skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

MODERNIZATION OF THE JOHN F. KENNEDY FEDERAL BUILDING, WAB No. 94-09 (WAB Aug. 19, 1994)


CCASE: MODERNIZATION OF THE JFK FEDERAL BUILDING, DDATE: 19940819 TTEXT: ~1 WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D.C. In the Matter of: MODERNIZATION OF WAB CASE NO. 94-09 THE JOHN F. KENNEDY FEDERAL BUILDING, BOSTON, MASSACHUSETTS Application of Wage Decision No. MA93-1, Modification No. 2 BEFORE: David A. O'Brien, Chair Ruth E. Peters, Member DATED: August 19, 1994 DECISION OF THE WAGE APPEALS BOARD This matter is before the Wage Appeals Board on the petition of the Building and Construction Trades Department, AFL-CIO; the International Brotherhood of Electrical Workers; and the International Brotherhood of Electrical Workers, Local No. 103 (collectively referred to as "Petitioners"), for review of a March 18, 1994 ruling by the Administrator of the Wage and Hour Division ("DOL"). In the ruling the Administrator denied the Petitioners' request to require the General Services Administration ("GSA") to incorporate all modifications to Wage Decision ("WD") No. MA91-1 that were published by DOL after exercise of the contract option for Phase II of the Modernization of the John F. Kennedy Federal Building, Boston, Massachusetts ("JFK project"), but before construction was commenced, including, but not limited to WD No. MA93-1, Modification No. 2, published on April 9, 1993. The United States Army has filed a petition for intervention in opposition to both the Petitioners and DOL. For all the reasons stated below, the matter is remanded to the Administrator for action consistent with this decision.[1] ~2 I. BACKGROUND This matter involves the exercise of a contract option by GSA pursuant to its agreement with the Suffolk Construction Company ("Suffolk") for Phase II of the JFK project. GSA awarded a contract to Suffolk on July 20, 1990 for Phase I of the project. The renovation was divided into three phases. On March 12, 1992, during construction on Phase I, GSA notified Suffolk of its intent to exercise an option for Suffolk to perform the renovations called for under Phase II of the project. GSA informed Suffolk on April 14, 1992 that performance was expected to commence on Phase II on April 15, 1993. At that time GSA informed Suffolk that the applicable wage determination for Phase II of the renovation project would be No. MA91-1 (Modification Nos. 1-17), dated March 20, 1992 ("MA91-1"). On April 9, 1993 DOL issued WD MA93-1, which reflected the rate applicable to electricians under a collective bargaining agreement between Local No. 103 and the Boston Chapter of the National Electrical Contractors Association, effective September 1, 1991 through August 31, 1993. Construction on Phase II of the JFK project began on May 17, 1993. On August 9, 1993 Local No. 103 asked DOL to determine that GSA should have incorporated WD MA93-1, rather than WD MA91-1 in Phase II of the project. In support of this request Local No. 103 argued that because construction of Phase II was not to begin for over a year after exercise of the option, the contract should contain the newest wage determination in effect at commencement of construction. Local No. 103 urged, by analogy, that 29 C.F.R. [sec]1.6(c)(3)(iv) was intended to protect employees from the adverse impact delays of more than 90 days could have on prevailing wages. On March 18, 1994 DOL denied Local 103's request and rejected the contention that the exercise of an option is analogous to the grant of a negotiated, non-competitively bid contract. Instead, DOL likened the case to those situations where a wage determination is properly incorporated in a contract at the time of a competitively bid award, but where considerable lag time exists before actual construction begins. Therefore, DOL found that WD MA91-1, the wage determination in existence at the time GSA exercised the option on Phase II, set out the appropriate wage rate. The DOL cited All Agency Memorandum ("AAM") No. 157), which sets forth an allegedly long-standing policy that equates the exercise of an option clause in a contract with the award of the contract. DOL noted that 29 C.F.R. [sec] 1.6(c)(3) provides that modifications to wage determinations may be effective only if received prior to contract award. DOL found that none of the exceptions to the general rule contained in 29 C.F.R. [sec]1.6(c)(3) requires GSA to use MA93-1 in Phase II of the project pursuant to the application for a wage decision modification after contract award.[2] ~3 [3] The United States Army has intervened to argue that neither WD MA91-1, nor WD MA93-1 is the appropriate wage determination. The Army argues that AAM No. 157 is invalid and that the policy it purports to promulgate is legally erroneous. The invalidity of AAM No. 157 is allegedly based upon violations of the Administrative Procedure Act in the adoption of the memorandum. The Army states that the appropriate wage determination for Phase II of the project is the same wage determination as incorporated in Phase I of the project, WD MA90-1. The Army points out that "unless otherwise expressed in the contract or a particular statute, the exercise of an option comprises an extension of the terms of the original contract" and as set out in the Federal Acquisition Regulations ("FAR") 48 C.F.R. [sec] 22.404-1(a)(1) "[o]nce incorporated in a contract, a general wage determination normally remains effective for the life of the contract." II. DISCUSSION A. The Petition for Intervention by the United States Army The Army concedes that the specific terms of a contract could treat the exercise of an option under that contract as the start of a new contract. See Intervenor's Statement in Opposition to Petitioners, page 13. Paragraph 2.03, OPTION TO EXTEND TERM OF THE CONTRACT, page 77 of the contract at issue, states that "[a]t the time of exercise of an option, current wage rates will be incorporated into the option." Wage determination WD MA 90-1 should not apply because the very language of the contract dictates that "current wage rates" will apply upon exercise of the Phase II option. Therefore, despite any potentially favorable decision with regard to the Army's argument that AAM No. 157 is invalid and/or legally erroneous, GSA incorporated the correct current wage determination at the time the Phase II option was exercised. We therefore, decline to rule on the Army's allegation that AAM No. 157 is invalid and/or legally erroneous.<1> The Army's petition to intervene is granted, but the relief requested therein is denied.[3] ~4 [4] B. The Administrator's decision In issuing her decision the Administrator relied primarily on AAM No. 157 which provides, in pertinent part, that: [T]he exercise of such an option requires a contractor to perform work for a period of time for which it would not have been obligated -- and for which the government would not have been required to pay -- under the terms of the original contract if the option had not been exercised. Thus, once the option on a contract is exercised, the additional period of performance becomes a new contract. As interpreted by the Administrator this language provides that the exercise of an option is equivalent to the "award" of a contract. See Statement of the Administrator, page 5. The Administrator also argues that in an analogous situation under the McNamara-O'Hara Service Contract Act the exercise of an option on a multi-year service contract is equivalent to the "award " of a contract. The Administrator cites 29 C.F.R. [sec] 4.143 which states that: Also, whenever the term of an existing contract is extended, pursuant to an option clause or otherwise, so that the contractor furnishes services over an extended period of time, rather than being granted extra time to fulfill his original commitment, the contract extension is considered to be a new contract for purposes of the application of the Act's provisions. All such "new" contracts as discussed above require the insertion of a new or revised wage determination in the contract as provided in [sec] 4.5. The Board notes that neither provision cited by the Administrator states that the exercise of an option is equivalent to the "award" of a contract. The cited provisions only state that the exercise of an option is equivalent to a "new" contract. The code section cited by the Administrator as controlling, 29 C.F.R. [sec] 1.6(c)(3), states that: All actions modifying a general wage determination shall be effective with respect to any project to which the determination applies, if notice of such action is published before "contract award" (or the start of construction where there is no "contract award"). . . . (emphasis added). Here the option was exercised on April 14, 1992, but construction did not begin until May 17, 1993. In the meantime a new wage decision was issued, WD MA93-1, on April 9, 1993.[4] ~5 [5] If the Administrator's interpretation of AAM No. 157 is correct the exercise of an option would be the same as the "award" of a contract and the appropriate wage determination would be WD MA91-1 because that was the wage determination in effect at the time of the "award" of the Phase II contract. On the other hand, if the exercise of an option is not the equivalent of a "contract award," then WD MA93-1 would apply because, as far as Phase II is concerned, no contract would have been "awarded" and wage determination WD MA93-1 was implemented prior to the beginning of construction.<2> C. Davis-Bacon and Related Acts policy on prevailing wages The Davis-Bacon and Related Acts ("DBRA") were adopted to protect the laborers and mechanics employed on federally- funded and assisted contracts. Prevailing wages must be paid to laborers and mechanics on such construction projects. Universities Research Assn., Inc. v. Coutu, 450 U.S. 754 (1981). The very concept of a prevailing wage necessarily encompasses a current wage. A wage simply cannot be prevailing if it is outdated. In proposing 29 C.F.R. [sec] 1.6 the Secretary stated, after the notice and comment period closed on the second publication, that "DOL's policy has been that bid solicitations should contain the most recently issued determination of current prevailing wages which can be included without causing undue disruption of the procurement process." 47 Fed. Reg. 23646 (May 28, 1982). The Secretary's regulations address the problem of outdated wage rates in, at least, two different ways. First, new or modified wage determinations are effective if published before contract award, or the start of construction if there is no contract award. 29 C.F.R. [sec] 1.6(c)(3). Secondly, projects that are assisted under the National Housing Act or receive assistance pursuant to Section 8 of the U.S. Housing Act of 1937, situations in which competitive bidding does not usually take place, must include updated wage rates if construction is not begun within 90 days after initial endorsement of the agreement. 29 C.F.R. [sec] 1.6(c)(3)(iv). The reason for not including updated wage rates in all situations right up to the start of construction is based upon the disproportionate effect that varying wage rates would have on the bidding process. Changing the wage rate between bid opening and contract award would create a situation in which competing [5] ~6 [6] bidders could be treated differently. In order to assure fairness in the bidding process all contractors must submit their bids based upon the same wage rates. 29 C.F.R. [sec] 1.6(c)(2)(i)(A) also helps resolve the outdated wage rate problem by stating that modifications to wage determinations received less than 10 days before bid opening are still effective unless the contracting agency finds that it does not reasonably have enough time to notify bidders of the change. The priority the Secretary places on the need to have current wage rates in place is highlighted by this particular code section. Note that wage modifications received just 11 days before bid opening must be implemented and that wage modifications received even 1 day before bid opening can only be excluded upon a showing that there is not reasonable time still available to notify bidders. The Administrator compares the present case to a situation in which "a wage determination is properly incorporated in a contract at the time of award, and there may be considerable time lag before actual start of construction." (emphasis added). Petitioners compare the present case to a situation in which a negotiated, non-competitively bid contract is executed. The analogy presented by the Petitioners is right on point, while the analogy suggested by the Administrator depends on the assumption that the "award" of a contract is the equivalent of exercising a non-competitively bid option contained in a previously "awarded" contract. In the present case there was no competition for the new contract on Phase II of the JFK project. Therefore, incorporating the most current wage modification does not create an unfair situation among bidders. The Petitioners position is clearly supported by the underlying principals of the DBRA. In fact, DOL has even conceded that "[w]hile the policy urged by the petitioners may be laudable, they simply have no right to such a dramatic change in the absence of any clear statutory or regulatory basis." But, Petitioners do have such a regulatory basis if the term "contract award" as used in 29 C.F.R. [sec] 1.6(c)(3) is interpreted as not including the exercise of a non-competitively bid option contained in a previously "awarded" contract. D. Interpretation of 29 C.F.R. [sec] 1.6(c)(3) Petitioners are not arguing that AAM No. 157 is in any way invalid. In fact, Petitioners state that they "wholeheartedly agree" with the Administrator that modifications to contracts should be regarded as "new" contracts for wage determination purposes. See Petitioners Reply Memorandum, page 21. Therefore, Petitioners agree that GSA complied with the requirements of 29 C.F.R. [sec] 1.6(c)(3) by incorporating WD MA91-1 into the new Phase II construction contract. See Petition for Review, page 7. In the standard situation that decision by GSA would end the dispute because construction on Phase II [6] ~7 [7] would normally commence fairly soon after the exercise of the new contract. Certainly, if construction had begun prior to the issuance of WD MA93-1 on April 9, 1993 the question presented here would be moot. Since construction on Phase II of the JFK project did not begin until after the publication of WD MA93-1, the proper interpretation of [sec]1.6(c)(3) becomes the focal point of our analysis. A number of specific exceptions to the general rule stated in 29 C.F.R. [sec]1.6(c)(3) are set out in subparagraphs (i) through (vi) of that code section. Petitioners argue that an additional exception should be read into the subparagraphs of 29 C.F.R. [sec]1.6(c)(3) which would cover the unique situation in which an option is exercised such a long time prior to the start of construction. Petitioners point out that the policy of the DBRA would be better served if such an exception were to be adopted. The failure of the Secretary's regulations to cover this unique situation is asserted as a basis for the creation of an additional exception to [sec] 1.6(c)(3). We reject this argument for three reasons. First, where a general rule is followed by specific exceptions, the general rule must be followed if none of the exceptions apply. Second, creating such an exception as urged by the Petitioners would violate subparagraph (iv) of this code section which states that a modification to a wage determination shall not be effective if published after contract award, or the start of construction where there is no contract award. Third, the argument concedes that the exercise of an option is equivalent to the "award" of a contract because no exception would need to be applied if a contract was not "awarded" at the time of exercise of the option. The real issue, as identified by this Board, is the meaning of the term "contract award" in 29 C.F.R. [sec]1.6(c)(3). The Army argued persuasively in its Petition for Intervention that the exercise of an option is not the equivalent of the award of a new contract. The Army pointed out many distinctions between the exercise of an option and the award of a new contract, as follows: The initial formation of a new contract requires the meeting of the minds; it demands consensual acts by both parties and consideration. By contrast, the exercise of an option is a unilateral extension of the contract with the necessary consent of only one party. The consent of the party who must perform under the option is not required. . . . Under the control of federal procurement statutes, certificates of compliance with environmental laws, equal employment opportunities regulations, and procurement integrity requirements are essential only upon initial contract formation. These initial requirements need not be re-[7] ~8 [8] executed upon the exercise of an option. Furthermore, Small Business eligibility continues during options even if the business has outgrown its eligibility for other purposes and is no longer qualified for the program. Lastly, no additional competition is required before an option is exercised. In numerous provisions of FAR the term "contract award" is used in the context of executing a contract with a winning bidder. The exercise of an option is not referred to as the "award" of a contract. While these provisions are not controlling, they are instructive as to the intended meaning of the term "contract award" in the Secretary's regulations. FAR (at 48 C.F.R. [sec] 17.207(d)(3), Exercise of Options), refers to "[t]he time between the award of the contract containing the option and the exercise of the option. . . ." The Elements of Sealed Bidding (FAR at 48 C.F.R. [sec] 14.101 notes under the heading "(e) Contract Award" that "[a]fter bids are publicly opened, an award will be made with reasonable promptness to that responsible bidder whose bid, conforming to the invitation for bids, will be most advantageous to the Government, considering only price and the price-related factors included in the invitation." Webster's New World Dictionary defines award in the context applicable to this case as "to give as the result of judging the relative merits of those in competition." Blacks Law Dictionary notes that "[o]ne awards a contract to a bidder. Jackson v. State, 194 Ind. 130, 142 N.E. 1, 2, (holding that a finding that a contract was `awarded to' a bidder meant it was entered into with all required legal formalities)." (Emphasis in original). The use of the term "contract award" in 29 C.F.R. [sec]1.6(c)(3) would seem to include the notion of executing a contract with a winning bidder. The interpretation of the term "contract award" as not including the exercise of a non- competitively bid option contained in a previously "awarded" contract is further supported by a Comptroller General's Decision, that while not controlling, is right on point. When faced with the question of whether or not the exercise of an option was the equivalent of the award of a contract, the Comptroller General stated that: The FAR defines an option as a "unilateral right in a contract by which for a specified time, the government may elect to purchase additional supplies or services called for by the contract, or may elect to extend the term of the contract." 48 C.F.R. [sec] 17.201. . . . Thus, while for certain purposes the exercise of an option is in effect considered a contract award, see, e.g. 29 C.F.R. [sec] 4.4(a)(1) (1986) (involving the Service Contract Act), the exercise of an option is essentially no more than the [8] ~9 [9] government's taking advantage of a right it possesses under an existing contract, rather than the award of a new one." Matter of Action Manufacturing Company, 66 Comp. Gen. 463, 467 (May 15, 1987). The reasoning of the Comptroller General, if adopted by the DOL, would further the policy of the DBRA to incorporate "the most recently issued determination of prevailing wages which can be included without causing undue disruption of the procurement process." 47 Fed. Reg. 23646 (May 28, 1982). Since the Administrator has not yet had the opportunity to consider the meaning of the term "contract award" in 29 C.F.R. [sec] 1.6(c)(3) as set out above and because the Petitioners never made this precise argument to the Board as a basis for reversing the Administrator's original ruling<3> , we remand this matter to the Administrator for consideration of the exact meaning of the term "contract award" contained in 29 C.F.R. [sec]1.6(c)(3). We direct the Administrator to give the Petitioners an opportunity to address this issue prior to entry of her decision after remand. E. The timeliness of Petitioners' challenge Although not raised directly in its brief, at oral argument DOL raised the issue of Petitioners' timeliness in seeking to challenge the JFK Phase II wage determination. We address the issue because, depending on the Administrator's decision as to the proper interpretation of the term "contract award," the issue may need to be addressed on remand. A long line of Wage Appeals Board decisions from Ganada Development Corp., WAB Case Nos. 73-03 and 74-01 (May 14, 1977) through Harper County, Kansas, WAB Case No. 90-30 (Oct. 23, 1990) have held that: . . . in order for a challenge to be considered timely, it is a prerequisite that such action be taken prior to contract award, or the start of construction where there is no contract award. In the absence of such a timeliness rule, one of the basic purposes of the Davis-Bacon and Related Acts would be rendered meaningless. Dairy Development, Ltd., WAB Case No. 88-35 (Aug. 24, 1990), slip op. at p. 18. In stressing the importance of timely challenging wage determinations, the [9] ~10 [10] Dairy Development Board went on to state (Id. at pp. 18-19) the following as a principal reason for the timeliness rule: It is vital to ensure that contractors competing for federally-assisted construction contracts know their required labor costs in advance of bidding. Manifest injustice to bidders would result if the successful bidder on a project could challenge [the] contract's wage determination after all other competitors were excluded from participation. In numerous cases since the adoption of 29 C.F.R. [sec] 1.6(c)(3) the Board has cited that provision as "codifying" the Board's rulings regarding the requirement for timeliness. See Harper County, Kansas, supra. This Board steadfastly adheres to the timeliness rule as set out above, but considers that rule to necessarily follow from the principal set out in 29 C.F.R. [sec] 1.6(c)(3), as opposed to being "codified" by that code section. With the exception of the provisions for correcting clerical errors in a wage determination (29 C.F.R. [sec] 1.6(d)) and the specific situations set out in 29 C.F.R. [sec]1.6(f), the only time a wage determination can be modified is prior to contract award, or the start of construction if there is no contract award.<4> See 29 C.F.R. [sec] 1.6(c)(3)(vi). Therefore, a challenge to a wage determination must be timely made to DOL (unless one of the specific exceptions contained in [sec]1.6(d) or (f) is applicable), or the correct wage determination, if the challenge is successful, could not be incorporated by DOL.<5> The wage determination challenge by Petitioners is dated August 9, 1993 and construction began on Phase II on May 17, 1993. The Petitioners would therefore, be precluded from asserting their challenge if the Board's timeliness rule is applied. The application of the Board's timeliness rule to the facts of this [10] ~11 [11] case will not further the primary purpose of the rule -- to prohibit unfair competition in the bidding process. The timeliness rule has not been enforced in other situations in which the primary purpose of the rule is not served and the application of the rule is fundamentally unfair to the party seeking to challenge a wage determination. In this situation the critical analysis from a timeliness perspective focuses on the reasonable notice Petitioners had of the allegedly incorrect wage determination. In Utility Services, Inc., WAB Case No. 90-16 (July 31, 1991) the Board held that the timeliness rule would not apply because the Petitioner "did not have adequate notice" of the challenged wage rate prior to award of the contract. The record in this case is insufficient for us to determine whether or not the Petitioners had adequate notice to challenge the wage determination prior to the start of construction. We direct the Administrator to determine, if appropriate after deciding the "contract award" interpretation issue, the extent to which the Petitioners had reasonable notice of the incorporation of the allegedly outdated wage determination prior to the start of construction. We further direct the Administrator to consider whether or not the wage determination incorporated into Phase II of the JFK project "clearly" does not apply in light of this decision and the provisions of 29 C.F.R. [sec]1.6(f). The Administrator shall give the Petitioners an opportunity to address these issues on remand. The Administrator is further directed to complete reconsideration on remand within 60 days of the date of this decision and provide a copy of the new ruling to the Board on the date of issuance. BY ORDER OF THE BOARD: David A. O'Brien, Chair Ruth E. Peters, Member Gerald F. Krizan, Esq. Executive Secretary [11] FOOTNOTES ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN1/ The Army has challenged the legality of AAM No. 157 in a request for a ruling from the Administrator pursuant to 29 C.F.R. [sec] 5.13. That request for an opinion is pending before the Administrator. /FN2/ WD MA 90-1 would not apply, even though that was the applicable wage rate at the time of the "award" of the original contract because the very language of that contract dictates that "current wage rates" will apply upon exercise of the Phase II option. /FN3/ The Petitioners did argue that the exercise of an option was not the equivalent of the award of a contract. See Memorandum on Behalf of [Petitioners], pp. 8 and 9, but only used that argument to bolster the assertion that an additional exception to 29 C.F.R. [sec] 1.6(c)(3) should be adopted by the Board. Id. at pp. 21 and 22. /FN4/ The three exceptions set out in 29 C.F.R. [sec] 1.6(f) are, as follows, if: 1) no wage determination was initially included in the contract; 2) a wage determination was used that is clearly wrong; or 3) the wrong wage determination was used due to inaccuracies in the contracting agency's request for a wage determination. /FN5/ By its very terms, 29 C.F.R. [sec]1.6(c)(3) applies directly only to the government. 29 C.F.R. [sec]1.6(c)(3) states as follows: All actions modifying a general wage determination shall be effective with respect to any project to which the determination applies, if notice of such actions is published before contract award (or the start of construction where there is no contract award). . . . Only the government can "modify" a wage determination. Only the government can "publish" a wage determination as set out in 29 C.F.R. [sec]1.6(c)(3)(v).



Phone Numbers