UTILITY SERVICES INC., WAB No. 90-16 (WAB July 31, 1991)


CCASE: UTILITY SERVICES INC. DDATE: 19910731 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of: UTILITY SERVICES, INC., Addition to Abert Hall WAB Case No. 90-16 Defense Mapping Agency Gaithersburg, Maryland BEFORE: Charles E. Shearer, Jr., Chairman Ruth E. Peters, Member Patrick J. O'Brien, Member DATED: July 31, 1991 DECISION OF THE WAGE APPEALS BOARD This case is before the Wage Appeals Board on the petition of Utility Services, Inc. ("Utility Services" or "Petitioner") for review of the February 6, 1990 ruling of the Acting Administrator of the Wage and Hour Division denying Petitioner's request to use the water and sewer line rates, rather than the building construction rates, for its portion of a project in Montgomery County, Maryland. For the reasons stated below, the Board remands this matter to the Wage and Hour Division for further proceedings consistent with this decision. [1] ~2 [2] I. BACKGROUND On March 21, 1986, the Department of the Army issued a bid solicitation for an addition to Abert Hall, Defense Mapping Agency, Brookmont, Maryland (Contract No. DACA31-86-C-0065). Included in the bid solicitation was Wage Decision No. DC86-1, a general wage determination for Washington, D.C., and adjacent jurisdictions in Maryland and Virginia. (This wage determination was later modified, and the bid solicitation was amended accordingly.) Not all the rates listed in General Wage Decision No. DC86-1 were applicable in all the jurisdictions covered by the wage decision. On the front page of the wage decision the types of construction covered by the wage determination were described as "BUILDING CONSTRUCTION PROJECTS (does not include single family homes and apartments up to and including four (4) stories), EXCLUDING INDEPENDENT CITY OF ALEXANDRIA; HEAVY CONSTRUCTION PROJECTS (does not include Sewer and Water Lines Construction Projects); HIGHWAY CONSTRUCTION PROJECTS IN DISTRICT OF COLUMBIA ONLY; SEWER AND WATER LINES CONSTRUCTION PROJECTS IN DISTRICT OF COLUMBIA AND MONTGOMERY COUNTY, MARYLAND ONLY." In the bid solicitation package the contracting agency attached a cover sheet to the wage decision. The cover sheet stated that Wage Decision No. DC86-1 would be used to conform with the Davis-Bacon Act requirements of the contract clauses. Typed on the cover sheet was the following phrase: "BUILDING CONSTRUCTION WAGE SCHEDULES FOR MONTGOMERY COUNTY, MD., ONLY APPLY TO THIS PROJECT." The text of the wage decision also specified, with respect to certain classifications and wage rates, the jurisdictions in which those rates applied. Thus, for example, the wage decision listed brick masonry rates for "Arlington and Fairfax Counties, and the Independent City of Alexandria;" a rate for painters in "Fairfax County, Virginia;" painters/drywall finishers rates for "Washington, D.C.," and another set of painters/drywall finishers rates for "Montgomery & Prince Georges Counties, Maryland & Arlington County, Virginia." The prime contract for the project was awarded to A.S. McGaughan Company, Inc. ("McGaughan"), on June 6, 1986. The prime contractor then subcontracted with Utility Services on July 14, 1986. Petitioner's work on the project consisted of rerouting existing storm sewers and installing new storm sewers. Construction on the project began on July 14, 1986. On June 22, 1987, McGaughan and Utility Services submitted a form for Request for Authorization of Additional Classification and Rate, by which they requested that three classifications (laborer, at $6.50 per hour plus $.56 in fringe benefits; pipelayer, at $8.50 per hour plus $.56; and backhoe operator, at $10.39 plus $1.45). However, these classifications and wage rates for Montgomery [2] ~3 [3] County were already listed in Wage Decision No. DC86-1 under "Sewer and Water Lines Construction" (as noted earlier, the wage decision contained sewer and water line construction classifications and rates for only two jurisdictions -- Washington, D.C., and Montgomery County, Maryland, where the Abert Hall project was situated). The Director of Wage and Hour's Division of Wage Determinations denied the request by letter dated July 18, 1988. Citing 29 C.F.R. 5.5(a)(1)(ii), which sets forth the criteria for approval of requests for additional classifications and wage rates, the Director stated that the request of Petitioner and the prime contractor could not be approved because the work to be performed by the requested classifications "is performed by classifications already included in the wage determination under building construction." The appropriate building construction classifications, the Director added, were "laborers, plumbers, (pipelayers) and backhoe." By letter dated November 6, 1989, Petitioner requested reconsideration of the Director's decision. Petitioner first took issue with the determination that building construction classifications the appropriate classifications for the work done by Utility Services. "Although the entire contract is for building construction," Petitioner stated, "Utility Services work is only the rerouting of existing storm sewers and installation of new storm sewers. All of this work is done separate and apart from the building construction and stops at least 5 ft. from any building. Therefore, the Sewer and Water Lines Construction Rates for Washington, DC and Montgomery County should be used." Secondly, Petitioner stated, the suggested additional classifications are in fact, covered in General Wage Decision No. DC86-1 which was included in the solicitation for the Addition to Abert Hall. . . . The difficulty and request for additional classification arose out of a disagreement between the parties as to which construction classification-- building or water and sewer--applied to [Petitioner]. Perhaps additional classification was a misnomer. The rates to which Utility Services should be obligated are those of water and sewer construction, which are listed in DC86-1. The Acting Administrator denied Petitioner's request for reconsideration by letter dated February 6, 1990. The Acting Administrator stated that 29 C.F.R. 5.5(a)(1)(ii) permits the addition of unlisted classifications and wage rates only when the work to be performed by the requested classification is not performed by a classification already listed in the wage determination. "The building schedule of wage rates as contained in Wage Determination No. DC86-1," the Acting Administrator stated, "includes laborers, pipelayers and backhoe operators classifications and wage rates." [3] ~4 [4] The Acting Administrator also rejected Petitioner's contention that the building construction rates were not relevant because Petitioner performed only utility work on the Abert Hall project. Information provided by the Corps of Engineers indicated that the sewer and water portion of the project was only $387,000 out of the total project cost of $21,000,000, or about 2% of the total project cost, the Acting Administrator noted. Accordingly, she stated, "we concur with their decision, as designated in their solicitation, that only the building construction wage rates apply to this project. The decision to consider the sewer and water construction incidental to the overall building project was in accordance with All Agency Memoranda Numbers 130 and 131 . . ., which provide guidance to contracting agencies in the application of this policy." II. DISCUSSION We begin our analysis of this matter by defining the issue presented for disposition by the Board. Although this case arose as a conformance proceeding, it is not, strictly speaking, a conformance matter, since the Montgomery County sewer and water line construction classifications and rates which Petitioner claims are applicable to its work on the Abert Hall project are already listed in General Wage Decision No. DC86-1. By the same token, the question presented by this case is not whether Wage Decision No. DC86-1 should be modified in some manner since, again, the requested sewer and water line rates are already included in the wage decision. Thus, the central issue in this matter is which classifications and rates listed in the wage decision -- the building construction rates or the water and sewer line construction rates -- apply to the work performed by Utility Services on the Abert Hall project. The Acting Administrator did not base her February 6, 1990 denial of Petitioner's reconsideration on the ground that Petitioner had not timely raised its contention that the water and sewer line rates were the appropriate rates for the work performed by Petitioner's employees. Instead, the Acting Administrator addressed the merits of Petitioner's contention and concurred in the contracting agency's application of building rates, since the utility work performed by Petitioner was only an incidental portion (about 2%) of the total project cost. Before the Board, however, the first line of argument by counsel for the Acting Administrator is that "in including WD No. DC86-1 in the bid solicitation, the contracting agency specified that only the `building construction' schedule applied to the project. Thus, Petitioner's request is most appropriately viewed as a request to modify the wage determination specified by the contracting agency by adding the schedule of rates for `Water and Sewer Line Construction."' [4] ~5 [5] Invoking Board decisions /FN1/ and Department of Labor regulations /FN2/ on the time requirements for a challenge to a wage determination, counsel argues that Petitioner's request for application of the sewer and water line rates should be rejected because the request was made a year after award of the prime contract and the utility subcontract. We note again, however, that this case does not present a challenge to the substantive correctness of the classifications and rates listed in General Wage Decision No. DC86-1, but instead involves the question of which rates in that wage decision are applicable to the utility work performed by Petitioner. Regardless of whether the Board precedent and the regulations cited by counsel for the Acting Administrator strictly apply to such a question, we think that counsel properly emphasized the responsibility of contractors to resolve questions of applicable wage rates before contract award. The exercise of that responsibility, however, presupposes that contractors have adequate notice that a question requiring resolution does exist. In this case, counsel for the Acting Administrator argues (Statement, at p. 8) that the meaning of the contracting agency's notation on the wage decision cover sheet ("BUILDING CONSTRUCTION WAGE SCHEDULES FOR MONTGOMERY COUNTY, MD. ONLY APPLY TO THIS PROJECT") is "unquestionably clear and precise" -- that is, only building construction rates apply to this project. Petitioner, on the other hand, argues (Petition, at p. 5) that the contracting agency did not strike the sewer and water line rates from the text of the wage decision, and that the cover sheet notation is "cryptic, imprecise and ineffective to fairly direct attention from the clear division of services, recognized in the industry . . . ." Upon review, the Board concludes that the contracting agency's notation does not provide adequate notice of the agency's intention that only building construction rates were applicable to the Abert Hall project. The notation does not precisely state that only building rates are applicable; instead, the notation states that "BUILDING CONSTRUCTION WAGE SCHEDULES [5] /FN1/ E.g., Granite Builders, Inc., WAB Case No. 85-22 (Jan. 27, 1986). /FN2/ 29 C.F.R. 1.6(c)(3) provides that All actions modifying a general wage determination shall be effective with respect to any project to which the determination applies if notice of such actions is published before contract award . . . . * * * * * (vi) A supersedeas wage determination or a modification to an applicable wage determination, notice of which is published after contract award . . . shall not be effective. [5] ~6 [6] FOR MONTGOMERY COUNTY, MD. ONLY APPLY TO THIS PROJECT." One possible interpretation of this statement is that only building rates -- and no other category of rates -- are applicable to the project. However, it is also possible, and perhaps far easier, to read that notation as an advisory that does not address the applicability of sewer and water line rates to the project's utility work, but instead simply states that of the building rates listed in the general wage decision which encompasses several jurisdictions, the rates that are applicable to this project are the rates for Montgomery County. In particular, we think this would be likely reading of that notation by a utility contractor such as Petitioner and the other contractors who bid on the sewer work which was awarded to Utility Services. In sum, the Board concludes that Petitioner did not have adequate notice of the contracting agency's intention that only building construction rates, and not water and sewer line rates, were to apply to the Abert Hall project. Accordingly, the Board declines to dismiss Petitioner's challenge to the application of building construction rates to the utility work for lack of timeliness. On the merits of this matter, the Acting Administrator concurred in the contracting agency's decision to apply building rates to the entire project, since the utility work was only an incidental portion of the total project cost. The Board agrees with the Acting Administrator that as a general matter the contracting agency's determination is consistent with the guidelines set forth in All Agency Memoranda ("AAM") 130 and 131./FN3/ However, a principal argument by Petitioner before the Board is that the area practice in Montgomery County entails payment of water and sewer line rates for utility work up to a certain distance from the foundation perimeter, at which point plumbers and mechanical contractors performed the work. As counsel for the Acting Administrator properly acknowledged, the guidelines in AAM 130 and 131 would ordinarily give way to an established area practice. The area practice issue was not addressed by the Acting Administrator in her decision, and the Board is unable to determine from the record before it whether the area practice claimed by Petitioner does exist. Accordingly, the Board remands this matter to the Wage and Hour Division for a determination on Petitioner's area practice claim within 30 days. [6] /FN3/ In discussing the classifications and rates to be applied to work which is incidental to the total project, AAM 130 offers the following illustration: For example, water or sewer line work which is a part of a building project would not generally be separately classified. [6] ~7 [7] The petition for review is granted. This matter is remanded to the Wage and Hour Division for further proceedings consistent with this decision. BY ORDER OF THE BOARD: Charles E. Shearer, Jr., Chairman Patrick J. O'Brien, Member Ruth E. Peters, Member ______________________________ Gerald F. Krizan, Esq. Executive Secretary [7]



Phone Numbers