that Mr. Lopez was not allowed to enter the area
because he did not have the required training and was not authorized in the RWP. TR 119, 125-126;
see CX 26 (providing a copy of the RWP for the vestibule area). Thus, Complainant asserts that Mr.
Lopez violated federal regulations, such as 10 C.F.R. 20.1 TR 119.
1See 10 C.F.R. § 20.1001(a)
(stating that these federal regulations were established to provide "standards for protection against
ionizing radiation resulting from activities conducted under licenses issued by the Nuclear Regulatory
Commission").
2See Transcript of Hearing Before the
Idaho Department of Labor Appeals Bureau (presented as RX 37 and CX 4) at 20, 22, 23-24, 34, 35, 37, and
52 (providing examples of the appeals examiner intervention in Complainant's attempt to cross-examine
witnesses at the hearing).
3 "Any right, fact, or matter in issue,
directly based upon or necessarily involved in a determination, redetermination, decision of the appeals
examiner or decision of the commission which has become final, shall be conclusive for all the purposes of
this chapter as between the interested parties who had notice of such determination, redetermination, or
decision. Subject to appeal proceedings and judicial review by the Supreme Court as set forth in this
section, any determination, redetermination or decision as to rights to benefits shall be conclusive for all
purposes of this chapter and shall not be subject to collateral attack irrespective of notice." Idaho
Code § 72-1368(11)(a) (emphasis added).