skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

IOWA DEPARTMENT OF TRANSPORTATION, WAB No. 94-11 (WAB Oct. 7, 1994)


CCASE: IOWA DEPARTMENT OF TRANSPORTATION DDATE: 19941007 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D.C. In the Matter of: IOWA DEPARTMENT WAB CASE NO. 94-11 OF TRANSPORTATION With respect to the applicability of an updated Davis-Bacon wage determination to construction of the new Burlington Bridge (U.S.34) over the Mississippi River at Burlington, Iowa BEFORE: David A. O'Brien, Chair Ruth E. Peters, Member Karl J. Sandstrom, Member DATED: October 7, 1994 DECISION OF THE WAGE APPEALS BOARD This matter is before the Wage Appeals Board pursuant to 29 C.F.R. [sec] 7.9 on the petition of the Iowa Department of Transportation ("IDOT") seeking review of a May 5, 1994 ruling issued by the Deputy Assistant Administrator, Wage and Hour Division, of the Department of Labor ("Administrator"), relating to an extra work order on a construction contract for a new bridge over the Mississippi River at Burlington, Iowa. In that ruling the Administrator determined that the work order issued by IDOT requiring the performance of additional demolition work on the old bridge constituted "a separate contract for Davis-Bacon purposes." See Record, Tab A-1. IDOT was therefore, ordered to incorporate a current Davis- Bacon wage determination to apply to the demolition work performed pursuant to that extra work order. The Federal Highway Administration ("FHWA") intervened on behalf of IDOT and the National Joint Heavy and Highway Construction Committee intervened in support of the Administrator's decision. For the reasons stated below the ruling of the Administrator is affirmed.[1] ~2 [2] I. BACKGROUND On June 29, 1990, IDOT awarded two contracts to Edward Kraemer & Sons, Inc. ("Kraemer") in connection with the construction of a new bridge over the Mississippi river at Burlington, Iowa. One contract was for the construction of the new bridge ("construction contract"). The second contract, BRF 34-9-(60)-38-29 ("approach contract"), required the removal of approximately 1151 linear feet of the Iowa approach structure to the old MacArthur Bridge, including demolition of the approach ramp structure and removal of part of the through truss section. The plans for the approach contract required removal of two piers and construction of a temporary pier to support the remaining truss section. The total costs of these two contracts was $30,561,000. The original project plans provided for the award of a third contract to remove the remaining portion of the old bridge ("demolition contract"). Bid opening date for this contract was scheduled for May 3, 1994 and the estimated cost of this final contract was $1,095,000. Based upon environmental concerns and because of possible substructure damage resulting from the 1993 floods IDOT elected to have Kraemer remove an additional 915 feet of the truss superstructure as an additional work order under the approach contract, as opposed to performing that work under the demolition contract as originally planned. On October 6, 1993 IDOT issued the work order requiring Kraemer "to remove the existing truss superstructure above the piers from the limit of removal specified in the original contract to Pier 5 of the MacArthur Bridge." Kraemer was to be compensated an additional $636,000 pursuant to the new work order. The Administrator found that the new work order substantially modified the original approach contract and ordered that an updated wage determination be applied. The Administrator stated that "when a contract for construction is substantially modified or amended in such a manner that the changed contract becomes a new contract for application of the labor standards statutes then an updated wage determination must be applied to the additional construction activity." The Administrator based this finding on the significant monetary value of the $636,000 extra work order, the actual amount of physical construction work required, the fact that the work was originally to be performed under the demolition contract and that the new work order was issued over three years after the award of the original approach contract. II. DISCUSSION The Davis-Bacon and Related Acts ("DBRA") were adopted to protect the laborers and mechanics employed on federally-funded and assisted contracts. Prevailing wages must be paid to laborers and mechanics on such construction [2]] ~3 [3] projects. Universities Research Assn., Inc. v. Coutu, 450 U.S. 754 (1981). The very concept of a prevailing wage necessarily encompasses a current wage. A wage simply cannot be prevailing if it is outdated. See Modernization of the John F. Kennedy Federal Building, WAB Case No. 94-09 (Aug. 19, 1994). The only legitimate reason for not including the most recently issued wage determination in a contract is based upon disruption of the procurement process. See 47 Fed. Reg. 23646 (May 28, 1982). In this case the original approach contract incorporated the most recent wage determination available at the time it was awarded on June 29, 1990. The extra work order was issued on October 6, 1993, after an updated wage determination had been published. IDOT argued in its Statement in Support of Petition for Review that 29 C.F.R. 1.6 contains two exceptions to the general rule that a wage determination remains effective throughout the life of a contract, neither of which was applicable to the extra work order issued in this case. Therefore, IDOT reasoned, the wage determination issued in conjunction with the original contract must remain valid for work performed pursuant to the extra work order. IDOT's argument must fail for a number of reasons. First, because it violates DBRA policy by incorporating an outdated wage determination. Secondly, because it violates that policy in a situation in which adherence to the policy will not disrupt the procurement process. And finally, because the Administrator's reasonable interpretation of the DBRA implementing regulations is that a previously awarded contract that has been "substantially" modified must be treated as a "new" contract in which the most recently issued wage determination is applied. See the ruling letters attached by the Administrator to the Statement in Opposition to Petition for Review. The Secretary's regulations state that a new or modified wage determination published after contract award, or after the start of construction where there is no contract award, shall not be effective. 29 C.F.R. 1.6(c)(3)(vi). The ruling letters cited by the Administrator clearly show that this regulation has been interpreted not to include situations in which the original contract has been "substantially" changed. Extra work orders which "substantially" change the original contract are considered "new" contracts for DBRA purposes. The Administrator's interpretation of the regulation is entirely reasonable given that the substantially changed portion of the contract is not in any respect "awarded" until the issuance of the extra work order.<1> The Administrator's interpretation is supported in analogous situations by All Agency Memorandum ("AAM") No. 157 and the decisions of the Comptroller General.[3] ~4 [4] AAM No. 157 specifically clarifies the application of Davis-Bacon wage determinations to contracts that contain option clauses. Therefore, AAM No. 157 is not right on point, but does contain language which supports the Administrator's policy of applying new wage determinations to "substantial" extra work orders. The relevant portion of AAM No. 157 states that "a provision to extend an existing contract -- pursuant to an option clause or otherwise -- so that the construction is performed over an extended period of time (as opposed to situations where a contractor is given additional time to complete its original contract commitment), must include a current Davis-Bacon wage determination." The modified contract is considered a "new" contract pursuant to AAM No. 157 because it "requires a contractor to perform work for a period of time for which it would not have been obligated -- and for which the government would not have been required to pay -- under the terms of the original contract." Both IDOT and FHWA argued pursuant to AAM No. 157 that the extra work order in this case did not extend the length of the original contract. At oral argument counsel for IDOT admitted that the original contract did not contain a set completion date. Therefore, the argument that the length of the contract was not extended due to the extra work order is irrelevant and disingenuous. The contractor did not get an additional $636,000 for nothing. That amount of money pays for a substantial amount of physical construction work for which the contractor would otherwise have not been obligated.<2> Whatever the anticipated length of time was for completion of the approach and construction contracts, that time period must have been extended, or considerable overtime undertaken, in order for the extra work to be completed. In an analogous situation under federal procurement policy the Comptroller General has held that "an existing contract may not be expanded so as to include additional work of any considerable magnitude, unless it clearly appears that the additional work was not contemplated at the time the original contract was entered and is such an inseparable part of the original work that it is reasonably impossible of performance by any other contractor." 5 Comp. Gen. 508 (1926). The work required under the extra work order in this case was originally to be performed under the demolition contract. Thus, the work in question was clearly contemplated at the time of the original contract. The fact that the demolition contract had to be awarded to the lowest bidder, whether or not that happened to be Kraemer, shows that the work could have been performed by another contractor.[4] ~5 [5] Counsel for IDOT conceded at oral argument that a "substantially" changed contract should include an updated wage determination. He went on to argue that the $636,000 cost of the extra work order in this case is not "substantial" when compared to the more than 30.5 million dollar cost of the combined approach and construction contracts. The approach and construction contracts were referred to as "tied contracts." The record is unclear as to what extent these two contracts were "tied" together. However, the extra work order only applies to the approach contract and makes no reference to the construction contract. We find that the only appropriate comparison is to the actual contract being modified. The record does not reflect an exact breakdown of the cost of the approach contract. However, common sense dictates and counsel for IDOT confirmed at oral argument, that the vast majority of the more than 30.5 million dollar figure is for performance pursuant to the construction contract. Therefore, we find that regardless of how you define "substantial" in this case, i.e. as a determination made by comparing the cost of the change to the cost of the original contract, or by examining the $636,000 on its own, the extra work order in this situation was so "substantial" as to be considered a new contract for Davis-Bacon wage determination purposes. A review of the actual work order itself also provides ample evidence of the substantial nature of the work to be performed. In the upper right hand corner of the IDOT form for a "change or extra work order" is a space to be marked to indicate whether the work order is "Non-Substantial" or "Substantial." The work order is marked Substantial. IDOT argued at oral argument that the exact nature of what is meant by this portion of the form is unclear from the record and this is no doubt true. However, if IDOT is going to come before this Board and submit one of its own pre-printed forms as evidence, without elaborating on a key portion of the form, we have no hesitation whatsoever in reading that unexplained portion of the form against IDOT. Alone and without explanation the notation that the work order was considered "substantial," for whatever reason, by the person filling out the form is certainly not dispositive, but just as certainly it is relevant and probative. Another reason the IDOT form is helpful in determining the substantial versus non- substantial nature of the extra work order is based upon the regulations of FHWA. 23 C.F.R.  635.120 mandates that "Following authorization to proceed with a project, all major changes in the plans and contract provisions and all major extra work shall have formal approval by the Division Administrator in advance of their effective dates." The extra work order in question was deemed to be a major change in the original contract by FHWA which required approval of the Division Administrator, Daniel Fuchs. "Major change or major extra work" is defined by 23 C.F.R. [sec] 635.101 as [5] ~6 [6] meaning "a change which will significantly affect the cost of the project to the Federal Government or alter the termini, character or scope of the work." Since IDOT considered the extra work to be, as indicated on its form anyway, "substantial" and FHWA considered it to be "major" we do not see how the Administrator could have erred in determining the extra work order to be substantial. The Administrator's decision notes the age of the original contract in determining whether or not the extra work order is considered a new contract. IDOT states that the age of the original contract is "completely irrelevant." The Administrator did not attempt to determine the substantial versus non-substantial nature of the extra work order based upon this information. A review of the length of time between the award of the original contract and the date of the extra work order is appropriate in the sense that the older the original contract is the more circumspect the extra work order becomes. Therefore, the Administrator's reference to the length of time between the original contract and the extra work order was appropriate. III. CONCLUSION Reversal of the Administrator's decision in this case would create a gaping loophole in the enforcement of the DBRA prevailing wage laws. Contracting agencies could enter into contracts which would, for example, name a contractor to perform all highway repair in the state of Iowa for the next five, ten, or more years with each new job being authorized as an extra work order under a wage determination locked in at the time of the original contract award. The policy and purpose of the Davis-Bacon prevailing wage law would be lost in a flood of extra work orders. As long as workers on federally funded and assisted construction contracts are required to be paid prevailing wages this cannot be allowed to happen. A contract that has been "substantially" modified must be treated as a "new" contract in which the most recently issued wage determination is applied. The decision of the Administrator is affirmed. BY ORDER OF THE BOARD: David A. O'Brien, Chair Ruth E. Peters, Member Karl J. Sandstrom, Member Gerald F. Krizan, Esq. Executive Secretary[6] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ <UL>FOOTNOTES</UL> <1> For a discussion of what it means to "award" a contract See Modernization of the John F. Kennedy Federal Building, supra. <2> The Administrator made a specific factual finding, which was not disputed by IDOT, that a significant amount of physical construction work was required under the extra work order. See p.2 of the Administrator's May 5, 1994 ruling.



Phone Numbers