skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

ATCO CONSTRUCTION, INC., WAB No. 86-01 (WAB Aug. 22, 1986)


CCASE: ATCO CONSTRUCTION, INC. DDATE: 19860822 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D.C. In the Matter of ATCO CONSTRUCTION, INC. WAB Case No. 86-01 405 Family Housing Units Adak NAS, Alaska Dated: August 22, 1986 Contract N62474-83-C2569 APPEARANCES: Terry R. Yellig, Esquire, for the Oregon State Building and Construction Trades Council, AFL-CIO, and the Building and Construction Trades Department, AFL-CIO. Robert J. Miller, Esquire, Douglas Davidson, Esquire, for the Wage and Hour Division, U.S. Department of Labor BEFORE: Alvin Bramow, Chairman, Thomas X, Dunn, Member, and Stuart Rothman, Member, filing a separate opinion. DECISION OF THE WAGE APPEALS BOARD This case is before the Wage Appeals Board on the petition of the Oregon State Building and Construction Trades Council, AFL-CIO, and the Building and Construction Trades Department, AFL-CIO, (hereinafter petitioners) seeking review of an October 30, 1985 ruling of the Deputy Administrator of the Wage and Hour Division, U.S. Department of Labor. This ruling concerned the application of the Davis-Bacon Act to the fabrication of 405 modular housing units by ATCO Construction, Inc., (ATCO) in [1] ~2 [2] Portland, Oregon, for erection at the Adak Naval Air Station, Alaska. The Deputy Administrator ruled that in view of the 3000 mile distance between the fabrication site in Oregon and the location where the housing units are to be erected, the fabrication site was not part of the site of work for Davis-Bacon purposes. Therefore, he concluded that ATCO's employees working in Portland were not subject to the prevailing wage requirements of the Davis-Bacon Act. The facts concerning this dispute are not complicated. ATCO is a subsidiary of J.A. Jones Construction Company, the prime contractor, which was awarded a contract by the U.S. Navy to design and construct 405 housing units on government-owned land at the Adak Naval Air Station in the Aleutian Islands in Alaska. ATCO is constructing the houses in Oregon and shipping them on concrete slabs to Alaska. J.A. Jones is constructing the utility services, roads, walks, site grading and drainage and overseeing the installation of the houses on Adak, which will result in a complete and usable housing facility. At Portland, ATCO constructed a temporary metal building for the purpose of fabricating the modular housing units for delivery to Adak. The metal building, which is to be removed by December, 1986, is described as a "temporary framing shop to fabricate housing units for shipping to Alaska". The work being performed in Alaska is subject to the labor standards provisions of the Davis-Bacon Act. The construction in Portland [2] ~3 [3] was not covered by the Davis-Bacon labor standards provisions. The Deputy Administrator's October 30, 1986 ruling in response to an inquiry by petitioners stated that the Davis-Bacon Act pro- visions apply only at the "site of the work" and that in this case the distance of 3000 miles between the fabrication facility and the location where the modular housing units are to be assembled is too great for the facility to be considered as a part of the "site of the work". On December 30, 1985, the petitioners appealed this ruling to the Wage Appeals Board. The petitioners argue that the fabrication facility devoted exclusively to the construction of military family housing in Alaska should be covered by the Davis- Bacon Act regardless of its distance from the actual construction site. The Wage and Hour Division relies on a line of cases decided by this Board which have established an exclusive or nearly exclusive use or dedication test, and a geographical test for covering fabrication plants, batch plants, and borrow or gravel pits located on adjacent or nearby property to a covered construction site. Following these cases, Wage and Hour argues that it would not be proper for the Board to cover the work performed by ATCO in Oregon or to consider a challenge to the Secretary's regulations. It further urges that the Department is bound by its own regulations. [3] ~4 [4] The Wage Appeals Board considered this appeal on the basis of the Petition for Review filed by petitioners, and the Statement on Behalf of the Deputy Administrator and the record of the case before the Wage and Hour Division filed by the Solicitor of Labor. On May 20, 1986, the Board held an oral hearing at which all interested persons were present and participated. * * * The Wage Appeals Board realizes that the Davis-Bacon Act requires the payment of those rates found to be prevailing to all laborers and mechanics employed "directly upon the site of work". The Department of Labor's regulation defines this statutory language at 29 CFR [sec] 5.2(l) which reads in pertinent part as follows: (l) The term "site of the work" is defined as follows: (1) The "site of the work" is limited to the physical place or places where the construction called for in the contract will remain when work on it has been completed and, as discussed in paragraph (l)(2) of this section, other adjacent or nearby property used by the contractor or subcontractor in such construction which can reasonably be said to be included in the "site". (2) Except as provided in paragraph (l)(3) of this section, fabrication plants, mobile factories, batch plants, borrow pits, job headquarters, tool yards, etc., are part of the "site of the work" provided they are dedicated exclusively, or nearly so, to performance of the contract or project, and are so located in proximity to the actual construction location that it would be reasonable to include them. [4] ~5 [5] The Wage Appeals Board in past cases has consistently upheld functional and geographical tests in determining the "site of the work". See United Construction Company, Inc., WAB Case No. 82-10 (January 14, 1983), Mayfair Construction Company, WAB Case No. 81-16 (April 18, 1983), Ontario Pipeline, Inc., and Farmington Concrete Products, Inc., WAB Case Nos. 81-12, 81-13 (January 28, 1985), and ABC Paving Co , WAB Case No. 85-14 (September 27, 1985). The Wage and Hour Division based its decision that all work in connection with this project not performed on Adak Island was not within Davis-Bacon Act coverage because it was performed 3000 miles away from the Adak construction site. It concluded that this was too remote to come within the Davis- Bacon Act axioms, principles and the Department's regulations. Therefore, the work was not covered. However, the Wage Appeals Board is of the opinion that this case may be an anomaly. The Department of the Navy contracted for construction of residential housing to house military personnel and their families on Adak Island. Adak Island is far out in the Aleutians. The successful bidder performed a portion of the work at Portland, Oregon, some 3000 miles away, by sea. An examination of the map shows that Portland is about as close in the Continental United States as you can get to Adak Island. Mainland Alaska isn't that much closer for purposes of this case. [5] ~6 [6] The Board was not told what the work was that was performed at Portland. Therefore, the Board asked the Office of the Solicitor representing Wage and Hour to secure and submit to the Board a copy of the bid documents including the project specifications and also photographs of the residential units in the course of construction if such photographs were available. Such photographs of the housing units at Portland, Oregon, and copies of specifications, but not the bid document forms, were submitted after the close of oral arguments. The documents and photos submitted show that the houses were substantially built in Portland. This information further shows that these residential housing units were built or assembled at Portland upon a concrete slab. Then the slab and the housing built or assembled on it are taken by barge to Adak Island. This appears to be the factual situation. Under this set of facts Portland, where the housing units are being built or assembled on concrete slabs, must be considered part of the "site of the work". Therefore, the Davis-Bacon Act is applicable to the construction of these housing units pursuant to the applicable Davis-Bacon Act wage rates in the Portland, Oregon, area for the crafts involved based on area practice for the type and nature of the work. [6] ~7 [7] The factory fabrication and prefinishing of metal roofing, fascia, panels, clapboard siding, trim bands, board and batt[e]n siding, other metal siding and other prefabricated and prefinished "closures" are not generally covered by the Davis-Bacon Act, taking into account standard Davis-Bacon principles concerning materials and supplies. However, the temporary fabrication framing shop used to fabricate the housing units is located in reasonable proximity to the actual construction location. Under the rules laid down in 29 CFR [sec] 5.2(l)(2) this fabrication plant (shop) would be considered to be included as part of the "site of the work". It follows that the Davis-Bacon Act is applicable to this fabrication work as well as the construction of the housing units on the concrete slabs. In view of the above, the case is remanded to the Wage and Hour Division to include the appropriate prevailing wage rates for the workers performing work on housing units built or assembled on the concrete slabs and the workers performing work at the fabrication shop in Portland, Oregon. * * * Member S. Rothman files the following separate opinion. I would remand this case to the Wage and Hour Administrator for a fuller determination of the facts pursuant to the following guidelines. The Board has not been given enough facts to decide [7] ~8 [8]all of the issues in this case. 1. If this residential housing which was built on concrete slabs at Portland, Oregon, for removal to Adak Island used conventional construction and erection methods and technologies, and employed laborers and mechanics in the conventional and identifiable building and construction crafts, the prevailing Davis-Bacon wage determination should apply to such construction. Photographs of the housing would indicate that this was conventional residential construction to be erected at Portland and transported to Adak Island on barges. But this should be checked out by the Wage and Hour Administrator. I concur in principle with the decision of the majority on this point. 2. If, upon a fuller factual investigation, this residential housing was manufactured according to the methods and technologies presently prevailing in the Portland, Oregon, area for the manufacture of mobile homes, and this housing is more comparable to a mobile home than it is to conventional construction and erection of residential housing, the Davis-Bacon wage determination should not apply. 3. This is indeed an anomalous situation with the fabrication of materials and the construction of housing at a temporary location in preparation for transporting the product constructed 3000 miles away to Adak Island. Although the fabrication of the basic components of the buildings took place in proximity to the construction project, it does not necessarily follow under [8] ~9 [9] the special circumstances that the fabrication work should be governed by the Davis-Bacon Act. If the prefinished metal roofing, fascia panels, clapboard siding, trim bands, board and batten siding, other metal siding and other prefabricated and prefinished "closures" as specified in the project plans are comparable to factory-fabricated or shop-fabricated materials, equipment, and supplies, this portion of the work should not be covered by the Davis-Bacon Act, taking into account standard Davis-Bacon principles concerning procurement of material and supplies. However, if the fabrication of these component parts of the housing was integrated, part and parcel, with the construction of the buildings using the same laborers' and mechanics' crafts and classifications interchangeably with the construction of the buildings, then it would appear that the Davis-Bacon Act would have to apply. These are factual questions requiring fuller investigation. 4. As meager as is the information given to the Board by the parties to this dispute, there is reason to believe that the logistics of this project including where construction prefabrication or manufacture were to take place being obviously p[er]tinent to government costs and the successful bidders' overall performance, the government agency or agencies involved may have overlooked specifying matters required to be specified in the contract documents, including the application of the Davis-Bacon Act Although it seems apparent that this housing would be constructed and erected away from Adak Island, namely, on the [9] ~10 [10] mainland, the contracting agency did not include the appropriate Davis-Bacon wage determinations in the contract document. I infer that any responsible contracting agency would have required the successful bidder to explain its construction plans before the award. On the remand which I propose, the Wage and Hour Administrator has the alternative of determining the extent and status of completion of the project in view of the delays which have taken place and to apply the Davis-Bacon Act or if the project is completed to take a non-enforcement position; the principles established herein to be applicable to future projects of this kind. BY ORDER OF THE BOARD Craig Bulger Executive Secretary, Wage Appeals Board [10]



Phone Numbers