skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

LUI LANDSCAPING, INC., WAB No. 94-05 (WAB May 20, 1994)


CCASE: LUI LANDSCAPING INC. DDATE: 19940520 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of: LUI LANDSCAPING, INC. WAB Case No. 94-05 and SIONE K. LUI Subcontractors BEFORE: David A. O'Brien, Chair Ruth E. Peters, Member DATED: May 20, 1994 DECISION OF THE WAGE APPEALS BOARD This matter is before the Wage Appeals Board on the petition of Lui Landscaping, Inc. and Sione K. Lui (collectively, "Petitioners" or "Lui"), for review of a January 7, 1994 Decision and Order of Deputy Chief Administrative Law Judge ("ALJ") John M. Vittone. That ruling entered a default judgment against Lui for failing to respond to a Pre-Hearing Order and failing to respond to an Order To Show Cause. The ruling also placed the petitioners' names on the ineligibility list for a period not to exceed three years. For the reasons stated below, the petition is denied and the ruling of the ALJ is affirmed. I. BACKGROUND In this case the Department of Labor sought only debarment. In two previous contracts -- Nos. I-15-8(61)387 and I-15-8(62)392 -- Lui failed to pay their employees the required wages and misclassified some employees. Lui did not request a hearing to dispute these prior violations. Petitioners were subsequently debarred from entering into any government contracts from February 26, 1990 through February 26, 1993. Mr. Sione K. Lui signed the return receipt indicating that he received notice of the debarment on May 15, 1990. Petitioners allege that they misunderstood the meaning of the original [1] ~2 [2] debarment and believed that an agreement to pay the back wages owed resolved the entire matter. Despite being debarred, Lui bid on and obtained fourteen government contracts. All fourteen contracts contained form FHWA 1273 which states that the subcontractor is, by submitting its proposal, certifying that neither it nor its principals are debarred. A letter from the Department of Labor ("DOL") was hand delivered to Lui on March 11, 1992 (although the letter was actually dated March 11, "1982," petitioners have not disputed the fact that the correct date is March 11, 1992) alleging that Lui had violated the Davis-Bacon Act and the Contract Work Hours and Safety Act by bidding on government contracts while debarred. On March 31, 1992 the petitioners acting through their duly authorized agent, attorney Donald E. Elkins, mailed a reply to the DOL requesting a hearing before an ALJ. The matter was referred to the Office of Administrative Law Judges for a hearing pursuant to 29 C.F.R. 5.11(b) and/or 5.12(a). On April 15, 1993 Deputy Chief ALJ John M. Vittone issued a Pre-Hearing Order which required the DOL to furnish Lui with certain identified information regarding the allegations set forth in the DOL's letter of March 11, 1992. The order specifically stated that "no later than 20 days after service of the aforementioned information, the [petitioners] shall serve and file an Answer admitting or denying the information furnished...." DOL filed its response to the Pre-Hearing Order on May 18, 1993. The petitioners' Answer was therefore, due by June 8, 1993. On July 13, 1993 the attorney originally representing the petitioners in this matter, Donald E. Elkins, filed a withdrawal as counsel effective immediately. No answer was filed, and on August 27, 1993 an order to Lui to show cause why a default judgment should not be entered in this case was issued. Copies of the Pre-Hearing Order, the DOL's response to the Pre-Hearing Order, the withdrawal as counsel and the Order to Show Cause were all certified as being served personally on Mr. Sione Lui. Pursuant to the Order To Show Cause the petitioners were given 20 days to respond and show why a default judgment should not be entered. On September 14, 1993 DOL filed a response to the Show Cause Order. As of January 7, 1994 Lui had not filed a response to the Show Cause Order. On that date Deputy Chief ALJ Vittone issued his Decision and Order that Lui's request for a hearing be dismissed, that certain facts set forth in this case by the DOL be adopted and that the petitioners' names be placed on the ineligibility list for a period not to exceed three years.[2] ~3 [3] II. DISCUSSION Petitioners have set out five basic arguments in support of the Petition for review, as follows: 1. That the March 31, 1992 letter with attachments constituted a sufficient Answer to the DOL's response to the Pre-Hearing Order pursuant to 29 C.F.R. 6.30(b); 2. That petitioners' attorney was responsible for the failure to respond to the Orders of the ALJ; 3. That Mr. Lui never personally received the Order to Show Cause; 4. That Mr. Lui's difficulty with the English language and his unfamiliarity with the justice system in this country should excuse his inaction; and, 5. That Lui Landscaping, Inc., should not be included in the default judgment since the Order to Show Cause was not directed at the corporation. The regulations governing ALJ proceedings provide (at 29 C.F.R. 18.6(d)(2)(v)) that if a party fails to comply with an order, the ALJ may rule that "a decision of the proceeding be rendered against the non-complying party...." The Wage Appeals Board has held under the Davis-Bacon and Related Acts that an ALJ was within her/his discretion in entering a default judgment against a party for failure to comply with a court order. See United Cooling and Contracting Co., WAB Case 91-04 (February 22, 1991) and Prime Roofing Inc., WAB Case No. 92-15 (July 16, 1993). The Prime Roofing case was also affirmed, in part, based upon the failure of the contractors therein to comply with a Pre-Hearing Order. In addition, the Board of Service Contract Appeals has held in two cases that an ALJ was within her/his discretion in entering a default judgment against a party for failure to respond to a Pre-Hearing Order. See Cynthia E. Aiken, BSCA Case No. 92-06 (July 31, 1992) and Tri-Way Security and Escort Services, Inc., BSCA Case No. 92-05 (July 31, 1992). The Wage Appeals Board may set aside the entry of a default judgment based upon the failure to comply with a Pre-Hearing Order only upon a finding of abuse of discretion by the ALJ. See Prime Roofing, supra. The petitioners have clearly not met the burden of showing that the ALJ abused his discretion in dismissing the request for a hearing. Petitioners' first argument is based upon 29 C.F.R. 6.30(b), which states that the response to a notification letter from the Administrator shall be given the [3] ~4 [4] effect of an answer. Certainly, if the DOL had ignored the March 31, 1992 letter from attorney Elkins and proceeded without a hearing the resulting decision would have to be set aside. However, the DOL did not ignore the request for a hearing. The DOL referred the matter to an ALJ for hearing. Therefore, the letter of March 31, 1992 was given the effect of an answer pursuant to 29 C.F.R. 6.30(b). The petitioners' delinquency came, not as a result of failing to file an answer, but in failing to comply with Pre-Hearing Order of the ALJ. Although the Pre-Hearing order states that an "Answer" is to be filed admitting or denying the information required to be disclosed by the DOL, the more appropriate description of what is required is a response to the specific allegations of the DOL. It should be noted that the disclosure of the information required by the Pre-Hearing Order is to the benefit of the petitioners. The response is required in order to join the issues for hearing. Failure to respond to a Pre-Hearing order coupled with the failure to respond to an Order to Show Cause dictate the result entered here -- a default judgment. The Board rejects petitioners' argument that they should be relieved from the effect of the default judgment, based on the purported negligence or misfeasance of their counsel. Mr. Lui -- personally -- was on the certificate of service list for all of the pertinent documents filed in this case. He had notice of all relevant matters, not only through his attorney of record, but also through direct receipt of the documents. Also, Mr. Lui received notice of Mr. Elkins' withdrawal as counsel on or about July 13, 1993, well before the entry of the Show Cause Order on August 27, 1993. Petitioners had plenty of time after the withdrawal of their original counsel to retain other counsel prior to the entry of the Default Judgment on January 7, 1994. Therefore, despite any shortcomings in the legal representation received by the petitioners they had sufficient notice of all the proceedings in order to respond appropriately on their own, or to secure competent counsel to respond on their behalf. In addition, this analysis applies to the argument of respondents that Mr. Lui's lack of understanding of the English language should excuse his inaction. Mr. Lui, not the ALJ or DOL, is responsible for recognizing his own lack of understanding and taking steps to rectify this problem. Petitioners also allege that Mr. Lui "never received the Order to Show Cause.'' In the factual background portion of their brief, petitioners only aver that "Mr. Lui does not believe that he received [the Show Cause Order].'' Petitioners admit that Mr Elkins' client file indicates that Mr. Lui received a copy of the order. The order itself certifies that a copy was sent directly to Mr. Lui. The meek allegation that Mr. Lui does not remember receiving a copy of the order is far outweighed by the evidence to the contrary.[4] ~5 As for the allegation that the Show Cause Order only applies to Mr. Lui, the Board notes that the heading of the order is specifically addressed to both Lui Landscaping, Inc. and Sione K. Lui. Both parties were listed as respondents to this action and thus, appropriately subject to the Decision and Order of the ALJ. The Board also notes that it would appear petitioners have a clear history of uncontested wage violations and have totally disregarded a prior valid debarment order. More importantly, we have concluded that petitioners have ignored the requirements of the Department's administrative hearing procedures at their own peril. The petitioners were apparently capable of understanding the detailed processes necessary to obtain government contracts, but allegedly are incapable of comprehending the process and procedure by which those contracts are interpreted and enforced. Petitioners cannot be found to understand and thereby obtain the benefit of a contract, without also being held to understand and thereby be accountable for breach of the duties and enforcement procedures pursuant to that same contract. For the foregoing reasons the decision of the ALJ is affirmed and the petition for review is dismissed. BY ORDER OF THE BOARD: David A. O'Brien, Chair Ruth E. Peters, Member Gerald F. Krizan, Esq. Executive Secretary [5]



Phone Numbers