skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

GREEN ISLAND ASSOCIATES, WAB No. 86-21 (WAB Aug. 7, 1987)


CCASE: GREEN ISLAND ASSOCIATES DDATE: 19870807 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D.C. In the Matter of GREEN ISLAND ASSOCIATES WAB Case No. 86-21 Bolton, New York Dated: August 7, 1987 APPEARANCES: Robert J. Bray, Esquire, and George A. Massih III, Esquire, for L. F. Driscoll Co.; Joseph Walsh, Esquire, for Green Island Associates Katherine Waldbauer, Esquire and Douglas Davidson, Esquire, for the Administrator, Wage and Hour Division, U.S. Department of Labor BEFORE: Alvin Bramow, Chairman, Stuart Rothman, Member, Concurring separately & Thomas X. Dunn, Member, Concurring in part and dissenting in part. DECISION OF THE WAGE APPEALS BOARD This case is before the Wage Appeals Board on the Petition of Green Island Associates (hereinafter GIA) seeking review of the decision of the Wage and Hour Administrator as published in Wage Decision S-85-NY-0324 issued September 23, 1985. This wage decision was issued to apply to the renovation and construction of the Sagamore Hotel on Green Island in the Town of Bolton, Warren County, New York. The wage decision in question was issued by the Wage and Hour Division as the result of an earlier decision by this Board, WAB Case No. 85-04. The earlier decision remanded the appeal to the Administrator to resurvey the area applicable to Bolton, New York, because construction and renovation of the hotel had begun in July, 1983, and the Wage and Hour Administrator was not aware of this fact. The Board directed the Wage and Hour Division to issue an Advisory Opinion reflecting wage rates prevailing at the time construction [1] ~2 [2] started, or when the contract was awarded. On September 25, 1985, the Wage and Hour Division issued a new wage determination applicable to the construction and renovation of the Sagamore Hotel. The total project is valued at $56 million. The original petitioner is the developer of the project. L.F. Driscoll Company is the contractor and has intervened in support of the developer. GIA was awarded a $5.275 million Urban Development Action Grant (UDAG) by the Department of Housing and Urban Development to partially finance the project. The wage rates contained in the reissued wage determination reflect approximately a 10% reduction of wage rates from those originally issued by Wage and Hour. Petitioners contend, however, that the wage determination does not reflect wages paid on construction in the Bolton area, but mainly come from construction projects in the Glens Falls urban area. Glens Falls is also located in Warren County. Petitioners characterize the wage rates issued by Wage and Hour as those negotiated by the local unions in the Albany, Schenectady and Troy metropolitan areas. Petitioners argue that they should be allowed to utilize a schedule of residential construction wage rates which Wage and Hour also issued in wage determination S-85-NY-0324 since the construction on the three-story, wooden frame hotel involves the same construction techniques, material and skills as are required for residential construction. The Wage and Hour Division has presented the Board with a motion to dismiss GIA's petition for review as untimely. The renovation of the hotel is completed and the petitioners' challenge to the wage rates was not initiated until after construction had started. No sums of money have been escrowed to assure that the laborers and mechanics will be paid the estimated $500,000 in back wages due employees on the project if the Board upholds the Administrator. [2] ~3 [3] The Wage and Hour Division disputes the petitioners' contention that they should be allowed to pay residential wage rates and asserts that it was proper to issue the wage rates contained in wage decision S-85-NY-0324 because its survey demonstrated that negotiated wage rates prevailed in Warren County at the time for which the survey was made. Wage and Hour further asserts that considering projects in all of Warren County was appropriate because of the small amount of construction which had been performed in the Town of Bolton itself, and that Wage and Hour's regulations, 29 CFR sec. 1.7, provide for considering the county as the normal entity for conducting wage rate surveys for Wage and Hour purposes. The Building and Construction Trades Department, AFL-CIO, has intervened in this case and filed a memorandum with the Board in support of the Administrator's motion to dismiss and the statement filed on behalf of the Administrator. On May 19, 1987, the Wage Appeals Board held an oral hearing at which all interested persons were present and represented by counsel, and in which all interested persons have participated. * * * The Wage Appeals Board indicated in its Notice of March 26, 1987 that the subject of the hearing would include the Administrator's Motion to Dismiss the Petition on the basis that the Appeal is untimely as well as the appropriate wage rates to be applied to the renovation and construction of the Sagamore Hotel in Bolton, Warren County, New York. The Board believes that it should rule on the primary issue of the appropriate wage rates and, then if necessary, consider the Motion to Dismiss for untimeliness. The definition of the term "area" used in the Department of Labor Regulations, 29 CFR sec. 1.2(b) indicates that in determining wage rates under the [3] ~4 [4] Davis-Bacon and related acts, area shall mean the city, town, village, county or other civil subdivision of the State in which the work is to be performed. The Regulations at 29 CFR sec. 1.7(a) further state in part that in making a wage determination, the "area" will normally be the county. Even though the county is the normal area considered by the Wage and Hour Division for the source of wage rate data for making wage determinations, the Regulations certainly allow a deviation from this norm. However, to use a smaller area than the county, it must be shown by substantial project data that it is inappropriate to apply wage rates from the normal geographic unit of consideration to the area of the county in question. Therefore, the Board must consider the nature of the project to be constructed along with the wage rate information in the area of the proposed project to determine if separate wage rates are appropriate. The project to be constructed is the complete gutting, refurbishing and reconstructing of the interior of the Sagamore Hotel. The Board in the past has considered hotel work as falling into the general category of "building construction". As this Board stated in In the Matter of Wage Rates for Biscayne Retirement Home, WAB Case No. 83-02 (1983), . . . this building is not, in a construction sense, a project of a character similar to the usual lowrise residential apartments or single family homes from which the residential wage rate information is compiled in wage and hour surveys. The Board considers this facility to be similar to [*] hotel, motel [*], clinic, hospital, dormitory, barrack or low rise commercial construction, all of which are included in the general category of building construction and are issued building construction wage rates by the Wage and Hour Division. [*Emphasis added.*] In view of the fact that the construction comes within the category of building construction, the Wage and Hour Division must only look to [4] ~5 [5] building construction wage data and not residential construction in making an applicable wage determination for the Sagamore Hotel project. The record in this case only reveals some very limited amount of building construction in the vicinity of Bolton which shows crafts such as carpenters and laborers being paid at lower rates than those contained in wage determination No. 5-85-NY-0324 which was issued by the Wage and Hour Division for application to the Sagamore Hotel project. This information is not sufficient in scope for the Wage and Hour Administrator to deviate from her normal geographical unit of consideration, i.e., the entire county in the use of wage data for making a wage determination. The petitioners request that even if the wage rates contained in wage determination No. 5-85-NY-0324 are correct it should be rescinded under the rationale of Muskogee Shopping Mall, WAB Case No. 85-26 (January 21, 1986). In that case this Board held that the provisions of regulation 29 CFR 1.6(f) authorizing the Administrator to include a wage determination after contract award or after beginning of construction would apply only with respect to contracts for which bids were solicited or negotiations were concluded on or after June 28, 1983. The same rationale applies to the provisions of 29 CFR 1.6(g) which govern this case. It is not clear to the Board that negotiations between the city and the developer were concluded prior to the effective date of the regulation. There appears to be some discrepancy as to the time frame which must be resolved. If the negotiations were concluded, then the Board would rule as in Muskogee that the Wage and Hour Division has no authority to issue a wage determination. [5] ~6 [6] However, there appears to be a second discrepancy which needs clarification. Did the petitioners have knowledge that Davis-Bacon labor standards applied to this project prior to the conclusion of negotiations and the start of construction? The Wage and Hour Division maintains that petitioners had knowledge, whereas, petitioners contend that they were unaware of any such requirements prior to conclusion of the negotiations and start of construction. This is an important element in view of this Board's decision in Granite Builders, Inc., WAB Case No. 85-22 (January 27, 1986), wherein the Board stated in part: . . ., it appears to the Board that the only reason an appropriate wage determination was not given to the petitioner or the owners was due to their reluctance or negligence in obtaining the labor standards required by the loan agreement. It was incumbent upon them to go forward with all of the requirements of their agreement. This type of activity cannot be endorsed by the Board as an excuse to avoid Federal labor standards laws and regulations. The record is not conclusive on these points so that the Board can resolve the issues. Therefore, the case is remanded to the Administrator to make an investigation concerning these matters and, thereafter, to make a decision in accordance with the above guidelines. * * * Member Rothman, Concurring I concur in the remand for the reasons stated. I take no position whether in the Bolton locality the renovation and rehabilitation of a wooden, three-story, rambling structure built over 100 years ago as a hotel, would in today's market conditions be classified by the local building and construction [6] ~7 [7] industry as normal building and commercial construction or as the type of construction classified for Davis-Bacon purposes as residential, four-story or less. The factual record is not sufficient to reach a conclusion on such a point, and there is no reason at this time to resort to presumptions in such a special case. * * * Member Dunn, Concurring in part and dissenting in part. I concur with Chairman Bramow's findings and conclusions in this case, except for the conclusion that the Board has no authority to issue a wage determination in this case if negotiations between the City of Bolton and the developer, Green Island Associates, to purchase the Sagamore Hotel and surrounding lands were concluded prior to the effective date of 29 CFR sec. 1.6(g). The majority relies on its holding in Muskogee Shopping Mall, supra, to justify its conclusion. The Board, in Muskogee Shopping Mall, recognizing the limit imposed by the Secretary, concluded that it was without authority to direct the Wage and Hour Administrator to issue a prevailing wage determination applicable to the project because it found that the negotiations between the City of Muskogee and the project developer were concluded prior to the effective date [of] 29 CFR sec. 1.6(f). Prior to the promulgation of 29 CFR sec. 1.6(f) in 1983, the Board and the courts held that Davis-Bacon prevailing wage determinations could not be incorporated in federally funded construction contracts after award or beginning of construction. /FN1/ However, the courts recognized that the post-award incorporation of wage determinations would be permissible if the Labor Department [7] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN1/ See, Installation of Conveyor System, Naval Supply Center, WAB Case No. 78-24 (Apr. 6, 1979; 40 Comp. Gen. 565, 570-571 (1961); Universities Research Association v. Coutu, 450 U.S. 754, 761, n. 9 (1981).[7] ~8 [8] promulgated appropriate regulations. /FN2/ Accordingly, the Secretary of Labor promulgated a new CFR Part 1 on April 29, 1983, which became effective on June 28, 1983. The preamble to the newly promulgated 29 CFR, Part 1 stated: The provisions of this part shall be applicable only as to wage surveys compiled on or after June 28, 1983, except for sec. 1.6 which shall be applicable only to contracts entered into pursuant to invitations for bids issued or negotiations concluded on or after June 28, 1983. None of the revisions herein shall be applicable to any contract entered into prior to June 28, 1983. 48 F.R. 19532 (Apr. 29, 1983). The majority believes it is bound by the Secretary's limitation on the applicability of 29 CFR sec. 1.6. It does not follow however, that the Board is precluded from requiring the contractors and subcontractors employed by Green Island Associates and its construction manager, L.F. Driscoll, on the Sagamore Hotel project to comply with otherwise applicable Davis-Bacon prevailing wage requirements. Section 1.6(g) of 29 CFR Part 1 provides: (g) If federal funding or assistance under a statute requiring payment of wages determined in accordance with the Davis-Bacon Act is not approved prior to contract award (or the beginning of construction where there is no contract award), the agency shall request a wage determination prior to approval of such funds. Such a wage determination shall be issued based upon the wages and fringe benefits found to be prevailing on the date of award or the beginning of construction (under the National Housing Act, under section 8 of the U.S. Housing Act of 1937 or where there is no contract award, as appropriate, . . . . The Secretary proposed this regulation after the Board ruled in Hartsfield International Airport, WAB Case No. 77-24 (Feb. 25, 1977) that Davis-Bacon rules and regulations do not apply to projects that receive federal funding after contract award and commencement of construction. The Board's decision was later reversed in [] North Georgia Building and Construction [8] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN2/ Universities Research Association v. Coutu, 450 U.S. at 761, n.9 (1981) [8] ~9 [9] Trades Council v. Goldschmidt, 23 Wage & Hour Cases 250 (N.D. Ga. 1977), affirmed in part and remanded, 621 F.2d 697 (5th Cir. 1980), which held that under such circumstances, Davis-Bacon prevailing wage rates are retroactively applicable to the project from the time construction began. After 29 CFR sec. 1.6(g) was published for comment in late 1979 (44 FR 77026, Dec. 28, 1979) one commentator questioned the Labor Department's authority to require retroactive application of Davis-Bacon prevailing wage rates. In response, the preamble to the January 16, 1981 final regulation stated that "the Department's position in this regard is consistent with the recent decision in North Georgia Building and Construction Trades Council v. Goldschmidt" 621 F.2d 697 (5th Cir. 1980) 46 FR 4309 (Jan. 16, 1981). /FN3/ Accordingly, unlike sec. 1.6(f) which changed pre-existing law /FN4/ sec. 1.6(g) is simply the codification of pre-existing law. In other words, if the Secretary had never promulgated sec. 1.6(g) as a final rule, the Board would still be authorized to find that Davis-Bacon prevailing wage requirements apply retroactively to the Sagamore Hotel project on the basis of the holding in North Georgia, supra. /FN5/ Thus, the effective date of sec. 1.6(g) is irrelevant to the resolution of this case. [9] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN3/ Implementation of the Jan. 16, 1981 regulations was delayed by Labor Secretary Donovan on several occasions until August 14, 1981 (46 FR 41,444 et seq.) at which time new proposed Davis-Bacon regulations were published for comment. Proposed 29 CFR sec. 1.6(g) was not changed, however, and was promulgated as a final rule on April 29, 1983 in the same form originally proposed on December 28, 1979. ÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN4/ See footnote 2. ÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN5/ The majority states that, if the negotiations between the City of Bolton and Green Island Associates were completed before the effective date of sec. 1.6(g), it would rule that the Administrator has no authority to issue a wage determination. Such a holding would be consistent with the rationale for the holding in Hartsfield International Airport, supra, which the Fifth Circuit overruled. [9] ~10 [10] For this reason, I must respectfully dissent from that part of the majority opinion which remands the case to the Wage and Hour Administrator to determine whether negotiations between the City of Bolton and Green Island Associates were concluded before the effective date of 29 CFR sec. 1.6(g). BY ORDER OF THE BOARD Craig Bulger, Executive Secretary [] [10]



Phone Numbers