skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 25, 2008         DOL Home > OALJ Home > Whistleblower Collection
USDOL/OALJ Reporter
Fabricius v. Town of Braintree/Park Dept., 97-CAA-14 (ALJ Sept. 8, 1997)

U.S. Department of Labor
Office of Administrative Law Judges
John W. McCormack Post Office and Courthouse
Boston, Massachusetts 02109
Room 507
(617) 223-9355
(617) 223-4254 (FAX)

Date:   September 8, 1997
Case No.:   97-CAA-14

In the Matter of:

Theodorus J. Fabricius
    Complainant

    v.

Town of Braintree/Park Department
    Respondent

Appearances:

For the Complainant
    William T. Salisbury, Esq.

For the Respondent
    Arthur A. Smith, Esq.

Before:
    David W. Di Nardi
    Administrative Law Judge

RECOMMENDED DECISION AND ORDER

    This proceeding arises under the employee protection provision of the Clean Air Act, 42 U.S.C. §7622, and the implementing regulations found at 29 C.F.R. Part 24. Complainant, Theodorus J. Fabricius, first contacted the Town of Braintree Building Inspector's Office on March 25, 1997, raising concerns about the presence of asbestos-like material at the Sunset Lake Bath Facility, located in Braintree, Massachusetts. On March 31, 1997, Complainant


[Page 2]

received one written warning notice for leaving his worksite without permission of a supervisor and one written disciplinary notice for chronic tardiness. On April 4, 1997, Complainant filed a complaint with the U.S. Department of Labor, Occupational Safety and Health Administration, in Braintree, Massachusetts. This matter proceeded to a full hearing on the merits before the undersigned in Boston, Massachusetts on June 3 and 4, 1997.

Evidentiary Matters

    As indicated at hearing (TR 185, 282-283), this Judge has separated and further identified those exhibits admitted into evidence as ALJ EX 8 and ALJ EX 9 at the time of hearing. The exhibits have been further marked for the sake of identification and clarity of the record. The exhibits are identified by Order Regarding Identification of Exhibits, dated July 22, 1997.

    Complainant's Motion to Add Additional Exhibits, filed via facsimile on August 1, 1997, is hereby GRANTED. The August 12, 1996 note from Dr. Shadick is relevant to determining the genuineness of the chronic tardiness warning. In this respect, I have also admitted into evidence the controverting affidavit of Mr. William Hedlund.

     Post-Hearing evidence has been admitted as follows:

RX 4                June 24, 1997 Letter from Attorney              06/25/97
                    Smith with

RX 2                Complainant's time cards from January           06/25/97
                    1997 to present enclosed; and

RX 3                Respondent's Work Schedules from                06/25/97
                    October 1995 through June 1997 enclosed

CX 6                June 26, 1997 Letter from Attorney Salisbury    07/02/97
                    concerning filing date for post-hearing
                    briefs

CX 7                Claimant's July 10, 1997 Motion to Add          07/11/97
                    Additional Exhibits

CX 8                July 15, 1997 Letter from Attorney              07/15/97
                    Salisbury requesting extension of time
                    for filing briefs

ALJ EX 10           Order Granting Claimant's Motion for            07/15/97   
                     an Extension of Time

RX 5                July 18, 1997 Letter from Attorney Smith        07/18/97   


[Page 3]

                    objecting to Claimant's Motion to Add
                    Additional Exhibits          

CX 9                Claimant's July 18, 1997 Motion to Reopen       07/18/97
                    the Record and Reconvene the Hearing

CX 3                June 23, 1997 letter from Dr. Nancy             07/18/97
                    Shadick to William Hedlund concerning 
                    Complainant's medical condition

ALJ EX 11           Order Regarding Identification of               07/22/97
                    Exhibits and Order Regarding Pending
                    Motions

ALJ EX 12           Amended Order Regarding Identification          07/23/97
                    of Exhibits

CX 10               Complainant's Post-Hearing Brief                07/23/97
                    with Attorney Fee Petition Enclosed

RX 6                Respondent's Post-Hearing Brief                 07/24/97

CX 11               Complainant's August 1, 1997 Motion             08/01/97
                    to Submit An Additional Exhibit with

CX 4                Dr. Shadick's 08/12/96 letter                   08/01/97
                    to Mr. Hedlund regarding Complainant's
                    need for accommodation enclosed;

CX 5                Dr. Shadick's authentication of                 08/01/97
                    her 08/12/96 letter to Mr. Hedlund 
                    enclosed; and

CX 12               Affidavit of Complainant, dated                 08/01/97
                    July 28, 1997 enclosed

RX 7                August 12, 1997 Letter from Attorney            08/12/97
                    Smith with

RX 1                Affidavit of Mr. Hedlund, dated                 08/12/97
                    August 12, 1997 (with attachments) enclosed

    The record was closed on August 12, 1997 as no further documents were filed.


[Page 4]

    The parties stipulate (TR 7, 178, 380-81), and I find:

1. There was an employer-employee relationship between Complainant and Respondent at the relevant time;
2. Asbestos was discovered during and in the course of Complainant's employment;
3. There was a complaint made to the Building Inspector and OSHA;
4. There were two notices of discipline given to Complainant; and
5. No one thinks anyone should be exposed to asbestos.

Statement of Facts

    Mr. Theodorus J. Fabricius (hereinafter Complainant) has been employed by the Town of Braintree, Park Department (hereinafter Respondent), since July 1988 as a motor equipment operator. In addition to those duties described in his job description, Complainant, who had previously worked for a contractor, does carpentry work. Complainant's immediate supervisor is Mr. Al Graziano and his second line supervisor is Mr. William Hedlund.

    Complainant's work day usually starts with his reporting to work at the Park Department garage, which is located off of Union Street in Braintree, Massachusetts, at 7:00 a.m. A short time thereafter, Mr. Graziano usually gives the orders for the day. Complainant would then be assigned a truck and would go out to accomplish his tasks. Complainant states it is not usual for Mr. Graziano to accompany the employees to a work site and that employees are not required to check in throughout the day as they proceed from one job to another. If necessary to call into base, however, each truck is equipped with a two-way radio.

    The end of the workday is usually 3:30 p.m. and the employees are allowed a fifteen minute clean up period. Accordingly, employees usually start to load up the trucks and head back to the Park Department garage at about 3:00 p.m.

    On March 24, 1997, Complainant reported to work at 7:00 a.m. His instructions for the day were to meet Mr. Graziano at the bathhouse at Sunset Lake for instruction as to specific assignments. (TR 33) Complainant received the instructions as to what he and two other employees, Paul Greene and Dan Gray,1 were to do that day. The instructions included removal of privacy partitions inside the bathhouse, exterior gutters, facial boards, and all things that were attached to the building that were removable. (TR 33) Mr. Graziano also instructed Complainant that the ceiling, walls, and some of the plumbing had to come out. Complainant commented that Mr. Graziano was clear in stating that he wanted the ceiling to come out and that certain support columns, which were screwed into the ceiling and ran down into the poured concrete floor, would have to come out first. (TR 42) (ALJ EX 9T) All debris


[Page 5]

was to be stored in a dump truck that would be driven to a transfer station at the end of the day. It was Complainant's understanding that the employees had to demolish the interior and exterior of the bathhouse so that it could be renovated by a contractor. According to Complainant, Mr. Graziano explained this to him as an effort to keep costs down on the renovation project. By 9:00 a.m., shortly after receiving this instruction, Complainant left work for the day for personal reasons.

    On March 25, 1997, Complainant reported to work and received his instructions for the day. Complainant was instructed to go to the bathhouse at Sunset Lake and then to Lakeside School for a job. By the afternoon of the 25th, Complainant and Mr. Gray had completed all that Mr. Graziano had instructed them to do on the exterior of the bathhouse and began working on the interior. Complainant and Mr. Gray attempted, to no avail, to remove the columns by unscrewing the screws. They then attempted to remove the columns with an electric drill and to kick them out, but were similarly unsuccessful. Finally, a sledgehammer was employed. Upon Complainant's swing, the column came out of the ceiling and pieces from the ceiling, other debris, and dust fell all over the two employees. During the kicking and hammering, pieces of ceiling tile and dust started coming down. (TR 46) Complainant states this occurred at approximately 2:15-2:30 p.m.

    Complainant commented that the falling material looked like asbestos. Complainant and Mr. Gray grabbed the few tools that were laying around on the floor of the bathhouse and immediately left the building. Complainant closed the doors, but did not have a key to lock them. Once in the truck, Complainant attempted to reach Mr. Graziano2 by radio for approximately two to three minutes. In fact, Complainant states nobody at base station picked up the call either. Complainant and Mr. Gray then left the bathhouse and went to complete the job at the high school, which was approximately five minutes away. The job at the high school took about a half an hour and the employees finished at about 3:00-3:05 p.m.

    It was now the end of the work day, and Complainant and Mr. Gray began to head back to the Park Department garage. Complainant states that one would travel by the town offices en route from the high school to the Park Department office.3 (TR 52) Complainant suggested to Mr. Gray that they stop at the town offices and Complainant would run in to the Building Inspector's office to see if he could determine the identity of the material at the bathhouse.4 Mr. Gray waited for Complainant in the truck while Complainant went into the Building Inspector's office. Complainant identified himself by name, where he worked, and the work in which he was engaged and requested to speak to the Building Inspector. A gentleman then appeared, whom Complainant assumed to be the town inspector but who was later discovered to be Mr. Russell Forsberg,5 and again the Complainant identified himself, where he worked, and the work in which he was engaged. Complainant then stated his suspicion that the falling material may have been asbestos. Complainant then gave Mr. Forsberg the Park


[Page 6]

Department's telephone number, Mr. Forsberg began dialing and Complainant left. Complainant estimates the conversation took about three or four minutes.6

    It was now 3:20 p.m. and Complainant, who had to pick his daughter up from school, drove right back to the Park Department garage, quickly cleaned up and left for the day. Complainant states he does not recall seeing either Mr. Graziano7 or Mr. Graziano's truck that afternoon. Complainant also did not see Mr. Hedlund and admits that he did not go to the office to look for him. Upon returning home, Complainant undressed in his garage, placed his clothes in a plastic bag, and showered off.

    On March 26, 1997, Complainant reported to work as usual. While waiting for Mr. Graziano to come out and give the orders for the day, as is the usual practice, Complainant's name was called over an intercom with instruction to report to the office. Complainant went to the office and spoke with Mr. Graziano about his visit to the Building Inspector's office. According to Complainant, the conversation concluded with Mr. Graziano instructing Complainant to radio in to Mr. Graziano in between jobs. (TR 39-40, 60) Prior to this date, Complainant never had to report like this. Complainant questioned Mr. Graziano as to the reason for this new requirement and Mr. Graziano responded by saying that Complainant had to do it because that is what Mr. Graziano wanted. Mr. Graziano declined to put the instruction in writing, despite Complainant's request that he do so. (TR 61) Complainant then began to leave the office and Mr. Graziano followed him, instructing him to go back to the bathhouse and finish up the job.8 Complainant refused to do so until the identity of the material was determined. Mr. Graziano informed Complainant that he had been to the site with the Building Inspector, who stated the material was "wonder board." Complainant told Mr. Graziano that one could not make that determination merely by looking at the substance and again refused to return to the work site. According to Complainant, Mr. Graziano was "insistent" that he return to the work site and that he "chased" Complainant out into the garage. (TR 61-62)9 Complainant continued to refuse to return to the work site.

    A short while later, Mr. Graziano came out of the office and gave Complainant different instructions for the day. Upon completion of the first assignment, Complainant called in to Mr. Graziano on the two-way radio. Mr. Graziano instructed Complainant to return to the garage, whereupon Mr. Graziano told Complainant not to get smart and sent him back out to finish his assignments for the day.

    During lunch hour, Complainant had the opportunity to speak with employees from the Water and Sewer Department, whom he encountered when stopped at a set of lights in front of the Town Hall. Complainant asked the employees whether they knew of any asbestos at the bathhouse and one of the men said there was definitely asbestos in there and that the plans, which


[Page 7]

were at the Water and Sewer Department, clearly showed transite tile. (TR 69)

    At the end of the day, at approximately 3:10 p.m., Complainant was again driving past the town offices and stopped to go to the Water and Sewer Department to obtain the plans for the bathhouse. Complainant states that he ran into a man, Joe Salano, as he went towards the building and Mr. Salano told Complainant that the plans to the bathhouse had been given to Mr. Hedlund. Complainant estimates this conversation took about two or three minutes. Complainant then returned to the garage so that he could take a look at the plans. Upon arriving at the garage, Complainant ran into Mr. Greene and the two of them went to the office. Mr. Hedlund and Mr. Graziano were in the office and Complainant asked for the plans. Mr. Hedlund informed Complainant they were on a table, rolled up, and Complainant looked at the plans and immediately saw that they indicated transite tile was used in the ceiling. (ALJ EX 8C) Complainant asked if he could copy the plans and was allowed to do so. Complainant then returned the plans to Mr. Hedlund, pointed out the fact that transite tile was used, and told Mr. Hedlund that a grievance had been filed in the past about transite pipe used at a Town golf course. Mr. Hedlund responded that this information did not mean anything to him and that he had merely glanced over the plans.10

    Later this same day, Complainant contacted a business agent from the union because he was getting worried. (TR 78) The business agent recommended Complainant file a grievance to document the events and on March 27, 1997, Complainant did just that, basing his grievance on working with toxic materials. (ALJ EX 9C)

    On the 27th or the 28th, Complainant called OSHA to find out what to do with his possibly contaminated clothing. A representative from the Braintree office asked Complainant where he might have been exposed and he explained the situation to her. The woman from the OSHA office stated she would have to contact a hygienist for instructions. Complainant called back on Monday or Tuesday and the hygienist recommended he make sure the clothes were wrapped in a double plastic bag. In the interim, between Complainant's initial call and OSHA's return call, OSHA apparently called the Building Inspector to determine whether that office was investigating the matter. On March 28, 1997, Complainant filed an injury report with the town. (ALJ EX 9F)

    On March 31, 1997, Complainant was given one warning notice11 and one disciplinary notice.12 The warning notice was for going to the Building Inspector's office and to the Water and Sewer Department without first notifying a supervisor. (ALJ EX 9G) This was issued despite Complainant not being aware of any work rule or anything in the collective bargaining agreement that prohibited him from contacting another Town official. The management person responsible for issuing this warning, Mr. William Hedlund, states he knew the reason that Complainant went to the Water and Sewer Department at the time that he issued the warning. The disciplinary notice was issued for chronic tardiness. (CX 2) Complainant decided he had to grieve his two warnings.


[Page 8]

    On April 3, 1997, Complainant again telephoned OSHA because he wanted a definite determination on what to do with the contaminated clothing. It was during this conversation that Complainant was informed he may be protected by law and the OSHA representative recommended Complainant draft a complaint. On April 4, 1997, Complainant dropped off a complaint at the OSHA office at approximately 8:30 a.m. when he was on a coffee break, going to the Dunkin' Donuts "right next door." (TR 86) (ALJ EX 9I)

    An informal grievance meeting was held between Complainant, Mr. Gray, Mr. Hedlund, Mr. Greene and Mr. Graziano. Mr. Hedlund offered to take the contaminated clothes from Complainant and to replace them. Complainant did not want to turn the clothing over to Mr. Hedlund because he did not know whether Mr. Hedlund would know what to do with them. Complainant recalls that during this informal meeting, Mr. Hedlund explained the warning was issued because Complainant had failed to follow the chain of command. During this meeting, which did not result in resolution of Complainant's grievance, one of the gentlemen brought up that Complainant had gone to OSHA. (TR 92) After this, Complainant states "they started putting a little pressure on for what reason I really don't know...my supervisor was saying that I just didn't seem to be working up to snuff any more lately." (TR 93)

    On or about April 24, 1997, Complainant's grievances proceeded to a Step One grievance meeting before the Board and Parks Playground Commission. Complainant set forth his complaint which, he states, was not received very well, with one of the Board members indicating he did not have any "respect for you people" and, at one point, telling Mr. Gray to shut up. (TR 96-97) Complainant later learned that after the conclusion of the meeting, one of the commissioners made a comment that he was "ridiculous" and that he should be fired. (TR 97) Subsequent to the Step One grievance meeting before the Board and Parks Playground Commission, Complainant contacted Mr. Charles Goldstein, a licensed counselor.13 (ALJ EX 8F) Complainant continues to see Mr. Goldstein once a week. Complainant's two grievances are still pending and are scheduled to proceed to Step Two, before the Personnel Board, because they were denied at the First Step.

    Mr. Daniel Gray, a Town employee of approximately nine years, is also employed as a motor equipment operator. In addition, Mr. Gray is the shop steward for AFSCME Local 1350. Mr. Gray, who is also supervised by Mr. Graziano and Mr. Hedlund, confirmed Complainant's testimony as to how the orders for the day's work were distributed in the morning and that an employee was not required to report to the office at the end of each assignment.

    Mr. Gray received a warning for tardiness14 two days after he and Complainant stopped at the town office on March 25. Mr. Gray admitted that he was, in fact, tardy on that day and adds that it was only by about two minutes. (TR 138) Mr. Gray also states he has been two minutes late on other occasions, but that he did not receive warnings on those dates. (TR 141) Mr. Gray describes the warning as a "slap in the wrist for going to the building inspector." (TR


[Page 9]

133) It is a fact that, at first, management believed it was Mr. Gray who had gone to the Building Inspector's office.

    Mr. Gray has filed a grievance for exposure to asbestos requesting the Town replace his clothing and compensate him at the hazardous duty pay rate. During the informal conference with Mr. Hedlund, the grievance was denied. Mr. Gray then proceeded to Step One before the Commission on April 24, 1997 and, again, the grievance was denied. One of the Commission members told Mr. Gray to shut up and called him a dope. (TR 135) Mr. Gray also later learned of the statement by another Commission member that he would fire the whole crew. (TR 137)

    Mr. Gray admitted on cross-examination that he has been informed by Mr. Hedlund that he was compensated at the hazardous duty pay rate for the two days he spent at the bathhouse. Mr. Hedlund also offered to have Mr. Gray's clothing replaced if they were brought in and given to Mr. Hedlund. Mr. Gray, however, chose not to deliver the clothing after having discussed it with Complainant who indicated OSHA would be instructing Complainant as to what to do with his clothing.

    Ms. Sheila D. Roach, an elected member of the Board and Parks Playground Commission for over twenty (20) years, also testified at hearing. Ms. Roach has known Complainant since he became employed by the Respondent. According to Ms. Roach, she received a telephone call from Complainant on the evening of March 26 for information as to how he could find out whether or not the substance he discovered was asbestos. Ms. Roach, after having made a few phone calls, gave Complainant the name of a man to call. Ms. Roach was present for the Step One grievance meeting on the evening of April 24. Ms. Roach believes a certain Commission member was hostile during that meeting. She also confirms the exchanges between Mr. Gray and the commission member and that another commission member made a statement about firing the whole crew. Ms. Roach also adds that either Mr. Al Graziano or Mr. Dan Graziano, whose testimony is summarized below, made a statement that he would only keep two of the crew. (TR 150-151) Ms. Roach is of the opinion that all of the disciplinary notices given to Complainant should be withdrawn. (TR 152) In fact, Ms. Roach was the one dissenting vote taken on Complainant's grievance.

    Mr. Daniel J. Graziano, member of the Board and Parks Playground Commission for seven years, was also present for the April 24 grievance hearing. Mr. D. Graziano confirmed the exchange between Mr. Gray and a commission member. Mr. D. Graziano adds, however, that the exchange was precipitated by some "sarcastic answers from Mr. Gray and speaking out of turn" which stopped only after a second warning. (TR 190) Mr. D. Graziano voted to deny the grievance and he did so because, in his opinion, Complainant "should have made -- and Mr. Gray for that matter, should have made more of an effort to contact their supervisors or have returned back to the office and let them know what the situation was." (TR 191, 200-201) According to Mr. D. Graziano, the Board decided to deny the grievance to remove the warning


[Page 10]

from Complainant's file, having found out that the hazardous pay was already remitted to Complainant and that an offer to replace the contaminated clothing had been extended.

    Mr. Russell Forsberg, employed by the Town as a local building inspector since January 1996, testified at hearing that he was the individual with whom Complainant spoke on the afternoon of March 25 at approximately 3:00 p.m. Mr. Forsberg stated he could not recall if the Complainant identified himself by name, but that he does recall being informed that he was a Park Department employee. The Complainant informed Mr. Forsberg of his experience at the bathhouse, and Mr. Forsberg stated he would check into it. He then unsuccessfully attempted to contact the Parks Department. A short while later, Mr. Forsberg informed Mr. Galewski, another inspector, about the incident and Mr. Galewski made arrangement to go down to the bathhouse and perform a field inspection. The inspection was completed on March 25 sometime between 3:30 and 4:00 p.m. When Mr. Galewski returned to the office, he informed Mr. Forsberg that he was not sure of the material's identity. He then turned over a portion of the ceiling tile to Mr. Forsberg, who transported it for testing. The test results determined that the material was in fact asbestos. (ALJ EX 8D/9B)

    Mr. Robert M. Galewski, who has been Building Inspector for approximately three (3) months and who was a local building inspector for fourteen (14) years prior, testified at hearing that he telephoned Mr. Hedlund at approximately 3:30 p.m. on March 25 and arranged for a site inspection. Mr. Galewski states "at first, [he] thought it was durarock." (TR 167; Cf. ALJ EX 9R wherein Mr. Galewski attested he believed the material "might very well be asbestos")15 Upon testing, however, he learned that it was asbestos. Mr. Galewski also states that although a permit was required for the type of work being performed at the bathhouse, there was never one obtained. Furthermore, in order to obtain a permit, Mr. Galewski would have wanted to see the new plans and possibly the old plans. Mr. Galewski states that a notation concerning transite might possibly have indicated something to him. (TR 172-173) In Mr. Galewski's opinion, the Town would have violated the law by tearing down and removing the material in the way that had been planned. (TR 176)

   Mr. William Hedlund, who also testified at hearing, has been Superintendent of Parks and Recreation for the Town of Braintree since 1981. Mr. Hedlund obtained the May 1, 1948 plans of the bathhouse in late February. He looked at them with the architect, who then took the plans for about a week, and returned them to Mr. Hedlund. Indeed, Mr. Hedlund met with the architect on site and the architect did not make a suggestion that the Town should have the ceiling checked for asbestos. In this regard, Mr. Hedlund describes the discovery of the asbestos as "a dart that came out of nowhere that really surprised me."16 (TR 218) Mr. Hedlund was embarrassed when he first heard about the asbestos on the afternoon of March 25 because, according to Mr. Hedlund, he likes control. (TR 252)


[Page 11]

    Mr. Hedlund states that on March 25, he was in his office from approximately 1:45 p.m. until 6:30 p.m. At no later than 3:15 p.m., he received a telephone call from the building inspector concerning the possibility of asbestos at Sunset Lake. During the course of this conversation, Mr. Hedlund offered to have Mr. Graziano meet the building inspector at the building and so Mr. Hedlund yelled to Mr. Graziano, who was out in the garage, and told the inspector that Mr. Graziano would meet him there in about ten minutes. According to Mr. Hedlund, it took Mr. Graziano a good ten minutes to leave the building. In less than an hour, between the time Complainant saw the building inspector and the time Mr. Graziano was at the bathhouse, Mr. Graziano was on the site with the building inspector.

    Mr. Graziano figured out the next morning, the morning of the 26th, that it was actually Complainant that went to the building inspector, and not Mr. Gray as was first believed. Mr. Hedlund was advised of a conversation between Mr. Graziano and Complainant, wherein Complainant stated he went to the building inspector himself because he could not get in touch with Mr. Graziano. Accordingly, Mr. Hedlund did not have a conversation with Complainant because Mr. Graziano had already "admonished" Complainant for having taken the matter into his own hands and run with the investigation. (TR 219, 279) Mr. Hedlund states "In my 26 years, I can't think of an employee going in an exploratory nature to another agency of an issue concerning safety, health, welfare of, you know, a working job site." (TR 220)

    Mr. Hedlund recalls that he offered to replace Complainant's clothing during the informal meeting. (TR 223) This offer was again extended during the April 24, 1997, Step One grievance meeting. Again, it was declined. Mr. Hedlund states that Complainant and Mr. Gray both stated during the informal meeting that they were back at the garage at shortly after 3:00 p.m. According to Mr. Hedlund's calculations and his testimony that Mr. Graziano was in the garage, this gave the Complainant and Mr. Gray a good ten minutes, if not twenty minutes, to speak with Mr. Graziano. (TR 225) Instead, they "withheld" the information of their contact with the building inspector.

    Mr. Alexander A. Graziano, grounds maintenance supervisor since September 1986, was the individual responsible for giving Complainant and the other two employees their work assignments on the morning of March 24. Mr. Graziano began by discussing the whole job assignment with Complainant and specifically instructed Complainant that, as far as that Monday was concerned, Mr. Graziano wanted all partitions removed. In regards to Mr. Graziano's intentions for the job, he did inform Complainant that the entire interior was to be gutted. (TR 344) He did not, however, give any instruction concerning removal of either the ceiling or the support beams.17 On Tuesday, March 25, Mr. Graziano instructed Complainant and Mr. Gray to do some work on the exterior of the building and then to start pulling out certain plumbing items on the interior. Again, Mr. Graziano states there was no instruction to remove the ceiling. (TR 334) The posts were to eventually come out, only not within those two days. (TR 347)


[Page 12]

    Mr. Graziano testified he met Mr. Galewski at the bathhouse at approximately 3:30 - 3:45 p.m. According to Mr. Graziano, Complainant never made contact with him on the Tuesday afternoon. (TR 337) In this regard, Mr. Graziano states he was in the shop between quarter past three to 3:30 p.m. and that he did see Complainant. In fact, Mr. Graziano states he briefly spoke with Complainant about a job that was done that day. There was no mention, however, of a possible asbestos problem.

    In addition to Mr. Graziano's conversation with Complainant on the morning of the 26th, Mr. Graziano again spoke with Complainant that afternoon. According to Mr. Graziano, it was at this time that complainant "accused" him of knowing there was asbestos in the bathhouse before he sent him in there. Complainant did not mention that he had been at the Water and Sewer Department. Mr. Graziano had no problem with Complainant reporting to OSHA on his own time. In conclusion, Mr. Graziano states he had never had much of a problem with Complainant's work and that Complainant is a steady worker. (TR 363)

Discussion

    This case proceeded to a full hearing on June 3 and 4, 1997. Accordingly, examining whether Complainant has established a prima facie case is no longer particularly useful and this Administrative Law Judge shall consider whether, viewing all of the evidence as a whole, the Complainant has shown, by a preponderance of the evidence, that he was discriminated against for engaging in protected activity. See Hoffman v. Bossert, 94-CAA-4, at pp. 3-4 (Sec'y 9/19/95); Carson v. Tyler Pipe Co., 93-WPC-11, at p. 6 (Sec'y 3/24/95). To carry that burden, Complainant must prove that Respondent's stated reasons for reprimanding Complainant are pretextual, i.e., that they are not the true reasons for the adverse action and that the protected activity was. Hoffman, supra, at p. 4; Leveille v. New York Air Nat'l Guard, 94-TSC-3/4, at p. 4 (Sec'y 12/1/95). It is not sufficient that Complainant establish the proffered reason was unbelievable; he must establish intentional discrimination in order to prevail. Leveille, supra.

    Respondent argues Complainant was issued a disciplinary warning because of his failure to follow departmental policy regarding the proper chain of command and his failure to obtain supervisory permission to leave the work site despite specific instructions given by Mr. Graziano on March 26.18 In this regard, Mr. Hedlund states the Park Department does not have an employee handbook or handbook, per se. The chain of command and requirement that an employee obtain a supervisor's permission before leaving the work site, however, have been stressed in writing on monthly project schedules and are standard operational procedure in the Department.19 (TR 220-221, 285, 289, 295-296, 305, 308) These operating schedules are posted on a monthly basis throughout the year, except for the months of December through March.20 There are also employee directive notices


[Page 13]

posted on occasion by Mr. Hedlund. Mr. Hedlund states there are references in these documents to not leaving a job site without the permission of your employer.

    According to Mr. Hedlund, the essence of the warning is that Complainant took Town time to investigate and make his complaint about the asbestos and that he did not at least notify a management person. (TR 270) Consistent with this, Mr. Hedlund states he has commented on Complainant's activity with OSHA only because it was done on Town time, unknown to the management team. (TR 283)

    Under the ERA it is not permissible to find fault with an employee for failing to observe established channels when making safety complaints. Carson, supra, at p. 5 (Citing Pillow v. Bechtel Constr., Inc., 87-ERA-35, at p. 22 (Sec'y 7/19/93); Pogue v. U.S. Dept. of Labor, 940 F.2d 1287, 1290 (9th Cir. 1991)). An employer may not, with impunity, discipline an employee for failing to follow the chain-of-command, failing to conform to established channels, or circumventing a superior, when the employee raises an environmental health or safety issue. Leveille, supra, at p. 9 (Citations Omitted). See Also West v. Systems Applications Int'l, 94-CAA-15, at p. 4 (Sec'y 4/19/95) ("...it is not permissible to find fault with an employee for failing to observe established channels when making safety complaints.") In Leveille, the Secretary reasoned that an employer's practice of mandating that all environmental complaints be handled internally with no recourse to any external regulatory agencies, depending upon what the person in charge determined to be the correct route, is "clearly...prohibited." Leveille, supra, at p. 8. Such restrictions on communication, the Secretary held, would seriously undermine the purpose of the environmental whistleblower laws to protect public health and safety.

    Accordingly, this Judge rejects Respondent's argument that its claimed chain of command procedure provides a legitimate, non-discriminatory explanation for the warning notice. The aforementioned precedents clearly establish this stated reason as unpersuasive. Furthermore, neither Mr. Forsberg nor Mr. Galewski is aware of any regulation or other procedure that forbade Complainant from going directly to the Building Inspector's office with his concern. Similarly, Mr. D. Graziano testified the Commissioners did not have any procedures for chain of command to report hazardous materials, although, Mr. D. Graziano states, he thinks it would have been standard operating procedure. (TR 196-197)

    Respondent's argument that Complainant was reprimanded for leaving his work area without permission from his employer must stand or fall alone. I find this reason pretextual. In this regard, see Priest v. Baldwin Assoc., 84-ERA-30 (Sec'y 6/11/86) (wherein the Secretary found respondent's stated reason for termination, that complainant was out of his work area without permission, was pretextual because respondent could not verify its witness' testimony that other employees had been similarly reprimanded and the work rules failed to address discipline for being out of one's work area).


[Page 14]

    Complainant's is the first instance of an employee leaving a work site without permission. (TR 220, 318) The work schedules supplied by Respondent do not clearly support Mr. Hedlund's claim that this policy was standard operating procedure. (RX 3) The work schedules, which were as recent as June 1997 and stretched as far back as October 1995, generally addressed the procedure for leaving work when taken ill and/or for union business. (RX 3 dated October 1992, para. 18; October 1995, para 9; June 1994, para. 2(p); November 1993, para. 15; and October 1992, paras. 8 and 10) Not one of these schedules reflected a policy regarding leaving a work site to report an environmental safety hazard.

    This Judge finds and concludes the stated reason for the warning notice, that Complainant left his work site without permission, is disingenuous for two reasons. First, there is the evidence that the standard procedure was applied disparately. I cannot logically reconcile Complainant's having received a warning with the fact that Mr. Gray did not receive one. Both Town employees were in the truck, Mr. Gray admitted to having been informed of Complainant's attempt to stop at the Town Office, and his thought that this was a good idea.

    Mr. Hedlund, in an attempt to explain this disparate treatment, states that Mr. Gray was not given a warning for leaving the work site without permission because he was not warned on the morning of the 26th, as Complainant was, and because it was Complainant's idea to go to the Town Office and it was Complainant who actually spoke with the building inspector. As Mr. Gray did not proceed with "follow-up initiatives," he did not get a similar warning. (TR 321) It is Mr. Hedlund's judgment that Mr. Gray was not as culpable as Complainant.

    'Follow-up initiatives' and culpability, however, should have no impact on the efficacy of issuing Mr. Gray a warning. By virtue of his presence, Mr. Gray was as much off work site without permission as was Complainant. It follows, therefore, that Mr. Gray is equally guilty of violating the rule against leaving one's work site without the permission of one's supervisor.

    Second, there is the evidence that neither Mr. Hedlund nor Mr. Graziano could estimate with any specificity the length of time Complainant was engaged in these 'follow-up initiatives' and whether Complainant was on a coffee and/or lunch break.21 If one were to leave work for an illness or to conduct union business, it would be reasonable to anticipate an absence of greater than seven to eight minutes. Neither supervisory authority, Mr. Hedlund or Mr. Graziano, knew how long Complainant was gone from the work site without permission. Mr. Graziano states it is not relevant how much time Complainant took, it is the fact that he took time at all. It could have been a matter of minutes or a matter of an hour. Complainant, however, was absent no more than eight minutes. In this regard, I note RX 3 dated June 1994, para. 2(h), indicates employees should not stop for chats that "curtail productivity." It logically follows that chats which do not curtail productivity are allowed.

    Even assuming the policy reflected on these work schedules could be


[Page 15]

stretched to apply to Complainant's visiting the Town Offices and the Water and Sewer Department, it is dubious that Complainant actually left his work site as is contemplated by the policy. In this case, the testimony of Complainant, Mr. Hedlund, Mr. Graziano and Mr. D. Graziano consistently establishes that the Town Offices were on Complainant's way as he returned to the Park Department office at the end of his work day.

    I further question whether Complainant could be categorized as having engaged in personal business during these absences. The basis of the warning, Complainant's visit to the Town Offices and the Water and Sewer Department, clearly consisted of reporting the possible presence of asbestos and an attempt to verify that suspicion.22 This Judge finds these acts to be of no personal benefit to Complainant.

    This Judge's determination of Respondent's true motivations behind this warning was particularly guided by the testimony of Mr. Hedlund. Mr. Hedlund's testimony was characterized by such statements as Complainant committing "three unilateral personal initiatives" and a "covert investigation." (TR 222) (See Also TR 284, ALJ EX 9L, TR 311) Mr. Hedlund also refers to Complainant as "out of control." (TR 288, ALJ EX 9L, TR 308-309) These comments were generally delivered in a heightened tone, which indicated, to this Judge, Mr. Hedlund's frustration with the situation presented by Complainant. The critical inquiry is whether this frustration and anger were generated merely by Mr. Hedlund's embarrassment caused by Complainant turning without the Park Department infrastructure23 or whether it was generated by Complainant's reporting of safety concerns.

    This Judge finds and concludes the true motivation behind Respondent's action was discriminatory. Initially, this Judge finds and concludes Respondent has presented shifting explanations for its adverse employment action. On the one hand, the terms of that notice specifically reflect Complainant was reprimanded for leaving the work site without permission from a supervisor. (ALJ EX 9G) On the other hand, Mr. Hedlund appeared at hearing repeatedly and strenuously complaining of Complainant's failure to follow the established chain of command. I view this shifting explanation as evidence of pretext. See Hoffman, supra (holding the shift in reasons for the adverse action proffered by a respondent is indicative of pretext).

    Furthermore, I note Mr. Hedlund's comments in his April 23, 1997 statement given to OSHA in which he writes "I feel that Ted Fabricius is using OSHA and that the warning was merited." (ALJ EX 9N) Mr. Hedlund further comments upon Complainant's unilateral act of contacting OSHA by telephone, despite Complainant's having been informed that Mr. Graziano had met with the Building Inspector and that the material was being tested. (ALJ EX 9L) (See Generally TR 283-288) This Judge finds and concludes these remarks speak directly to the issue of discriminatory intent. See Blake v. Hatfield Elec. Co., 87-ERA-4 (Sec'y 1/22/92) (wherein the Secretary found the respondent's statement that complainant used the NRC as a threat to speak directly to respondent's discriminatory intent because it was not merely a


[Page 16]

stray remark and respondent's explanation was lame and illogical).

    This finding is further buttressed by the animated testimony of Mr. Hedlund which repeatedly stressed that management within the Park Department could have and would have handled the situation by similar remedial steps in a perhaps more timely fashion. Rather than state it was responsible for Complainant to report the suspected violation to the Building Inspector in what was no deviation from his route back to work, Mr. Graziano is of the opinion that Complainant should have reported to his supervisor or superintendent beforehand. (TR 358) It is a fact, however, that little to no time was wasted by Complainant's reporting his concerns to the Building Inspector at the earliest opportune time.24 In this regard, see Mandreger v. Detroit Edison Co., 88-ERA-17, at p. 11 (Sec'y 3/30/94), wherein the Secretary held "the strongest evidence of a retaliatory motive on [respondent's] part is [respondent's] statement that it was wrong for [complainant] to [report to an outside agency] because [respondent] could have solved the problem about which [complainant] complained."

    Respondent attacks Complainant's failure to contact Mr. Graziano or the office by two-way radio and argues that the failure to do so is not creditable. Mr. Hedlund states the radios are the preferred method of communicating with employees and supervisors in the field and it is rare for an employee in the field to telephone into the office. (TR 268-269) In regards to the radio system used by the Park Department, Mr. Hedlund states that he has hand-held radios in the office and that, in fact, he has "one directly on [his] desk." (TR 213) In addition to the hand-helds, there is a wall mount monitor in both the front and back office. Mr. Hedlund testified that there was no radio transmission or phone call on that afternoon from either Complainant or Mr. Gray and he knows this because there is always at least one person in either the front or back office. On March 25, in particular, Mr. Hedlund states there were two women in the front office and he was in the back office. Mr. Graziano testified that he carried his portable that day and that he had the radio which was mounted in his pick-up truck. (TR 350)

    To the contrary, both Complainant and Mr. Gray testified to an unsuccessful two to three minute attempt to reach Mr. Graziano by radio. Complainant states it is not always possible to reach Mr. Graziano by radio. In addition, Complainant states that he was not aware of any other means of contacting Mr. Graziano at the time of the incident. Specifically, Complainant was not aware that Mr. Graziano had a beeper. Even had he been aware of that, Complainant would have been required to leave the work site and find a telephone in order to page Mr. Graziano.

    Complainant did not attempt to telephone the office because "he had never called the office for any work related situation before."25 (TR 102) Complainant had also never used the telephone to communicate with Mr. Graziano before. (TR 116) Similarly, Mr. Gray had never used the telephone to reach Mr. Graziano and was unaware that Mr. Graziano carried a beeper.

    This contested factual issue of whether Complainant and Mr. Gray attempted


[Page 17]

to radio their supervisor is of little to no matter. As previously mentioned, Complainant was under no obligation to contact his immediate and/or second line supervisor. In the absence of such an obligation, this Judge would be no more and no less persuaded if Complainant had, indeed, never made such an attempt at communication.

    Respondent similarly focuses on the argument that it was unaware of the presence of asbestos. Again, this is of no matter in a whistleblower proceeding.26 The relevant inquiry is Respondent's action toward Complainant once Complainant has expressed what he believes to be an environmental concern. While Respondent's knowledge or lack thereof regarding the presence of asbestos might circumstantially impact a finding as to whether Respondent acted discriminatorily towards Complainant,27 it is not of itself an element to a whistleblower claim.

    Respondent argues the one day suspension for chronic tardiness was unrelated to the incident of March 25, 1997. Mr. Hedlund, who describes tardiness among full-time employees as a woeful problem, states that Complainant received his fifth warning slip for tardiness, which came with a one day suspension, on March 31 because of a "several year history" of chronic tardiness. (TR 227) In this respect, Mr. Hedlund specifically refers to the fifty-four (54) instances of tardiness by Complainant between January 1996 and March 1997.28 One of Complainant's earlier warnings was issued in September 1996, others were issued in 1993, 1994 and 1995. (TR 227, 305) Mr. Hedlund testified "Coincident or otherwise, it has nothing to do with harassment." (TR 227)

    Generally, the proximity in time between the decisionmaker's awareness of Complainant's protected activity and the adverse employment action is sufficient to raise an inference of causation. Carson, supra, at p. 5 (Citations Omitted). In this case, an extremely short amount of time, a mere six (6) days, expired between Complainant's engagement in protected activity and the date the tardiness warning was issued. This temporal proximity is not only sufficient to raise an inference of causation, it is a beacon to such a finding.

    This Judge finds and concludes the tardiness warning, and the resultant one day suspension, was caused by nothing other than Complainant's protected activity. In addition to the brow-raising temporal proximity between the protected activity and adverse action, there is the evidence which establishes the specific days on which Complainant was tardy and the length of time for which he was tardy. (RX 2) The time slips reveal that Complainant was last tardy on March 19, 1997, for a period of one minute. This Judge regards it as highly suspicious that Respondent waited twelve days to issue a discipline notice, which notice, I might add, was precipitated by a tardiness of one minute. My suspicions are further raised by the evidence that prior to the March 19 tardiness, Complainant was tardy on March 13 for a period of ten minutes; on March 10 for a period of one hour and thirty-three minutes; on March 6 for a period of three minutes; and on March 3 for a period of twenty-one minutes. The disciplinary notice might have been rendered credible if


[Page 18]

it had been issued in closer proximity to a tardiness that had stretched a greater length of time.29 Indeed, the evidence reflects that Mr. Gray, who candidly admitted to being late by two minutes on occasions prior to his March warning for tardiness, states he had never, before then, been issued a warning for being tardy for two minutes. Supra, pp. 8-9.

    Furthermore, there is evidence of record which supports a finding that Respondent was aware that Complainant's occasional tardiness was the result of a medical condition. Mr. Hedlund states that he is aware that Complainant has verbally requested he be allowed to come into work late because of a medical condition caused by a back injury during an industrial accident in 1992. Mr. Hedlund, however, is of the opinion that Complainant was given a clean bill of health for that injury and, therefore, Mr. Hedlund disagrees with Complainant's requests. He bases this opinion on medical records of evidence on file in Town Hall and at the personnel office. (TR 306) The Park Department requested something in writing from a doctor on or before May 15 and, as of the date of hearing, Complainant had failed to supply any such documentation.

    This Judge notes the post-hearing evidence which demonstrates a dispute between the parties as to whether the tardiness warning was bona fide. In this regard, Complainant claims that the tardiness warning was retaliatory because Respondent knew of his medical condition and his request to be allowed to be intermittently tardy based on that condition. (CX 4, 5, 12) Respondent contends it was not on notice of medical records which would substantiate Complainant's request for leeway in his reporting time. (RX 1) Even if this Judge were to assume Respondent was not in receipt of medical records to support Complainant's request, I find and conclude that the tardiness warning was retaliatory in nature in light of the warning's temporal proximity to the protected activity and in light of the infrequency and minimal amount of Complainant's tardiness in relation to the date of the warning.

    Accordingly, this Judge finds and concludes that the Respondent's stated reasons for Complainant's reprimands are not creditable. Complainant has proven, by a preponderance of the evidence, that Respondent's articulated reasons for the reprimands are pretextual.30 I further find and conclude that the true reason for these reprimands was in retaliation for Complainant engaging in protected activity.

Damages

    This Judge, having found the Respondent in violation of the Energy Reorganization Act, may issue a recommendation on damages to be awarded to Complainant. Complainant has requested compensatory damages, compensation for certain days he missed from work and out of pocket expenses incurred as a result of pursuing this action, costs of obtaining medical care and treatment, remuneration for his contaminated clothing, and attorneys fees.


[Page 19]

Complainant also requests certain documents be expunged from his personnel file, that Respondent cease and desist from hits discriminatory treatment and harassment of Complainant and be enjoined from causing his termination, and that Respondent be required to dispose of his contaminated clothing.

    Prior to embarking upon those damages this Judge has authority to issue and which I deem appropriate, I shall note I specifically reject Complainant's request of two specific remedies. First, this Judge declines to award compensation for any out of pocket expenses incurred by Complainant as a result of his protected activity and in pursuing this action because Complainant failed to offer any evidence to this effect. Second, this Judge declines to issue an Order enjoining Respondent from causing termination of Complainant's employment because such termination might be occasioned for valid reasons, unrelated to Complainant's protected activity.31

    This Judge finds and concludes the Complainant is entitled to recover a back pay award for the day he was suspended without pay, together with interest calculated in accordance with 26 U.S.C. §6621 on that award. In regards to Complainant's request for an award for those days of work he missed in order to attend the hearing of this matter, this Judge is not able to fashion such a remedy as the record fails to indicate whether or not Complainant was otherwise compensated for those days. For example, he may have been on vacation or personal leave.

Compensatory Damages

    Pursuant to the CAA compensatory damages may be awarded for emotional pain and suffering, mental anguish, embarrassment and humiliation. 42 U.S.C. §7622(b)(2)(B)(ii). See Generally Nolan v. AC Express, 92-STA-37 (Sec'y 1/17/95) (analogous provision of the STA); Deford v. Secretary of Labor, 700 F.2d 281, 283 (6th Cir. 1983) (analogous provision of the ERA). Where appropriate, a complainant may recover an award for emotional distress when his or her mental anguish is the proximate result of respondent's unlawful discriminatory conduct. See Bigham v. Guaranteed Overnight Delivery, 95-STA-37 (ALJ 5/8/96) (adopted by ARB 9/5/96); Crow v. Noble Roman's Inc., 95-CAA-8 (Sec'y 2/26/95). See Also Blackburn v. Metric Constructors, Inc., 86-ERA-4 (Sec'y 10/30/91). Complainant bears the burden of proving the existence and magnitude of any such injuries; although, as a caveat, it should be noted that medical or psychiatric expert testimony on this point is not required. Bigham, 95-STA-37 (ALJ 5/8/96), at p. 14; Lederhaus v. Paschen, 91-ERA-13 (Sec'y 10/26/92), at p. 7 (Citation Omitted).

    The Board has found it appropriate to review other types of wrongful termination cases, as well as awards in other whistleblower decisions involving emotional distress, to assist in the analysis of the appropriate measure of compensatory damages in whistleblower cases. Accordingly, this is precisely what this Judge has done. See Doyle v. Hydro Nuclear Services, 89-ERA-22 (ARB 9/6/96) (wherein the Board affirmed the ALJ's recommendation of $40,000 compensatory damages)32 ; Bigham, 95-STA-37 (ARB 9/5/96) (wherein the Board increased the ALJ's award of


[Page 20]

compensatory damages from $2,500 to $20,000 after reviewing the observations and accounts of complainant's emotional distress)33 ; Creekmore, supra (wherein the Board upheld this Judge's award of $40,000 after reviewing complainant's evidence of emotional distress)34 ; Gaballa v. Atlantic Group, Inc., 94-ERA-9 (Sec'y 1/18/96) (wherein the Secretary reduced the ALJ's recommended compensatory damage award from $75,000 to $25,000)35 ; Blackburn v. Metric Constructors, Inc., 86-ERA-4 (Sec'y 8/16/93) (wherein the Secretary reduced the ALJ's recommended award of compensatory damages to 5,000)36 ; Marcus v. United States Environmental Protection Agency, 92-TSC-5 (ALJ 12/3/92) (adopted by Sec'y 2/7/94) (wherein the Secretary adopted the ALJ's recommended compensatory damages award in the amount of $50,000)37 ; Lederhaus v. Paschen, 91-ERA-13 (Sec'y 10/26/92) (wherein the Secretary reduced the compensatory award from a recommended amount of $20,000 to $10,000)38 ; McCuistion v. Tennessee Valley Auth., 89-ERA-6 (Sec'y 11/13/91) (wherein the Secretary increased compensatory damages from the ALJ's recommended award of to $10,000)39 ; Johnson v. Old Dominion Security, 86-CAA-3/4/5 (Sec'y 5/29/91) (wherein the Secretary affirmed the ALJ's recommendation of $2,500 in compensatory damages as to two of the complainants and reduced the third complainant's compensatory damage award to $2,500).40

    The only evidence of record this Judge has pertaining to compensatory damages is a letter from Charles Goldstein, L.I.S.C.W., D.C.S.W., to Attorney Salisbury dated May 28, 1997. (ALJ EX 8F) The letter indicates Complainant's "symptoms include: feeling worthless, fatigued, having difficulty concentrating, difficulty falling and remaining asleep, decreased appetite including a weight loss of 18 pounds over the past three months, increased irritability, and feelings of hopelessness." Mr. Goldstein attributes the "root cause" of Complainant's depression to be stress at work and notes the March 31 warnings have had a deleterious effect upon Complainant's condition. Mr. Goldstein concludes with a diagnosis of Major Depression.

    I pause to note that Mr. Goldstein did not appear at hearing to testify as to his assessment of Complainant's condition. I hasten to add, however, that Respondent has not objected to the document's admittance as an exhibit and/or the fact that it would not have the opportunity to cross-examine. Accordingly, this Judge accepts Mr. Goldstein's letter as evidence of Complainant's major depression and its manifestations.

    While this Judge accepts Mr. Goldstein's evaluation and diagnosis of Complainant, I find and conclude it offers little value in fashioning an appropriate compensatory damage award. See Generally Willy v. Coastal Corp. and Coastal States Management Co., 85-CAA-1 (ALJ 5/8/97) (wherein the ALJ recommended a modest award


[Page 21]

of compensatory damages where it was clear from the circumstances that complainant suffered damages but there was scant testimony or documentation to quantify the scope of that damage). The bareboned assessment of Complainant's condition is little more than a recitation of text book symptoms of Major Depression. The record lacks descriptive evidence which would make this Complainant's distress lucid in this Judge's eye. Instead, I am left with a black and white portrait. Accordingly, this Judge finds and concludes a compensatory damage award in the amount of ,500.00 is appropriate in this case.

Attorney's Fee

    In calculating attorney fees under the CAA, 42 U.S.C. §7622(b)(2)(B)(ii), it is usual to use the lodestar method which requires multiplying the number of hours reasonably expended in bringing the litigation by a reasonable hourly rate. In this regard, see generally Clay v. Castle Coal and Oil Co., Inc., 90-STA-37 (6/3/94), at p. 4. The fee petition must be based on records providing details of specific activity taken by counsel and indicating the date, time and duration necessary to accomplish the specific activity. Sutherland v. Spray Sys. Envtl., 95-CAA-1 (ARB 7/9/96); West v. Sys. Applications Int'l, 94-CAA-15 (Sec'y 4/19/95). In addition to an attorney's fee for services, a successful complainant is entitled to reimbursement of the costs in bringing and prosecuting the complaint. Hoffman, supra, at p. 5.

    Attorney Salisbury has personally expended 53.50 hours on this matter at a rate of $225.00 per hour and an associate in his firm has expended 38.75 hours at $175.00 per hour. He sufficiently identifies these services as being performed on various tasks, such as consultation with and correspondence to the Complainant, preparation for and attendance at hearing research of the law and review of the evidence, and preparation of a post-hearing brief. Attorney Salisbury also seeks expenses in the amount of ,269.45 and submits, in conjunction with his fee petition, substantiating invoices for these expenses.

    Respondent has failed to submit any objection to the fees and expenses requested. Accordingly, the fee petition as submitted is hereby approved.

ORDER

    Based upon the foregoing findings of fact, conclusions of law and upon the entire record, I RECOMMEND Complainant, Theodorus J. Fabricius, be awarded the following remedy:

1) Compensation for the one day Complainant was suspended without pay relative to the tardiness warning;


[Page 22]

2) remuneration for the cost of obtaining medical treatment and medications for his emotional upset caused by Respondent's wrongful conduct and medical treatment for Complainant's exposure to asbestos;
3) replacement of Complainant's clothing contaminated with asbestos;
4) compensatory damages in the amount of ,500.00;
5) attorneys fees in the amount of $20,088.20.

It is FURTHER RECOMMENDED that

1) Respondent shall expunge Complainant's personnel file of the warning notice and disciplinary notice issued on March 31, 1997;
2) Respondent shall immediately expunge from Complainant's personnel record any negative reference relative to his protected activity;
3) Respondent shall immediately cease and desist its discriminatory treatment and harassment of Complainant;
4) Respondent shall properly dispose of Complainant's contaminated clothing; and
5) Respondent shall post a written notice in a centrally located area frequented by most, if not all, of Respondent's employees for a period of thirty (30) days, advising its employees that the disciplinary action taken against Complainant has been expunged from his personnel record and that Complainant's complaint has been decided in his favor.

      DAVID W. DI NARDI
      Administrative Law Judge


[Page 23]

NOTICE: This Recommended Decision and Order and the administrative file in this matter will be forwarded for review to the Administrative Review Board, U.S. Department of Labor, Frances Perkins Building, Room S-4309, 200 Constitution Avenue, NW, Washington D.C. 20210. The Administrative Review Board is the authority vested with the responsibility of rendering a final decision in this matter in accordance with 29 C.F.R. Part 24.6, pursuant to Secretary's Order 2-96, 61 Federal Register 19978 (May 3, 1996).

Boston, Massachusetts
DWD:jw

[ENDNOTES]

1Mr. Gray was not present when the orders were given concerning the work to be done at the bathhouse. He states that he would, as a junior employee, follow those instructions as relayed to him through Mr. Greene and Complainant. Generally, his understanding was that the employees were at the bathhouse to "gut the place." (TR 124)

2Mr. Graziano had a two-way radio mounted in his truck and carried a portable two-way radio.

3This testimony is confirmed by that of Mr. Graziano and Mr. Hedlund. (TR 271, 358) Mr. D. Graziano, whose testimony is discussed later, similarly testified that he does not think Complainant deviated at all from the work that he was doing for the Town or at least from the route that he would take to return to the Park Department garage. (TR 200)

4According to Mr. Gray, the two gentlemen had a conversation about what Complainant was going to do and Mr. Gray testified he "absolutely" thought it was a good idea. (TR 130)

5Mr. Forsberg appeared at hearing and his testimony will be discussed.

6Mr. Gray estimates Complainant was in the Building Inspector's office approximately five (5) minutes.

7Mr. Gray similarly testified he did not see Mr. Graziano at the Park Department garage on that afternoon.

8Mr. Graziano admits to a conversation during which going back in to the bathhouse was discussed, but states that no one was ever instructed to go back in there. (TR 355) According to Mr. Graziano, he approached Complainant shortly after 7:00 a.m. on March 26 to question Complainant as to why he did not contact Mr. Graziano. Mr. Graziano testified he did not instruct Complainant, or any other employee for that matter, to return to the bathhouse on that day and denies giving any direction to Complainant to check in before he went from one job site to another. (TR 342) He states the instruction was for Complainant to refrain from conducting any kind of personal business during town time without a supervisor knowing beforehand. Mr. Hedlund is not aware of any supervisor instructing employees to go back into the Sunset Lake bath house subsequent to Complainant raising his concern.

9Mr. Gray recalls Complainant walking by, shaking his head, and saying he could not believe they were sending him back up there. (TR 132)

10The testimony varies widely on what transpired in the office on this occasion. Mr. Hedlund describes Complainant and Mr. Greene looking at the plans in the office on March 26 and states that he was at his desk and Mr. Graziano was at his desk. According to Mr. Hedlund, neither Complainant nor Mr. Greene spoke a word, other than asking if the plans were in the office, and Mr. Greene pointed to the lower right corner of the plans and the two men left without saying a word and without making a copy of the plans.

11After four written warnings for the same transgression an employee could be terminated. (TR 82)

12Complainant received a one day suspension without pay for this disciplinary notice.

13Complainant testified he also consulted Dr. Eric Cohen of Quincy. Doctor Cohen ran some pulmonary tests and took some x-rays.

14Mr. Gray has received one warning in the past, perhaps three or four months prior to this incident, for tardiness. (TR 133) Mr. Gray did not grieve that warning.

15Upon redirect, Mr. Galewski states when he looked at the material he was not convinced that it was asbestos, but was suspicious enough to send it out for testing. (TR 182)

16Both Mr. Hedlund and Mr. Graziano testified that they had both been in the bathhouse themselves numerous times and had never thought about the possibility of asbestos. Mr. Graziano also notes that he never saw the plans and did not even know that they were on Mr. Hedlund's desk.

17Mr. Hedlund testified the ceiling was not part of the work orders on March 24 and 25 even though the inside was going to be gutted. (TR 253, 304) Later in his testimony, however, Mr. Hedlund states that it was discussed, but not directed. (TR 299-300)

18Respondent suggests "At issue is whether Complainant notified the appropriate authorities and whether he acted like a reasonably prudent person in reporting to other than his superior." See RX 6 , at p. 3.

19Mr. Graziano confirms Mr. Hedlund's testimony as to the existence of a policy within the department that employees who wish to perform personal tasks while they are on the job must first contact their supervisor.

20According to Mr. Hedlund, these monthly schedules contain reminders for employees as to proper procedure and the conduct of their on-the-job work responsibilities. (TR 324)

21Mr. Graziano states Complainant can take a lunch break at any time he wants and that he can take a coffee break too. (TR 347) Coffee breaks are set at 9:00 to 9:20 a.m. and 1:30 to 1:50 p.m. Lunch is at 11:00 to 11:30 a.m. (TR 368)

22In comparison, Complainant's visit to the OSHA office to deliver his complaint, assuming it occurred on Town time, might arguably have amounted to personal business in violation of the claimed policy/procedure. Mr. Hedlund testified at hearing, however, that this delivery to the OSHA office was not a part of the March 31 warning notice. (TR 289; ALJ EX 9G) The reason Complainant never received a written warning for this visit to the OSHA office, in light of Respondent's claimed policy/procedure, remains unexplained.

23Mr. Hedlund states he was embarrassed when he first heard about the possible asbestos on the afternoon of March 25 because he likes control. (TR 252) This embarrassment as explanation for the unfolding actions, however, is rendered unlikely given Mr. Hedlund's subsequent discounting of this embarrassment by his testimony that it is "not the first time that embarrassment's [sic] occurred in the public section [sic]." (TR 252-253)

24A matter of only about twenty minutes expired between Complainant's stop at the Town offices and the time that Mr. Hedlund learned of the suspected asbestos problem from Mr. Galewski.

25There was, however, one instance when Complainant dialed 911 in regards to an accident on the Town golf course (TR 106)

26I stress the nature of this proceeding because Respondent has referred to key tort principles such as a reasonably prudent person and its knowledge of the asbestos.

27For example, a respondent's clear cut knowledge of a violation of the Clean Air Act and its failure to remedy that violation until a whistleblower engages in protected activity might support an inference that the respondent had no intention of remedying the violation and that respondent discriminated against the whistleblower for exposing a violation that it had, until that point, managed to keep under wraps.

28Mr. Hedlund states that more than half of these instances were less then ten minutes. (TR 242)

29I question whether this employee's lateness by the one, two, three and perhaps even the four minute periods should reasonably be classified as tardiness at all. Such a harsh result would lead to the ridiculous requirement that Complainant's watch be in precise sync with the time clock at work.

30Reference to the dual motive analysis at p. 4 of Respondent's brief is premature, as this Judge only reaches the dual motive analysis if I determine there is legitimacy to Respondent's stated reasons for the adverse employment action.

31If Complainant were to be terminated for invalid reasons, i.e., his protected activity, that may properly be the ground for a new complaint.

32The evidence which supported an award in this amount consisted of complainant consulting physicians who prescribed anxiety and depression medications, as well as other medications for chest pain; a treating psychologist testified that respondent's discriminatory acts caused complainant's anxiety disorder and post-traumatic stress disorder and respondent failed to offer any countervailing evidence on causation; and that same psychologist testified complainant's wife and children noticed a radical change in complainant's behavior, a serious strain in the marital relationship, and that divorce proceedings were begun, although the couple did eventually reconcile.

33At hearing, complainant testified to his lowered self-esteem and uncommunicativeness, to his change in sleep and eating habits, and to the adverse effect on his marriage. He also testified that he was not interested in socializing, felt 'less than a man' because he could not support his family, and that the family experienced a sparse Christmas. Finally, complainant testified the family had to cancel their annual summer vacation and charge the credit cards to the limit. Complainant's wife testified she noticed complainant's withdrawal in the weeks after Christmas.

34In Creekmore, the Board noted ample evidence which justified an award of substantial compensatory damages. The Board specified complainant's credible testimony that his layoff caused him embarrassment in seeking a new job, emotional turmoil due to the disruption to his family life brought on by his temporary consulting work and eventual relocation, and panic about being able to meet his financial obligations. The Board stated that although it had reservations about whether complainant's heart attack was the "natural sequela" of his layoff, it held an award of $40,000 was nevertheless justified in light of the demonstrated panic, embarrassment, pain and suffering.

35The ALJ recommended a $75,000 compensatory damage award based on the treating psychologist's finding that complainant suffered from chronic stress, paranoid thinking, a general distrust of others, a lack of confidence in his engineering judgment, a fear of continuing repercussions, and a general feeling of apathy. The psychologist further testified complainant will forever suffer from a full-blown personality disorder and a permanent strain on his marital relationship. The Secretary reduced the award based on the fact that the same psychologist indicated this psychological state was caused in part by a co-respondent who had previously settled out of the case and that part of that settlement compensated for part of complainant's compensatory damages.

36The testimony of complainant, his wife, and his dad established complainant was of the opinion that firing someone was like saying that person is no good. The evidence also established complainant felt really in a low and that he relied on his dad to come out of depression. The termination affected complainant's self-image and impacted his behavior, which became short with his wife. The wife testified to the stress and emotional strain on the marital relationship and the father testified to complainant's pride and work ethic and the fact that complainant felt sorry for himself after the termination.

37This award rested on complainant's testimony that bringing the case had disrupted his home life, that his children's college plans were changed because of the financial burden of unemployment, that he gained weight and developed a blood pressure problem, that his stomach was in an uproar, and that he had feelings of great depression. In addition, complainant testified to an incident where he was physically grabbed by agents of the respondent and that he felt like a criminal because of these agents' aggressive and intimidating behavior. Finally, complainant testified that he suffered harm to his reputation caused by respondent distributing to other supervisors information stating complainant's behavior was violent and aggressive.

38In Lederhaus, the evidence established complainant remained unemployed for 5 months after his termination, he was harassed by bill collectors, foreclosure was begun on his home and he was forced to borrow $25,000 to save the house. In addition, complainant's wife received calls at work from bill collectors and her employer threatened to lay her off. Complainant had to borrow gas money to get to an unemployment hearing and experienced feelings of depression and anger. Complainant fought with his wife and would not attend her birthday party because he was ashamed he could not buy her a gift, the family did not have their usual Christmas dinner, and complainant would not go to visit his grandson. In fact, complainant cut off almost all contact with his grandson. The evidence revealed complainant became difficult to deal with and this was corroborated by testimony from complainant's wife and a neighbor. Complainant contemplated suicide twice.

39The evidence revealed the complainant was harassed, blacklisted, and fired. In addition, complainant lost his livelihood, he could not find another job, and he forfeited his life, dental and health insurance. The blacklisting and termination exacerbated complainant's pre-existing hypertension and caused frequent stomach problems necessitating treatment, medication, and emergency room admission on at least one occasion. Complainant experienced problems sleeping at night, exhaustion, depression, and anxiety. Complainant introduced into evidence medical documentation of symptoms, including blood pressure, stomach problems, and anxiety. Complainant's wife corroborated his complaints of sleeplessness and testified he became easily upset, withdrawn, and obsessive abut his blood pressure.

40The evidence support an award in this amount where the complainant sustained prolonged exposure to chemical substances that adversely effected their health, at least one of the substances was carcinogenic, and the complainants experienced ongoing anxiety about symptoms and frustration at the employer's inaction. In addition, the complainants were stonewalled and harassed and forced to live in economic uncertainty occasioned by their termination.



Phone Numbers