skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

HARRY JOHNSON PLUMBING CO., INC., WAB No. 84-19 (WAB June 6, 1985)


CCASE: HARRY JOHNSON PLUMBING CO DDATE: 19850606 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D.C. In the Matter of HARRY JOHNSON PLUMBING CO., INC. WAB Case No. 84-19 Walla Walla, Washington EPA Contract No. 0599-0600 Dated: June 6, 1985 BEFORE: Alvin Bramow, Chairman, Thomas X. Dunn, Member Stuart Rothman, Member DECISION OF THE WAGE APPEALS BOARD This case is before the Wage Appeals Board on the petition of Harry Johnson Plumbing Company, Inc., (hereinafter Harry Johnson Plumbing) seeking review of a decision of the Department of Labor dated July 25, 1983 denying the Environmental Protection Agency's (EPA) recommendation to waive the liquidated damages assessed at $2860.00. The refusal to waive the assessment of the liquidated damages was based on a finding by the Wage and Hour Division of the Department of Labor that the amount of the liquidated damages was correctly computed and that the firm did not meet the statutory standards for waiver contained in 40 U.S.C. 330. On October 14, 1980, petitioner was awarded a contract by EPA to construct a sewer project in Moscow, Idaho. This contract was subject to the requirement that time and one-half would be paid for all hours worked in excess of eight hours per day and forty hours per week as required by the Contract Work Hours [1] ~2 [2] and Safety Standards Act (CWHSSA). An investigation of the project by the Wage and Hour Division revealed that Harry Johnson Plumbing had failed to pay its employees all of the overtime compensation required by CWHSSA and had falsified its certified payrolls to EPA to make it appear that it was in compliance. At a conference following this investigation Wage and Hour determined that $3,596.67 was due in overtime back wages to 11 of the firm's employees. Petitioner paid all of the back wages due to its employees and promised to comply with CWHSSA in the future. Wage and Hour has now determined that $2860 are due from petitioner for liquidated damages pursuant to 40 U.S.C. 328. The liquidated damages assessed may be reduced or waived according to 40 U.S.C. 330 if certain conditions contained therein are met. On January 4, 1983 EPA recommended that the liquidated dam[a]ges be waived. On July 25, 1983 the Wage and Hour Division disagreed with this recommendation, finding that the violations were not inadvertent and that petitioner had not exercised due care. Primarily, Wage and Hour placed reliance on petitioner's submission of the falsified certified payrolls as support for this finding. On two occasions in August and October, 1983, EPA requested petitioner to forward the $2860 in liquidated damages to the [2] ~3 [3] government. Instead of paying the damages, on November 14, 1984 petitioner requested the Wage Appeals Board to review Wage and Hour's denial of the waiver of the liquidated damages. The Board considered this appeal on the basis of the Petition for Review and a subsequent response to the government's statement filed by the petitioner, a record of the case before the Wage and Hour Division and the Statement for the Wage and Hour Division filed by the Solicitor of Labor. No request for an oral hearing was received by this Board. * * * The sole question before this Board is whether a waiver or adjustment should be granted of the liquidated damages which were assessed as a result of violations by the petitioner of the Contract Work Hours and Safety Standards Act, 40 U.S.C. 327 et seq. The Contract Work Hours and Safety Standards Act under which the liquidated damages were assessed provides in pertinent part: . . ., if it is found . . . that the contractor or subcontractor violated the provisions of this Act [*] inadvertently notwithstanding the exercise of due care on his part and that of his agents [*], recommendations may be made to the Secretary that an [*] appropriate adjustment in liquidated damages be made [*], or that the contractor or subcontractor [*] be relieved of liability for such liquidated damages [*]. The Secretary shall review all pertinent facts in the matter and may conduct such investigations as he deems necessary, so as to affirm or reject the recommendation. 40 U.S.C. at [sec] 330(c). [*] (Emphasis added.) [*] There is no question that the petitioner violated the overtime provisions of the aforementioned statute. The record shows [3] ~4 [4] that Harry Johnson Plumbing failed to pay its employees the required overtime for hours worked in excess of forty hours per week and eight hours per day for most of the contract period. During certain weeks, the petitioner reported on its certified payrolls that no more than forty hours per week and eight hours per day were worked. This concealment in itself shows that the violations were not "inadvertent" and that petitioner did not exercise "due care". In a recent decision the Board indicated that where there is a submission of falsified payrolls the assessment of liquidated damages should not be waived: See Major Associates, Inc., WAB Case No. 84-14 (May 20, 1985). Also, in Major Associates the Board held that where the violations were not flagrant and there were no known previous violations, the full assessment of liquidated damages is not necessarily mandated. Here, the Board is faced with a similar case. The overtime violations certainly do not appear to be of a flagrant nature. This, coupled with the fact that the operating officer is new in the business and has performed no previous government contracts, leads the Board to believe that the violations in this case do not warrant the full assessment of liquidated damages. [4] ~5 [5] In view of the foregoing, it is the decision and order of this Board that the liquidated damages be adjusted to $715.00. BY ORDER OF THE BOARD Craig Bulger, Executive Secretary Wage Appeals Board [5]



Phone Numbers