skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

L.T.G. CONSTRUCTION CO., WAB No. 93-15 (WAB Dec. 30, 1994)


CCASE: L.T.G. CONSTRUCTION CO. DDATE: 19941230 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of: L.T.G. CONSTRUCTION CO. WAB Case No. 93-15 Prime Contractor, et al. BEFORE: David A. O'Brien, Chair Ruth E. Peters, Member Karl J. Sandstrom, Member DATED: December 30, 1994 DECISION OF THE WAGE APPEALS BOARD This matter is before the Wage Appeals Board on the petition of L.T.G. Construction Co., Phoenix-Griffin Group II, Gatsby Housing Associates and Lloyd T. Griffin, Jr. a principal of each the above (collectively referred to as "petitioners") for review of the July 1, 1993 decision and order issued by Administrative Law Judge ("ALJ") David W. DiNardi. The ALJ determined that petitioners had failed to pay statutorily required wages on the housing projects in question, ordered that the back wages due be paid, and further ordered that petitioners be debarred in accordance with the provisions of 29 C.F.R. 5.12 (a) (1) and be ineligible to receive any contract or subcontract subject to any of the statutes listed in 29 C.F.R. 5.1 for a period of three years. For the reasons set forth below, the decision and order of the ALJ is affirmed. I. BACKGROUND This case arises from the Turnkey Housing Project in Providence, Rhode Island, a scattered-site public housing development funded by the United States [1] ~2 [2] Department of Housing and Urban Development ("HUD") under the United States Housing Act of 1937, as amended (42 U.S.C. [sec] 1437j)( the "Housing Act") and therefore subject to federal construction contract prevailing wage requirements of the Davis-Bacon Act (40 U.S.C. [sec] 276a et seq.) pursuant to 29 C.F.R. Part 5. The Providence Housing Authority (the "PHA") was the contracting agency for this project. The PHA contracted with Phoenix-Griffin Group II, Ltd. ("PGG") for development of Phase I of the project, which ultimately involved ninety-two housing units, scattered throughout the City of Providence. PGG then contracted with L.T.G. Construction Co., Inc. ("L.T.G.") to construct the units. L.T.G. utilized its own employees and subcontractors to prepare the sites, fabricate and erect the houses, install interior material such as linoleum and cabinets and contracted with Gatsby Housing Associates ("GHA") to clean the units prior to their being tendered to PHA. At the time it submitted its bid in April 1988, L.T.G. anticipated it would also be the successful bidder on Phase II of the project which was to involve an additional sixty-two units of housing. However, Phase II was subsequently cancelled. To control costs and provide security, L.T.G. chose to build the housing units in sections at a prefabrication plant located on Veazie Street in Providence. The sections were transported to the various housing sites and erected on foundations. Petitioners believed that the wages paid at the Veazie Street site were exempt from the prevailing wage requirements of the Housing Act. Mr. Griffin based this belief on a written opinion and a handbook that he had received from PHA and HUD, the governmental entities responsible for administering this project. The actual construction work undertaken at the building sites was subcontracted by L.T.G. Framing subcontractors were responsible for the assembly and erection of the prefabricated panels on each site. The various subcontractors provided labor and tools, while L.T.G. was responsible for the organization and delivery of materials to the site and the furnishing of major pieces of equipment. The subcontractors retained for the project were for the most part owner-operated small companies. Petitioners believed, again based on communication from HUD, that wages paid to owner operator were exempt from the prevailing wage requirements. In November 1990, the Wage and Hour Division instituted an investigation into possible Davis-Bacon prevailing wage violations on this project. At the conclusion of the investigation, the Wage and Hour Division found that petitioners failed to pay Davis-Bacon prevailing wages at the Veazie Street fabrication facility and at the various scattered housing sites. Additionally, it found that petitioner L.T.G. had failed to keep adequate records, and failed to pay subcontractors who were owner operators and clean-up crews prevailing wages. Finding the violations [2] ~3 [3] to be aggravated and willful, the Wage and Hour investigator recommended that petitioners be debarred from federal government contracts for three years. In March 1991 the Department of Labor ("DOL") directed HUD to withhold $500,000 from future funding of the project for failure of petitioners to pay Davis-Bacon prevailing wages. As a result of this directive, L.T.G. ceased all construction activity on the project. At this stage, 52 of the units had been completed and conveyed to the PHA. Another 35 were virtually complete and 5 were at the foundation stage. In light of the withholding order and the possible loss of repayment funds, Fleet Bank, the source of construction financing, refused, in accordance with a pre-set requisition procedure, to advance any additional funds from the revolving construction loan. After a series of meetings between petitioner Griffin and representatives of DOL during which petitioner was informed of the basis for the withholding order, Mr. Griffin through counsel requested a hearing pursuant to 29 C.F.R. 5.11(a) and 5.12(a). A hearing was scheduled before ALJ DiNardi. After 24 days of hearing between October 13, 1992 and November 24, 1992, the ALJ issued his decision and order on July 1, 1993 upholding the Administrator's position on each of the major issues. Petitioners have appealed that decision to the Board pursuant to 29 C.F.R. Parts 6 and 7. II. DISCUSSION This matter presents the Board with three issues for review: (1) whether the employees employed by L.T.G. at its Veazie Street facility are entitled to Davis-Bacon prevailing wages; (2) whether the Department of Labor should be estopped from seeking back wages for workers employed at the Veazie Street site as independent contractors; and (3) whether the violations found by the ALJ were aggravated or willful. The Board addresses each of these issues in turn below. A. Veazie Street Facility There is no question that laborers and mechanics employed in the development of a low income housing project funded, in whole or in part, under the Housing Act, are required to be paid Davis-Bacon prevailing wages. Section 1437j(a) of the Housing Act provides: Any contract for loans, contributions, sale or lease pursuant to this Act shall contain a provision requiring that not less than the wages prevailing in the locality as determined or adopted (subsequent to a determination under applicable State or local law) by the Secretary, shall be paid to all architects, technical engineers,[3] ~4 [4] draftsmen and technicians employed in the development, and all maintenance laborers and mechanics employed in the operation, or the low income project involved; [*]and shall also contain a provision that not less than the wages prevailing in the locality, as predetermined by the Secretary of Labor pursuant to the Davis-Bacon Act (49 Stat. 1011) [40 USCS 276a et seq.] shall be paid to all laborers and mechanics employed in the development of the project involved[*] (including a project with nine or more units assisted under section 8 of this Act [42 USCS 1437f], where the public housing agency or the Secretary and the builder or sponsor enter into an agreement for such use before construction or rehabilitation is commenced), and the Secretary shall require certification as to compliance with the provisions of this section prior to the making any payment under such contract. [*](Emphasis added)[*]. Section 1437a(c)(1) of the Housing Act defines "development" as follows: The term "development" means any or all undertakings necessary for planning, land acquisition, demolition, construction, or equipment, in connection with a low- income housing project. Applying this definition to the facts of this case, the Board finds that the work performed by petitioners' employees at the Veazie Street facility is covered. The fabrication of integral construction elements by a contractor in a facility largely dedicated to the production of those elements is unmistakably an "undertaking necessary for . . . construction . . ., in connection with a low-income housing project." The fact that the work in question is of a type that is commonly performed at the site of construction removes any question regarding its coverage. To find otherwise would defeat Congress's clear and unambiguous intent to guarantee that workers employed in the development of federally financed or assisted low-income housing projects are paid Davis-Bacon prevailing wages. It would fly in the face of logic to find that Congress intended that architects and draftsmen involved in the planning of low-income housing projects be paid prevailing wages but not the employees of the contractor who actually construct the walls of the project. To reach this judgment, it not necessary for this Board to lay out the full contours of the term "development;" it is necessary only for the Board to find that the work at issue clearly falls within the plain meaning of the statute. In finding that petitioners' Veazie Street employees were engaged in an "undertaking necessary for . . . construction . . ., in connection with a low-income housing project," the Board applies only the most natural and obvious meaning of those words.[4] ~5 [5] It is important to note that the Housing Act contains no "site of work" limitation similar to that found in the Davis- Bacon Act. The United States Court of Appeals for the District of Columbia relied in Ball, Ball & Brosamer, Inc. v. Reich, 24 F.3d 1447 (D.C. Cir. 1994) on that provision to strike down the Department of Labor's "site of work" regulations (29 C.F.R. 5.2(l)) as inconsistent with the plain language of the Davis-Bacon Act. In the instant case, the Administrator does not rely on DOL's definition of "site of work",/FN1/ as found in 29 C.F.R. 5.2(l), but on the plain meaning of the language of the Housing Act and on DOL's regulation at 29 C.F.R. 5.2(j). In support of the Administrator's position, the ALJ specifically cited the absence of a site of work limitation in finding that under the Housing Act that the workers at the Veazie Street facility were entitled to be paid Davis-Bacon prevailing wages. For the Board to graft onto the Housing Act a site of work limitation, as petitioners urge us to do, would be without statutory foundation. Instead the Board affirms the ALJ's decision and the Administrator's enforcement policy, which recognizes no site of work limitation in matters arising under the Housing Act. Even if the Administrator were to eventually acquiesce in Ball, Ball & Brosamer, it would consequently have no impact on the Board's decision in this case. For the reasons given above, the Board finds that the workers at petitioners' Veazie Street facility were employed in the development of a federally assisted low-income housing project on which Davis-Bacon prevailing wages were required to be paid. B. Estoppel Petitioners argue that DOL should be estopped from seeking back wages due: (1) employees at the Veazie Street facility; (2) subcontractors who were owner operators; and (3) employees of GHA who were employed in the cleaning of housing units prior to the conveyance of the units to the PHA. According to petitioners' argument, even if the Board were to find that these various categories of employees were entitled to Davis-Bacon prevailing wages, DOL should be estopped from making a claim against petitioners for the back wages due. Petitioners contend that statements contained in a HUD Handbook, entitled "Federal Labor Standards Compliance in Housing and Community Development Programs Handbook," and distributed to petitioners and statements made by HUD and PHA officials should bar DOL on equitable estoppel principles from making a claim against petitioners for back wages due. The Board finds it unnecessary [5] ~6 [6] to review all of the ALJ's factual findings in this regard or to decide whether petitioners approach the Board with the "clean hands" necessary to merit equitable relief. The Board deems it sufficient to conclude that even read under the most favorable light to petitioners the facts of this case would not merit the invocation of equitable relief against DOL. Whether petitioners could conceivably prevail on a contract modification or promissory estoppel theory against the PHA or HUD is not within the province of the Board to decide. It is well settled law that the mistakes of one agency cannot be used to estop another agency from carrying out its statutory responsibilities. U.S. v. Stewart, 311 U.S. 60 (1940) and Graff v. C.I.R., 673 F.2d. 784 (5th Cir. 1982). DOL is charged with the responsibility of assuring that workers on federally financed or assisted construction projects are not exploited and receive the prevailing wages to which they are statutorily entitled. To invoke estoppel against DOL to defeat a legitimate claim for back wages on behalf of aggrieved workers may be a legal impossibility (see Heckler v. Community Health Services of Crawford County, Inc., 457 U.S. 51 (1984)), but even if were not, it would require at a minimum a compelling demonstration of conscious and aggravated misconduct on the part of DOL. Additionally, petitioners would have to establish reasonable reliance to their detriment on that misconduct. The facts of this case will not bear the heavy burden placed on them by petitioners. Petitioners concede that the misconduct on which it allegedly relied was on the part of PHA and HUD. There is no suggestion that petitioners received or relied upon wrong advice given to them by DOL. Petitioners have failed to establish that DOL even knew, let alone participated in a conscious and aggravated manner, in the communication of misinformation to petitioners. As noted above, DOL has the statutorily mandated responsibility to see to it that employees on federally financed and assisted construction projects receive Davis-Bacon prevailing wages. This mandate cannot be defeated merely by petitioners' failure to appreciate which government agency has the responsibility and authority to render definitive decisions in this area. Unable to carry their burden on the first prong of the test, petitioners' failure to demonstrate that they relied on the advice that they were allegedly given by HUD removes any remaining doubt as to the appropriateness of equitable relief. The ALJ expressly rejected petitioners' contention that they relied on the advice. This is a question of fact which the Board will not upset absent a showing that the finding was clearly erroneous. There is sufficient evidence in the record to support the ALJ's finding in this regard.[6] ~7 [7] The Board has regularly and consistently taken the position that reliance on a contracting agency's advice is misplaced and will not defeat a contractor's obligation to pay employees legally required prevailing wages. In Tollefson Plumbing and Heating Co., WAB Case No. 78-17 (Sep. 24, 1979), at page 8, the Board stated "that advice by a contracting agency was not binding on the Department of Labor and did not estop the Department of Labor from requiring the payment of the proper wage rate." And in Fry Brothers Corp., WAB Case No. 76-06 (June 14, 1977), at page 19, the Board held that "only a written ruling of the Secretary of Labor can be relied upon for wages which must be paid under the Davis-Bacon Act." This case presents no compelling reason for the Board to stray from its well considered precedents. Therefore the ALJ's decision is affirmed and petitioners' request for equitable estoppel is denied. C. Debarment The Wage Appeals Board is an essentially appellate body. 29 C.F.R. 7.2(e). Only under extraordinary circumstances will the Board hear matters de novo. The Board will defer to the trier of fact, absent a convincing demonstration that the trier of fact's findings were clearly erroneous. Prime Roofing, Inc., WAB Case No. 92-15 (Jul. 16, 1993). The Department's regulations at 29 C.F.R. 5.12(a)(1) provide that a contractor who is found to be in willful or aggravated violation of the Davis-Bacon Act shall be ineligible to receive any contract subject to Davis-Bacon labor standards (See 29 C.F.R. 5.1). The test as to whether a violation or series of violations is willful or aggravated and therefore calls for debarment is primarily a question of fact. The Board will not overturn an ALJ's debarment order unless it is convinced that the order is without a factual foundation. The Board will not set aside a debarment order merely on the basis that the Board may have resolved some factual disputes differently than the trier of fact. The Board defers to the trier of fact as to the weight and credibility to be given to evidence. (See Wayne J. Griffin, Inc., WAB Case No. 93-05 (Oct. 29, 1993)). In the instant matter, the ALJ correctly identified a "willful" violation to encompass intentional disregard, or plain indifference to the statutory requirements of the Davis-Bacon Act. (ALJ's decision at p. 47). Although mere inadvertent or negligent conduct would not warrant debarment, conduct which evidences an intent to evade or a purposeful lack of attention to, a statutory responsibility does. Blissful ignorance is no defense to debarment. Applying these standards to the present case, the Board is compelled to affirm the ALJ's debarment order. In a lengthy decision which followed twenty four days of hearings, the ALJ extensively reviewed the factual record upon which he rested his decision. At pages 48 and 49 of that decision, the ALJ recites twelve [7] ~8 [8] specific findings in support of his debarment order. A review of those findings and the supporting record provide ample grounds for affirming the ALJ's order. The record demonstrates that L.T.G. and Lloyd Griffin were aware that subcontractors were required to pay prevailing wages to their employees. Nevertheless as the ALJ found, L.T.G. approved a clear subterfuge of this statutory requirement by its subcontractor, Henderson and Sullivan, whereby employees of the subcontractor were treated as subcontractors. To compound this violation, L.T.G. encouraged another subcontractor, Stone Framing, to employ the same ruse in evading its statutory responsibility to pay the prevailing wage. L.T.G. did not see fit to bring this highly questionable and indeed impermissible scheme to the attention of the appropriate officials. L.T.G.'s conduct in this regard evidences a clear indifference to, if not intentional violation of, its statutory responsibility. Further L.T.G.'s failure to regularly obtain certified payroll records from subcontractors and to keep adequate records itself and its suggestion to subcontractors that records could be falsified are all findings of the ALJ that have a substantial basis in the record and support his order. Again the ALJ was justified in concluding from this conduct that the petitioners exhibited a willingness to evade its statutory responsibility. This conclusion is bolstered by the ALJ's finding that L.T.G. engaged in a transparent attempt to evade the prevailing wage requirements by treating employees as subcontractors despite the fact these employees clearly lacked the indicia of independent contractors. Each of these findings would independently be sufficient to support the order of debarment. Therefore, it is unnecessary for the Board to address whether the ALJ's other findings, either independently or collectively, are sufficient to support a debarment order. In summary, the Board finds that the ALJ's decision accurately reflects the legal standard for debarment and further finds that ALJ's decision is supported by the preponderance of reliable and probative evidence on the record and is not clearly erroneous. Therefore the ALJ's debarment order is affirmed. BY ORDER OF THE BOARD: David A. O'Brien, Chair Ruth E. Peters, Member Karl J. Sandstrom, Member Gerald F. Krizan, Esq. Executive Secretary[8] FOOTNOTES ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN1/ The Administrator also argues that proper application of the "site of work" would still subject the Veazie Street facility to prevailing wage requirements. Because the Board accepts the Administrator's primary contention, there is no need for this Board to address the application of the "site of work" regulations to the facts of this case.



Phone Numbers