skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

S.D.F., INC., WAB Case No. 92-12 (WAB Aug. 31, 1993)


CCASE: S.D.F. INC. DDATE: 19930831 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of: S.D.F., INC., WAB Case No. 92-12 Subcontractor BEFORE /FN1/: Charles E. Shearer, Jr., Chairman Ruth E. Peters, Member DATED: August 31, 1993 DECISION OF THE WAGE APPEALS BOARD This matter is before the Wage Appeals Board on the petition of the Acting Administrator of the Wage and Hour Division for review of a June 16, 1992 decision and order issued by Administrative Law Judge ("ALJ") Joel R. Williams. Subcontractor S.D.F., Inc., ("S.D.F.") also petitioned for review of the ALJ's decision and order; the Board dismissed S.D.F.'s petition as untimely on March 30, 1993. The Acting Administrator appeals from two aspects of the ALJ's decision and order: (1) the ALJ's determination that the work performed by S.D.F. under an agreement which was supplemental to the basic subcontract and which did not include labor standards provisions was not covered by the Davis- Bacon provisions of the Urban Mass Transportation Act of 1964 ("UMTA"); and (2) the ALJ's order that funds withheld by the contracting agency and/or the prime contractor above the amount that the ALJ awarded as back wages be remitted to subcontractor S.D.F. For the reasons stated below, the petition for review is granted and the ALJ's decision and order is reversed on both points. [1] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN1/ Member Anna Maria Farias took part in the April 2, 1993 oral argument in this case, but did not participate in this decision.[1] ~2 [2] I. BACKGROUND In June 1989 the Dallas Area Rapid Transit Authority ("DART") awarded a contract to prime contractor Clearwater Construction, Inc. ("Clearwater") for the construction of improvements and renovations to DART's East Dallas Facility. That facility was used for housing, maintenance and repair of DART buses and other vehicles. Among other things, the contract provided for construction of a new Equipment Services Garage ("ESG"), to be erected with prepainted structural steel. Appended to the contract were separate prevailing wage rates for "Highway/Heavy" construction and for "Building" construction. On June 15, 1989, Clearwater entered into a subcontract with S.D.F. for painting of the project. The subcontract provided for completing all drywall texturing, taping and floating; utility and protective coating; painting; and vinyl coating. The basic subcontract excluded "steel touch-up." Clearwater and S.D.F. entered into a supplemental agreement on a time and materials basis on March 19, 1991 for touch-up of the structural steel on the ESG. The supplemental agreement did not contain any provisions setting forth Davis-Bacon prevailing wage requirements. Upon investigating S.D.F.'s performance on the project, the Department of Labor determined that S.D.F. had not paid its painters and laborers the prevailing wage required by the Davis- Bacon provisions of the UMTA. The Department determined that S.D.F. should have been paying its painters wages and fringe benefits totaling $16.54 based on the "Building-Group 4" rate listed in the "Building" wage schedule, and should have been paying its painter helpers the Building rate for laborers of $9.90 per hour for wages and fringe benefits. The Department further determined that S.D.F. owed its employees back wages totaling $93,783.82. Of total, $6,724 was for time spend by employees on the structural steel retouching job. Both Clearwater and S.D.F. were served charging letters advising them of their right to a hearing; only S.D.F. requested a hearing. Clearwater was not made a party to the instant proceeding. A hearing was held in this case on April 14, 1992, and the ALJ issued his decision and order on June 16, 1992. The ALJ concluded that S.D.F. "was required to pay the `Building' rate of $16.54 per hour to its painters and $9.90 per hour to its painter's helpers for all work that they performed under the original subcontract." The ALJ also concluded, however, that S.D.F. "is not responsible for payment of the prevailing wage for the `touch up' of the structural steel under the Extra Work Order." He stated that although Clearwater's representative had "expressed optimism" at the hearing that DART would reimburse Clearwater for the structural steel touch up, the firm had not received any payment or written commitment from DART at the time of the hearing. The ALJ stated that he [2] ~3 [3] could not conclude "on the basis of the record in this case that the work performed in the touch-up was `government-funded.' As there was no Federal monies shown to be used for the separately contracted work, the Davis-Bacon prevailing wage provisions of the Urban Mass Transportation Act are not applicable" (citing MARTA Contracts CN-710 & CN-730 and options thereto, WAB Case No. 83-09 (May 14, 1984) ("MARTA"). The ALJ ordered that out of the funds being withheld from S.D.F. "by the contracting agency and/or Contractor," $87,059.82 was to be paid over to the Comptroller General of the United States for distribution to the S.D.F. employees. The ALJ specified that the payments to the employees were not to include amounts alleged to be owed for the structural steel touch up work. He further ordered that any funds withheld over and above $87,059.82 be remitted to S.D.F. On July 27, 1992, within the 40-day period prescribed by 29 C.F.R. 6.34 for filing a petition for review, the Acting Administrator filed with the Wage Appeals Board a motion for a extension of time to August 27, 1992 for filing a petition for review from the ALJ's decision and order. Alternatively, the Acting Administrator requested that the Board treat the motion as a petition for review with leave to file a supporting statement by August 27, 1992. The Board issued Notices of Appeal and Extension on July 30, 1992, noting that the Board was in receipt of a petition for review filed by the Acting Administrator, and granting the Acting Administrator's request for an extension of time for filing a statement in support of the petition. S.D.F. mailed a petition for review, along with a motion for extension of time within which to file the petition, on September 4, 1992; these documents were received and filed by the Board on September 11, 1992. The Acting Administrator then moved to dismiss S.D.F.'s motion for extension of time in which to file a petition. The Board granted the Acting Administrator's motion in a Order of Dismissal on March 30, 1993, stating: In it[s] request for an extension, S.D.F. states that it then "had an opportunity to review the Petition for Review filed by the Acting Administrator and requests relief in order to file its own Petition for Review as to a finding made by the Administrative Law Judge below." S.D.F. Motion for Extension, p.1. There is -- as noted by the Acting Administrator -- no provision in the applicable regulation for tolling of the time limit in which to file a petition for review or extension request. This includes situations where, as here, a timely petition or extension request has first been filed by another party. Thus, S.D.F.'s argument for accepting its petition does not suggest any good cause for filing its extension request and petition for review well beyond the time limit specified [3] ~4 [4] in 29 C.F.R. 6.34. Similarly, the fact that the Acting Administrator timely sought and was granted an extension of time in which to perfect her petition is not comparable to S.D.F.'s inordinate delay in requesting an extension and submitting its petition. S.D.F. subsequently filed a motion requesting that the Board set aside the order of dismissal and grant the motion for extension of time in which to file a petition. The Board heard oral argument in this case on April 2, 1993. II. DISCUSSION A. Coverage of the structural steel touch up work The Acting Administrator has appealed from two aspects of the ALJ's decision and order, arguing that the ALJ erred in concluding that work performed by subcontractor S.D.F. under the supplemental agreement was not covered by the prevailing wage requirements of the UMTA, and that the ALJ also erred in ordering that funds be remitted to the subcontractor. We will first address the coverage issue. The statutory provisions relevant to the resolution of this issue are found in the UMTA and the Davis-Bacon Act. The UMTA provides (at 49 U.S.C. [sec] 1609(a)): The Secretary shall take such action as may be necessary to insure that all laborers and mechanics employed by contractors or subcontractors in the performance of construction work financed with the assistance of loans or grants under this chapter shall be paid wages at rates not less than those prevailing on similar construction in the locality as determined by the Secretary of Labor in accordance with the Davis-Bacon Act, as amended. The Secretary shall not approve any such loan or grant without first obtaining adequate assurance that required labor standards will be maintained upon the construction work. The Davis-Bacon Act requires payment of prevailing wage rates to "all mechanics and laborers employed directly upon the site of the work" by contractors and subcontractors on a government-funded project for "construction, alteration, and/or repair, including painting and decorating." The Department of Labor's Davis-Bacon regulations define (at 29 C.F.R. 5.2(j)) "construction, prosecution, completion or repair" as encompassing "[*] all types of work done on a particular building or work at the site thereof[*], . . . including without limitation, [4] ~5 [5] altering, remodeling, . . . [*] painting [*] and decorating . . . ." [*](Emphases supplied.)[*] The Department's regulations define (at 29 C.F.R. 5.2(l)(1) the "site of the work" as the "physical place or places where the construction called for in the contract will remain when work on it has been completed...." We agree with counsel for the Acting Administrator (Statement, at p. 6) that the touch up painting of the structural steel comes within the term "construction, alteration, and/or repair," since the work was painting --performed as an alteration or as repair -- on the structural steel erected under the basic contract. Furthermore, there can be no doubt that the touch up work was performed on the "site of the work," since the touch up painting was performed on the ESG, a new structure erected by another subcontractor pursuant to the basic contract. The ALJ, nevertheless, decided that the touch up work was not subject to prevailing wage requirements, stating that he could not conclude "on the basis of the record in this case that the work performed in the touch-up was `government-funded.' As there were no Federal monies shown to be used for the separately contracted work, the Davis-Bacon prevailing wage provisions of the [UMTA] are not applicable." However, the ALJ's reliance on the Board's MARTA decision as support for his determination is misplaced. MARTA involved construction of a subway rail system, of which some segments were built with federal funds and other segments were not. The instant case is not comparable to MARTA, since it does not involve segregable portions of a project but instead involves touch up work on a structure erected pursuant to the basic contract, which called for a completed structure. As Clearwater's project manager testified (Tr. 91-92), the touch up work was necessary in order for the structure to be completed. Thus, in the Board's view, whether the touch up work was performed onsite by Clearwater's own employees, or was performed onsite by employees of the structural steel supplier, or -- as actually occurred -- was performed onsite by employees of the painting subcontractor (S.D.F.), the work was subject to prevailing wage requirements. See ALCOA Construction Systems, Inc., WAB Case No. 75-06 (Sept. 11, 1975) (onsite repair of factory prefabricated kitchen and bathroom modules was subject to labor standards requirements, even though the contract between the supplier and the prime contractor did not include prevailing wage provisions). Counsel for the Acting Administrator notes (Statement, at pp. 9-10) that the ALJ stated that if the touch up work was subject to prevailing wage requirements, the responsibility for the underpayment should rest with prime contractor Clearwater, not subcontractor S.D.F. Counsel for the Acting Administrator further states that the ALJ's conclusion is consistent with Wage and Hour's enforcement position. As established in Board precedent (see, e.g., Northern Colorado Constructors, Ltd., WAB Case No. 86-31 (Dec. 14, 1987)), a prime contractor has a contractual obligation for payment of prevailing wage [5] ~6 [6] rates to the employees of its subcontractors. In this case, the prime contractor did not meet its responsibility under 29 C.F.R. 5.5 to incorporate labor standards provisions into the supplemental agreement with S.D.F., and must undertake the obligation to pay the applicable wage rates to the subcontractor's employees. In short, the ALJ's decision that the structural steel touch up work was not covered by prevailing wage requirements is reversed. Prime contractor Clearwater is liable for the underpayment of wages, in the amount of $6,724, for the touch up work. The Board also reverses the ALJ's order that withheld funds (corresponding to the amount of back wages owed for the touch up work) be remitted to the subcontractor. As counsel for the Acting Administrator notes (Statement, at p. 11), funds are always withheld from the contractor, not from a subcontractor. Further, an ALJ lacks authority to order that withheld funds be returned to a subcontractor, since the government has no contractual relationship with the subcontractor. B. S.D.F.'s motion to set aside the dismissal order The Board has considered S.D.F.'s motion to set aside the order dismissing S.D.F.'s motion for an extension of time within which to file a petition for review. Upon consideration, the Board reaffirms its dismissal order. S.D.F. did not file an extension request within the time prescribed in 29 C.F.R. 6.34 for filing a petition for review, and S.D.F. has demonstrated no extenuating circumstances that prevented it from filing either a timely petition or timely extension request. Accordingly, for reasons stated here and in the Board's dismissal order, the motion to set aside the order of dismissal is denied. BY ORDER OF THE BOARD: Charles E. Shearer, Jr., Chairman Ruth E. Peters, Member Gerald F. Krizan, Esq. Executive Secretary [6]



Phone Numbers