skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

DAIRY DEVELOPMENT, LTD., WAB No. 88-35 (WAB Aug. 24, 1990)


CCASE: DAIRY DEVELOPMENT, LTD. DDATE: 19900824 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of: DAIRY DEVELOPMENT, LTD. WAB Case No. 88-35 FARM FRESH, INC. CHANDLER, OK - UDAG BEFORE: Jackson M. Andrews, Chairman Ruth E. Peters, Member Stuart Rothman, Member, Separate Opinion DATED: August 24, 1990 DECISION OF THE WAGE APPEALS BOARD Petitioners Dairy Development, Ltd., Farm Fresh, Inc., the City of Chandler, Oklahoma, and Kan-Ark, Inc., are before the Wage Appeals Board pursuant to 29 C.F.R., Section 7.9, seeking review of the decision dated June 13, 1988 (Record OO), issued by the Administrator, Wage and Hour Division in the above captioned matter. The Administrator's decision is a final ruling issued pursuant to 29 C.F.R., Section 5.13. The petition for review was filed on July 11, 1988. The parties to this proceeding have consented to disposition without oral argument. [1] ~2 [2] I. BACKGROUND The parties are in basic agreement as to the facts which have given rise to this dispute. (FOOTNOTE 1) The Board bases its decision upon the Petition for Review, the Statement for the Administrator, Petitioners' Reply to the Administrator's statement, and the facts contained in the record. In her ruling, the Administrator first determined that the construction of a dairy products manufacturing plant in Chandler (Lincoln County), Oklahoma is subject to Davis-Bacon (FOOTNOTE 2) prevailing wage labor standards requirements of the Housing and Community Development Act of 1974, as amended (42 U.S.C. 5310; "HCDA"). Further, the Administrator ruled that Petitioners' challenge to the applicable wage determination was untimely. Petitioners now seek review of both rulings. The HCDA authorizes HUD to grant funds under the Urban Development Action Grant program. On May 15, 1985, the City of Chandler ("Chandler") applied to HUD for $3,250,000 in UDAG funds to apply to construction of a dairy products manufacturing plant (the "Plant") of almost 150,000 square feet (Record A). The original grant application (FOOTNOTE 3) specified that the Plant included dairy [2] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ (FOOTNOTE 1) It appears that the only fact-based disagreement is the timeliness of Petitioners' challenge to the correctness of the applicable wage determination in the proceeding before the Administrator. Petition, p. 1. (FOOTNOTE 2) 40 U.S.C. 276a et seq. (FOOTNOTE 3) An amendment (Record GG) to the initial grant application was subsequently submitted by Chandler on January 7, 1986 and was approved by HUD on March 25, 1986 (Record C). This amendment is discussed further, infra at p. 6. [2] ~3 [3] product processing equipment (Id.). The grant application contains the following partial description of the Plant: The proposed building is specially designed and constructed to handle and care for the milk products which will be produced. The refrigeration systems, control systems, floor and wall special finishes, detailed elevation for gravity flow of product and drainage systems are integral parts of the processing system. [. . . ]. Equipment to be purchased for operation of the plant includes stainless steel tanks and vats, processing equipment, handling systems, automated load out system, and a main programmable control system. [. . .]. (Id.; emphasis supplied). Under the grant application, the total estimated cost for the Plant project was $16,920,000; this amount included $7,258,000 for construction of the building structure and $6,006,000 for the purchase and installation of equipment (Id.). The record demonstrates that the equipment to be purchased and installed in the Plant consisted of 14 major items to be purchased from several different vendors; the total approximate cost of this equipment was $5,700,000 (Record JJ, KK). The Developer's estimated budget for the Plant stated the approximate labor cost for installation of the equipment to be $1,047,000 and further indicated that the installation of equipment would be performed by workers classified as ironworkers, pipefitters, millwrights, and electricians (Id.). Petitioners have further stated that the purchase price of four pieces of equipment (FOOTNOTE 4) included the cost of labor for their installation (Record LL). [3] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ (FOOTNOTE 4) These items were the ice cream equipment and hardening tunnel, the water filtering equipment, the material handling equipment, and the boiler (and associated equipment). [3] ~4 [4] Contained in Chandler's May 15, 1985 grant application was the certification that "[a]ll of the construction work will be subject to the Davis-Bacon Act." The Mayor of Chandler signed and submitted the application. Further, on May 24, 1985, Dairy Services, Inc. (the general partner for the plant's developer) submitted its assurance to Chandler that Davis-Bacon compliance would be required of all contractors and subcontractors constructing the Plant (Record A). By letter to the Chandler City Manager, the President of Dairy Services, Inc. clearly stated: This is to certify that during construction of the plant in Chandler, financed in part by UDAG, all contractors and subcontractors will be required to comply with the Davis- Bacon Act. Further, our contracts will require that payroll reports must be submitted to the City of Chandler to insure compliance. On June 21, 1985, HUD notified Chandler that the Plant construction funded "wholly or in part by federal funds is subject to labor standards regulations, including wage rates." (Record R). (FOOTNOTE 5) In this communication, HUD specifically notified Chandler, in pertinent part that: When federal funds are used for any of the following items Davis-Bacon wage rates shall apply to all construction work performed on the building or property concerned: [. . . ] [*] payment for the cost of equipment whose installation requires payment of prevailing wages [*] [. . .; emphasis supplied]. [4] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ (FOOTNOTE 5) Letter from Charles Ming, Manager, HUD, Oklahoma City Office (Region VI) to the Honorable Robert James, Mayor of the City of Chandler. [4] ~5 [5] HUD gave preliminary approval to Chandler's grant application on August 5, 1985 (Record B). Subsequently, an agreement committing $2,750,000 in UDAG funds was executed by HUD on November 18, 1985 and accepted by Chandler on December 30, 1985 (Id.). On December 4, 1985 (prior to Chandler's acceptance of the UDAG fund commitment), HUD provided Chandler with Wage Determination No. OK85-4051 (dated November 29, 1985) for application to construction of the Plant (Record D). On December 31, 1985, Dairy Development contracted for the Plant's construction with prime contractor Kan-Ark, Inc. (Record K). Under this contract, the parties provided that "[a]n allowance of $500,000 has been included for increased labor cost if the project must be built under the provisions of the Davis-Bacon Act." (Id.). That December 31 contract further stated that: The Parties reserve the right to use the lowest wages lawfully available. Any labor cost savintgs [sic] resulting from a total or partial relief from the effect of the Davis-Bacon Act will enure to the benefit of the Owner regardless of whether such savings were obtained by the efforts of the Contractor or Owner or both or neither, and any such savings will reduce the Contract Sum to that extent. (Id.). As previously indicated (supra, note 4), on January 7, 1986, Chandler applied for HUD approval of certain amendments to the UDAG agreement, well after the agreement committing UDAG funds was executed by HUD and accepted by Chandler. Among the requested amendments was one to the effect that the UDAG funding would be used only to purchase milk processing equipment for incorporation [5] ~ [6] into the project (Record GG). On March 25, 1986, HUD approved the amendments, providing, among other things, that the UDAG funds were to be utilized for "partial financing of the capital equipment for the project." (Record C). However, construction of the project had commenced on March 17, 1986 (Record K), prior to HUD's approval of the amendment requested by Chandler. Further, by letter dated March 28, 1986 (Record E), HUD notified Chandler that the amendment to the grant agreement would not alter the application of Davis-Bacon requirements to construction of the Plant. (FOOTNOTE 6) Specifically, HUD's notice stated: There has been some confusion concerning applicability of Davis-Bacon wage rates to the construction of the Farm Fresh Dairy Plant which is a part of the City's Urban Development Action Grant (UDAG) Project. The grant agreement between the City of Chandler and the developer, Dairy Services, Inc. included Davis-Bacon regulations and their assurance of compliance. The UDAG grant agreement is in the process of being amended to transfer the use of UDAG funds from construction of the building to purchase and installation of equipment. This amendment will not change Davis-Bacon wage rate requirements. On March 24, l986 Petitioners submitted a request to the Administrator's office challenging not only the applicability of Davis-Bacon provisions to the Plant's construction but the correctness of the wage rates in the (otherwise) applicable Wage Determination No. OK85-4051 (Record D). As noted, the wage [6] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ (FOOTNOTE 6) Letter from Charles Ming, Manager, HUD Oklahoma City Office (Region VI) to the Honorable Robert James, Mayor of the City of Chandler. [6] ~7 [7] determination had been provided to Chandler by HUD on December 4, 1985. On May 13, 1986, Chandler, the Chandler Industrial Corporation and the developer entered into an agreement whereby Chandler (as Grantee) agreed to loan UDAG funds to the developer. The developer, in turn, agreed to construct the Plant in accordance with the terms of the grant agreement (Record N). II. THE PARTIES' CONTENTIONS On behalf of the Administrator, the Solicitor of Labor argues that Petitioners are contractually bound to comply with the Davis- Bacon prevailing wage labor standards provisions by virtue of the express assurances to that effect given by both Chandler, as Grantee, and the developer, Dairy Development. In response, Petitioners argue that their contractual agreement to pay laborers and mechanics prevailing wages was conditional upon whether the UDAG funds were granted for construction work on the Plant building structure itself or for the acquisition of the equipment to be installed in the Plant's processing and control systems. Petition, pp. 1-2. The Administrator further argues that, notwithstanding the contract which clearly requires Davis-Bacon coverage in this case, the construction of the Plant was subject to Davis-Bacon requirements by operation of law, given the plain meaning of the HCDA's statutory language and the interpretation of that statute by the contracting agency (HUD) which administers the UDAG program under the HCDA. Thus, the Administrator argues that all [7] ~8 [8] construction of the Plant in this case is subject to coverage because the UDAG funds "were authorized under the terms of the grant agreement for the purchase of capital equipment, the purchase price of some equipment items included the cost of installation, and such installation involved substantial amounts of construction." Administrator's Statement, p. 13. In response to this argument, Petitioners characterize the Administrator's position as "an example of ad hoc rule making by the Agency." Petitioners' reply, p. 2. Further, the Petitioners argue that the UDAG funds were "earmarked exclusively for use of capital equipment acquisition . . . and kept segregated from the remaining funds which were to be used for construction of the project." Petition, p. 2. Finally, the Administrator argue that the Petitioners' challenge (dated March 24, 1986) to the correctness of Wage Determination No. OK85-4051 was untimely, having occurred after the start of construction on March 17, 1986. Petitioners respond that their challenge was not untimely, given their contentions that a challenge was not possible until after HUD had given "final approval of the UDAG grant" and that the "final approval was held up and delayed until such time as construction work had already begun on the project." Petition, p. 2. [8] ~9 [9] III. DISCUSSION A. COVERAGE UNDER THE TERMS OF SECTION 110 OF THE HOUSING AND COMMUNITY DEVELOPMENT ACT OF 1974 Our analysis of the applicability of the prevailing wage requirements of the Davis-Bacon Act to construction of the Chandler dairy products manufacturing plant begins with an examination of the terms of the relevant statutory provision, Section 110 of the H[CD]A. As noted earlier, the HCDA authorizes HUD to grant funds under the UDAG program. Section 110 of the HCDA addresses the application of Davis-Bacon requirements to projects, such as the Chandler dairy plant, that are financed with the assistance of UDAG funds. Section 110 provides: All laborers and mechanics employed by contractors or subcontractors in the performance of [*] construction work financed in whole or in part with assistance received under this chapter [*] shall be paid wages at rates not less than those prevailing on similar construction in the locality as determined by the Secretary of Labor in accordance with the Davis-Bacon Act, as amended (40 U.S.C. 276a-276-a-5). [*Emphasis supplied.*] The Administrator concluded that the Chandler dairy plant project involves "construction work financed . . . in part" by UDAG funds and, accordingly, that construction of the plant is subject to Davis-Bacon requirements. Our review of the record likewise leads us to conclude that the Chandler dairy plant project is subject to Davis-Bacon prevailing wage requirements by operation of Section 110 of the HCDA. The record shows that the City of Chandler applied for a UDAG grant to assist in the financing of a dairy products manufacturing [9] ~10 [10] plant. Total estimated cost of the project was $16,920,000, including $7,258,000 for construction of the building structure and $6,006,000 for purchase and installation of equipment. The total estimated cost of the 14 major equipment items was $5,700,000. The developer's estimated budget for the project listed the labor cost for installation of the equipment as $1,047,000, and stated that the installation of equipment would be performed by workers classified as ironworkers, pipefitters, millwrights and electricians. The purchase price of four pieces of equipment, according to petitioners' statements in the record, included the cost of labor for their installation. The total labor costs for installation of these four items is listed as $355,000 (Record JJ). An agreement committing $2,750,000 in UDAG funds was executed by HUD on November 18, 1985 and accepted by Chandler on December 30, 1985. Chandler, on January 7, 1986, applied for HUD approval of some proposed amendments to the grant agreement, including a proposal to the effect that the UDAG funds would be used only for "acquisition and installation" of equipment (emphasis supplied) (Record GG, Exhibit E). HUD, on March 25, 1986, approved an amendment providing that the $2,750,000 in UDAG funds were to be utilized for "partial financing of the equipment for the Project." (Record C). Subsequently, by letter dated March 28, 1986, HUD notified Chandler that "the grant agreement is in the process of being amended to transfer the use of UDAG funds from construction of the building to [*] purchase and installation of equipment. This [10] ~11 [11] amendment will not change Davis-Bacon wage rate requirements." [*] (Record E; [* emphasis supplied. *]) These facts lead ineluctably to the conclusion that the dairy plant project involves "construction work" -- namely, the work involved in installation of equipment in the plant -- financed with the assistance of UDAG funds. The amount of work involved in installing equipment in the dairy processing plant is substantial -- the total labor cost is estimated at more than $1 million, and involves work performed by ironworkers, pipefitters, millwrights and electricians. Furthermore, the purchase price of four equipment items included the cost of installation estimated at $355,000; thus, installation of these four items alone involves a substantial amount of work. In addition, the grant agreement was amended in light of a Chandler request that references use of UDAG funds for acquisition and installation of equipment, and the amended grant agreement, which refers to use of UDAG funds for "partial financing of the equipment" does not limit the use of UDAG funds to equipment acquisition. Indeed, HUD's expressed understanding of the amended agreement in its March 28, 1986 notice to Chandler is that the amended grant agreement encompasses purchase and installation of equipment. In view of all these circumstances -- the substantial amount of work involved in installation of the equipment, the inclusion of the cost of installation in the purchase price of four equipment items, the terms of Chandler's request for amendment of the grant agreement, the language of the amended grant agreement, and HUD's [11] ~12 [12] clearly expressed understanding of the effect of the amended agreement -- the dairy processing plant project involves "construction work financed . . . in part" by UDAG funds, and is subject to Davis-Bacon requirements by operation of Section 110 of the HCDA. Petitioners contend that the UDAG funds were somehow "earmarked" exclusively for capital equipment acquisition. However, the record is simply devoid of any documentation to support the claim that the UDAG funds were "earmarked" for use in the purchase of equipment, and not for equipment installation. Indeed, as discussed above, Chandler's request for amendment of the grant agreement refers to use of funds for purchase and installation of equipment, the terms of the amended agreement do not limit the use of funds to equipment acquisition, and the contracting agency's understanding is that the amended agreement provides funds for purchase and installation of equipment. The Board agrees with the Administrator that "[w]here the terms of the grant permit the use of grant funds for construction work (here, the installation of purchased equipment), any subsequent arbitrary and unilateral action of the grantee or developer in 'earmarking' the UDAG funds will not be recognized as defeating Davis-Bacon coverage of construction of the project." (FOOTNOTE 7) [12] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ (FOOTNOTE 7) Given that the grant agreement permits the use of UDAG funds for both purchase and installation of equipment, petitioners' reliance (Petition, p. 2) on the August 6, 1987 opinion letter of the Attorney General is misplaced. The Attorney General opined that "Section 110 does not require the payment of prevailing wages with respect to installation where [12] [FN7 CONTINUED ON 13] federal funds are provided exclusively for the purchase of equipment and not for its installation." Given the circumstances described above, however, the dairy plant project is not a situation "where federal funds are provided exclusively for the purchase of equipment and not for its installation." [END FN7] ~13 [13] Petitioners additionally contend that the Administrator's position is "an example of ad hoc rule making by the Agency." (Petitioners' reply, p. 2). Petitioners have missed the point of the Administrator's decision and of the essentially factual nature of the Administrator's inquiry. The Administrator did not engage in rule making at all, but simply applied the terms of Section 110 to the facts in the record to determine whether the dairy plant project involves "construction work financed . . . in part" by UDAG funds. Given all the surrounding factual circumstances discussed above, the Board agrees with the Administrator that the project does indeed involve "construction work" (FOOTNOTE 8) -- that is, installation of equipment -- financed with the assistance of UDAG funds. (FOOTNOTE 9) [13] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ (FOOTNOTE 8) The Davis-Bacon regulation which defines the term "construction" explicitly includes appropriate installation of equipment. See 29 C.F.R., Section 5.2(j). (FOOTNOTE 9) The Administrator notes that HUD has taken the position in a November 19, 1987 memorandum, in light of the Attorney General's opinion letter, that: where the purchase price of equipment, machinery or fixtures includes their installation (i.e., the items are sold "installed" and there is no separate charge for that installation), Title I financing of that purchase/installation would trigger Davis-Bacon requirements where the installation involves more than an incidental amount of construction work. While the Board is not bound by HUD's interpretation [13] ~14 [14] B. APPLICATION OF DAVIS-BACON PREVAILING WAGE REQUIREMENTS AS A MATTER OF CONTRACT The Administrator also determined that wholly apart from imposition of Davis-Bacon requirements by operation of Section 110, "both the City and the developer contractually agreed to comply with Davis-Bacon wage requirements in this instance." Upon examination of the record, the Board agrees that petitioners are contractually bound to comply with Davis-Bacon requirements. As a starting point, we note that the grant application of the City of Chandler included Chandler's certification that "[a]ll of the construction work will be subject to the Davis-Bacon Act." Furthermore, in May 1985 the developer's general partner submitted its assurance to Chandler that Davis-Bacon compliance would be required of all contractors and subcontractors constructing the Plant. The amendment to the grant agreement did not remove references to compliance with Davis-Bacon requirements. HUD's March 28, 1986 letter, after amendment of the grant agreement, informed petitioners that the amendment did not change the applicability of Davis-Bacon requirements (Record E). Indeed, HUD's letter made express reference to the fact that the grant ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ [FN9 CONTINUED ON 14] (Reorganization Plan No. 14 of 1950; 5 U.S.C. App.), we do note that the factors cited by HUD in its memorandum highlight the essentially factual nature of the determination as to whether a particular project involves "construction work financed in whole or in part" with the assistance of UDAG funds, thus triggering Davis-Bacon requirements. As stated earlier, it is the Board's view that this task requires an inquiry into all the surrounding circumstances, as conducted by the Administrator in this instance. [14][END FN9] [14] ~15 [15] agreement "included Davis-Bacon regulations and [the city's and the developer's] assurance of compliance." (Id.). After being so advised, Chandler, the Chandler Industrial Corporation and the developer entered into an agreement whereby Chandler agreed to loan UDAG funds to the developer. The developer, in turn, agreed to construct the plant in accordance with the terms of the grant agreement. In light of all these circumstances -- in particular, the assurances in the grant documents of compliance with Davis-Bacon requirements, and the acceptance of UDAG funds after being notified by HUD that the amended grant agreement did not change the applicability of Davis-Bacon requirements -- we agree that petitioners are obligated as a matter of contract to comply with Davis-Bacon requirements in connection with the dairy plant project. Woodside Village v. Secretary of United States Department of Labor, 611 F.2d 312 (9th Cir. 1980); Arbor Hill Rehabilitation Project, WAB Case No. 87-4 (November 3, 1987). C. THE UNTIMELINESS OF PETITIONERS' CHALLENGE TO THE WAGE DETERMINATION The final issue presented to the Board in this matter is whether Petitioners' request for reconsideration of the wage rates contained in Wage Determination No. OK85-4051 was untimely. The record establishes and the Petitioners have not disputed that the challenge dated March 26, 1986 (Record D) was untimely under the applicable Department of Labor regulations at 29 C.F.R, Section 1.6(c)(3). The Plant construction commenced more than one week [15] ~16 [16] prior to petitioners' submission of the request for reconsideration. Petitioners do not dispute the fact that construction of the Plant commenced on March 17, 1986 with "dirt work", in preparation for the building of the Plant structure and the installation of the equipment to follow (Record K). However, Petitioners argue that their untimeliness should be overlooked because the delay was not their of their doing, but rather, was occasioned by HUD's purported delay in processing the amendments which Petitioners had requested. The Board concludes that, irrespective of whose "fault" occasioned the lateness of the March 24, 1986 challenge before the Administrator, the ultimate responsibility for the untimeliness lies with Petitioners. (FOOTNOTE 10) The Board is not persuaded that any "delay" on HUD's part as to approval of the UDAG amendments mitigates the Petitioners' own failure to challenge the substantive correctness of the applicable wage determination. The private parties to the present UDAG agreement had given their assurances that Davis-Bacon rates would be paid in the construction of the Plant as early as May 24, 1985 (Record A). Moreover, HUD specifically informed Chandler on June 21, 1985 that the Davis-Bacon provisions would be applicable to the construction of the Plant in this case (Record R). The record is [16] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ (FOOTNOTE 10) The Board notes that, although HUD took more than three months to approve the UDAG amendments, the record does not support a finding that the delay in filing a challenge before the Administrator was occasioned by HUD. The Petitioners clearly could have filed their request for reconsideration of Wage Determination No. OK85-4051 with the office of the Administrator regardless of whether HUD had or had not approved the January 7, 1986 requested amendments by the time construction had commenced on the Plant. [16] ~17 [17] clear that the applicable wage determination was provided to Chandler in a timely manner on December 4, 1985 (Record D). This was more than three weeks prior to Chandler's acceptance of the UDAG commitment of funds for the Plant on December 30, 1985. Further, although the contract for construction was signed by the respective parties on December 31, 1985, no construction was performed on the Plant project until March 17, 1986. Thus, Chandler and the other Petitioners in this matter had full notice of the specific Davis-Bacon rates required to be paid in constructing the Plant more than three months before the commencement of construction activity. A timely challenge to the prevailing wages listed in Wage Determination No. OK85-4051 could therefore have been taken to the Administrator at any point during this period of more than three months, regardless of HUD's processing of the amendments to the original UDAG agreement. In this respect, the controlling regulation is explicit that a challenge could have been taken at any time after December 4, 1985 when the applicable wage determination was sent to Chandler, but before the start of construction. 29 C.F.R., Section 1.6(c)(3). It is well-established that the individual contracting agencies are charged with an initial determination of Davis-Bacon applicabil[i]ty. See Reorganization Plan No. 14 of 1950 (64 Stat. 1267; 5 U.S.C. App.). In this case, HUD clearly and repeatedly informed Petitioners that Davis-Bacon labor standards would apply to this grant. It is, in any event, also well-established that the final determination of such matters is that of the Secretary of [17] ~18 [18] Labor alone. North Georgia Bldg. & Const. Trades v. Goldschmidt, 621 F.2d 697, 701-02 (5th Cir. 1980); Arbor Hill Rehabilitation Project, supra. The Board acknowledges the fact that the Department's regulations regarding the timeliness of wage determination challenges are strict. Nevertheless, the principle that challenges to wage determinations must be made in a timely fashion is well- founded, being both reasonable and indispensable to the even-handed enforcement of the Davis-Bacon and related Acts. The Board has consistently ruled that in order for a challenge to be considered timely, it is a prerequisite that such action be taken prior to contract award, or the start of construction where there is no contract award. In the absence of such a timeliness rule, one of the basic purposes of the Davis-Bacon and Related Acts would be rendered meaningless. This was previously emphasized by the Board when it stated: One of the purposes of the Davis-Bacon Act is to protect laborers and mechanics by assuring that contractors know in advance of bidding what their approximate labor costs would be. Universities Research Association v. Coutu, 450 U.S. 754, 776 (1981). The wage determination process generally removes wages as a method of cutting the contract price to obtain a contract and places bidders on a relatively even competitive footing regarding wages paid by placing a floor thereunder. M.A. Mortenson Company, WAB Case No. 87-50 (February 17, 1989), at p. 6. It is vital to ensure that contractors competing for federally-assisted construction contracts know their required labor [18] ~19 [19] costs in advance of bidding. Manifest injustice to bidders would result if the successful bidder on a project could challenge his contract's wage determination rates after all other competitors were excluded from participation. The timeliness requirements are among the Board's longest- standing precedents concerning challenges to wage determinations and the Board has consistently endorsed the restriction against challenges which are untimely. Gananda Development Corporation, WAB Case Nos. 73-13 and 73-14 (May 14, 1977); Jordan & Nobles Construction Company, WAB Case No. 81-18 (August 19, 1983); Kapetan Incorporated, WAB Case No. 87-33 (September 2, 1988); M.A. Mortenson, supra at 6-7. The Department of Labor has promulgated regulations which mandate timely challenges. In this regard, the provisions at 29 C.F.R., Section 1.6(c)(3)(1983) have codified the Board's rulings regarding the requirement for timeliness. Specifically, this regulation, in pertinent part, mandates that: All actions modifying a general wage determination shall be effective with respect to any project to which the determination applies, [*] if published before contract award ( or the start of construction where there is no contract award) [*] except as follows: [The regulations proceed, listing certain exceptions and specifications which are not applicable here.] (vi) Modification or supersedeas wage determinations to an applicable general wage determination published after contract award [*] (or after the beginning of [19] ~20 [20] construction where there is no contract award) shall not be effective. [*] Id.; [*] emphasis supplied [*]. In this case, Petitioners were clearly bound to meet the standard of timeliness in 29 C.F.R., Section 1.6(c)(3). Accordingly, the Board affirms the Administrator's ruling that Petitioners challenge to Wage Determination No. OK85-4051 was untimely. The decision of the Wage and Hour Administrator in her letter of June 13, l988 is affirmed. The petition is dismissed. - - - Opinion of Member Rothman The Administrator's final ruling, contained in her letter to Petitioners dated June 13, l988 states: "A review of these facts leads us to conclude that the project involves 'construction work financed . . . in part by UDAG funds and therefore construction of the dairy processing plant is covered by the Davis-Bacon labor standards provisions of the Housing and Community Development Act." Also, "The UDAG grant agreement authorized the use of UDAG funds for partial financing of equipment, without specifying purchase or installation." As discussed above, the contract price included the cost of installation for some of this equipment. Where the terms of the grant permit the use of grant funds for construction work (here, the installation of purchased equipment), any subsequent arbitrary and unilateral action by the grantee or developer in 'earmarking' the UDAG funds solely for equipment purchase will not be recognized [20] ~21 [21] to defeat Davis-Bacon coverage of construction of the project. Equally, if not more importantly, the Administrator's letter of June 13, l988 states, "Moreover, both the City and the developer contractually agreed to comply with Davis-Bacon wage requirements in this instance", and further ". . . in doing so, the developer agreed to construct the dairy processing plant in accordance with the terms of the grant agreement, which explicitly required compliance with the Davis-Bacon prevailing wage requirements for 'all of the construction work.'" HUD had advised the city, the developer, and the contractor that Davis-Bacon requirements had not changed by its amendment that the $2,750,000 grant was to be used for equipment purchase. A UDAG grant in a particular case may be exclusively earmarked for equipment purchases only and where that is the clear unequivocal intent and purpose expressed in advance, such exclusive earmarking would not make the construction of the project subject to the Davis-Bacon Act. The Board in this case, however, concludes that in view of the parties' agreement that the Davis-Bacon Act will be applicable to all construction, it was not the intent of HUD at the time the grant was made or of the grantee in accepting the grant to drop a curtain between the use of the granted monies for equipment purchases as distinguished from construction. The express requirement was never changed by HUD in this case. The Administrator points to the factor that certain of the equipment purchased included on-site installation by the vendor. This bolsters the Administrator's position, but that is not the main [21] ~22 [22] point upon which the decision of the Administrator is affirmed. In the case in which HUD makes a deal with the grantee exclusively dedicating granted funds for equipment procurement only, such determination must be made clearly and unequivocally by HUD before construction begins and must be expressed as a term and condition of the grant. I believe it will be the rare case where such a clear cut determination would be made. It must be clear cut however to offer guidance that HUD and the Administrator can follow in the administration of the Davis-Bacon Act. Unless it can be said without equivocation that HUD entered into the loan arrangement with its eyes wide open that the grantee did not intend to comply with the Davis-Bacon Act for construction but was seeking funds solely for equipment purchases, the Administrator is not in a position to conclude that the Davis-Bacon Act is not applicable. Once UDAG funds are committed to the grantee on the basis that the grantee has agreed that the construction work will be subject to the Davis-Bacon Act in whole or in part, the grantee cannot thereafter reallocate funds in such a way as to result in removal of the construction of the project from Davis-Bacon coverage. HUD and the grantee/developers made the initial deals to get the UDAG grant based on a project subject to Davis-Bacon Act coverage. It effectuates the public purposes of the Davis-Bacon Act that the deal be lived up to. HUD's suggestion that the Davis- Bacon Related Acts (DBRA) requirements be put aside in this case are unpersuasive in view of the repeated HUD admonitions to the [22] ~23 [23] grantees that the DBRA requirements would apply to the construction. The Petitioners contend that the Davis-Bacon wage predetermination schedules were much higher than the actual prevailing wages in the locality. Petitioners present no specific survey data that this was the case, but under the circumstances of this case, such contention, supported by a survey or not, is inappropriate. An attack upon the accuracy of particular classifications in a wage schedule is something that must be done in connection with the award of the construction contract. In the case in which an award is not made on a competitive bid basis, but is the subject of negotiation, as it is in a number of DBRA programs, the attack upon the published Davis-Bacon predetermined wage schedules should be brought to the attention of the Department of Labor as a part of the ongoing negotiations with respect to the particular funding. Here the Board upon the review of the record is satisfied that the grantees were aware of the Davis-Bacon Act requirements in such negotiations and agreed to their application in the construction of the project. The contention of the Petitioners that the grant agreements were entered into with HUD on an understanding that maybe the Davis-Bacon wage schedule would apply and maybe it would not, and that that was something that remained to be seen or worked out, is not a permissible basis upon which a government agency making loans or grants can predicate the giving of federal funds by loan or grant and expect the government agency or the Administrator to be [23] ~24 [24] able to make the necessary Davis-Bacon decisions. Suffice it to say that my examination of the record in this case convinces me that HUD did not do so in this case. Petitioners claim there has been a procedural lack of due process in violation of the Administrative Procedures Act. The Administrator contends that the petition was not timely filed. I reject both contentions. The Wage Appeals Board should cut through the procedural arguments on both sides and resolve the issue in this case on whether the Administrator in considering its merits reached the correct decision. The Board's decision in Muskogee Shopping Mall, WAB 85-26, and the dissent therein are not apropos this case, nor is the majority view in Arbor Hill Rehabilitation Project, supra, pertinent here. - - - BY ORDER OF THE BOARD: __________________________ GERALD F. KRIZAN, ESQ., Executive Secretary Wage Appeals Board [24]



Phone Numbers