skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

RITE LANDSCAPE CONSTRUCTION CO., INC., WAB No. 83-03 (WAB Oct. 18, 1983)


CCASE: RITE LANDSCAPE CONSTRUCTION CO DDATE: 19831018 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of RITE LANDSCAPE CONSTRUCTION CO., INC. WAB Case No. 83-03 Army Contract No. DADA-03-80-C-0088 Fitzsimmons Army Medical Center, CO Dated: October 18, 1983 BEFORE: Alvin Bramow, Chairman, Thomas X. Dunn, Member Stuart Rothman, Member, Dissenting DECISION OF THE WAGE APPEALS BOARD This case is before the Wage Appeals Board on the petition of Rite Landscape Construction Co. seeking review of the ruling of the Assistant Administrator, Wage and Hour Division, dated September 21, 1982. This ruling concerns the appropriate wage rate applicable to the classification of lawn sprinkler installer, and the denial of an additional classification landscape laborers on an Army contract awarded to petitioner in Colorado. In the fall of 1980, Rite Landscape Construction Co., (hereinafter Rite) was awarded a contract for landscaping the grounds around several buildings at Fitzsimmons Army Medical Center in Adams County, Colorado. The contract was subject to the Department of Labor's general wage determination No. CO 79-5117, the Davis-Bacon Act and applicable regulations. [1] ~2 [2] In February 1981, Rite requested that two additional classifications for landscape laborers and lawn sprinkler installers be added to the general wage determination at a wage rate of $4.50 per hour for each classification. The Wage and Hour Division ruled that an additional classification for landscape laborers was unnecessary because the wage determination already contained a laborer classification. After further negotiation between Rite and Wage and Hour, Wage and Hour approved the addition of a lawn sprinkler installer at a wage rate of $8.29 per hour plus f[r]inge benefits. This rate was equal to the Laborers, Group 2, rate issued in the applicable wage determination. During the performance of the contract Rite did not pay the employees in question the wage rate specified by the Wage and Hour Division, resulting in the Army withholding $17,000 from payments to the company. Rite requested reconsideration by the Assistant Administrator of her ruling in this case and submitted data to Wage and Hour in support of its contention that a landscape laborer's rate of $4.50 should be issued and that the lawn sprinkler installer's rate should be changed to $4.50 per hour also. Wage and Hour did not change its ruling and on January 21, 1983, Rite petitioned the Board to review the Assistant Administrator's ruling. The petitioner's argument before the Board is that Wage and [2] ~3 [3] Hour never issued wage rates for either of the classifications it is requesting to be added to wage determination CO 79-5117, the determination applied to the project in question. Petitioner relies on wage data and surveys submitted to the Wage and Hour Division after the project was completed which tended to support petitioner's request for the rates at the $4.50 level. This wage data was obtained by petitioner from the Association of Landscape Contractors of Colorado, the Colorado Division of Employment and Training and the Career Service of the City and County of Denver, which is adjacent to Adams County where the Fitzsimmons Army Medical Center is located. Petitioner argues that all this wage information is substantial and credible since it was produced by independent private or governmental units simply to establish the amount of the wages being paid in the area. It is also petitioner's position that there is nothing whatsoever in the record to support the wage rates required to be paid by the Wage and Hour Division for landscape laborers and lawn sprinkler installers. Petitioner further complains that it protested the wage rates and requested additional classifications almost from the initiation of the contract but was permitted to complete the contract before it was advised that the rates that it paid were not acceptable. Petitioner argues that on this basis alone, the government should be estopped from asserting any higher wage rate. [3] ~4 [4] The Assistant Administrator argues that the regulations applicable to the establishment of additional classifications, 29 CFR 5.5(a)(1)(ii), require that new classifications be conformable to the other wage rates issued for the project. The rate approved by Wage and Hour was equivalent to that issued for Laborers, Group 2, the least skilled construction classification in the wage determination. It is therefore argued that the rate of $8.29 for lawn sprinkler installers is conformable to other rates in the decision and to allow the establishment of a rate of $4.50, as urged by petitioner, would be unfair to any other bidders who competed for the contract. The Wage and Hour Division also notes that the wage data which Rite submitted after receiving award of the contract should have been submitted prior to the receipt of bids in order to be timely and to be fair to all bidders. Finally, the Wage and Hour Division defends its denial of an additional classification of landscape laborer on the basis that the classification Laborers, Group 2, Building Construction Laborer, was sufficiently broad to include the duties of landscape laborer. It is suggested that even if the additional classification were permitted it presumably would be issued at a wage rate of $8.29, the same as the lawn sprinkler installer and for the same reasons. The appeal was considered by the Board on the basis of the Petition for Review and a Reply brief filed by petitioner, [4] ~5 [5] a Statement on behalf of the Assistant Administrator and a record of the appeal before the Wage and Hour Division filed by the Solicitor of Labor. No request for an oral argument was made to the Board. * * * It appears to the Board that the petitioner's contention that the wage rates for the job classifications of landscape laborers and lawn sprinkler installers should be $4.50 per hour is actually a challenge to the wage rate determination itself. The evidence submitted by the petitioner during this additional classification procedure certainly leaves some doubt as to whether the proper schedule of wage rates was included in the bid specifications and contract documents. It might be that this type of work when no building construction is involved is not performed by craftsmen receiving building trades' rates. However, as the Board held in one of its most recent decisions, Jordan & Nobles Construction Co. & W R. Pierce & Associates. WAB Case No. 81-18 (August 19, 1983): *** that there is one time when a contractor in the industry, whether the successful bidder or not, a sponsor or anyone else in the industry can challenge the accuracy of a Davis-Bacon wage determination. That time is prior to the award of bids. The Board has addressed the question of parties challenging wage determinations since its first decision in 1964. [5] ~6 [6] See Huntsville-Madison County Airport, WAB Case No. 64-01 (August 31, 1964), Fry Brothers Corp., WAB Case No. 76-06 (June 14, 1977), Holloway Sand and Gravel Trucking, Inc., WAB Case No. 79-13 (January 16, 1980), Southern Capital Corp., WAB Case No. 78-12 (January 16, 1979). The Board further realizes that petitioner attempted to clarify the problem at a very early stage. Still petitioner proceeded with the construction work. In Espana Gardens, WAB Case No. 76-15 (May 4, 1977) the Board ruled: It is apparent here that the petitioner is still trying to raise the question of what was the prevailing rate for the craft in question before the project started. Petitioner had at the time the question first arose in 1972 the options of appearing before the Wage Appeals Board to protest the prevailing wage rates in contention prior to the start of construction or initial endorsement of the mortgage, as provided in Regulations, Part 1, Section 1.7(b) (29 CFR); or he could have chosen not to proceed with the construction of the project until such time as the question of the wages was finally settled. Following neither of these options he chose to proceed with construction. He cannot be allowed to question the wage rates in the wage determination provided to him. The time to have come to the contracting agency and/or the Wage and Hour Division to show that the classifications and wage rates furnished for this project (landscaping only) were not realistic and in fact not those prevailing was prior to bid opening and contract award. To do so after bid opening and contract award was untimely. /FN1/ [6] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN1/ 29 CFR Part 1 was revised and published on April 28, 1983 (48 F.R. 19532) to take effect on June 28, 1983. The new regulation provides at section 1.7(f) that [FN1 CONTINUED ON PAGE 7] : [Continued]: The Administrator may issue a wage determination after contract award or after the beginning of construction if the agency has failed to incorporate a wage determination in a contract required to contain prevailing wage rates determined in accordance with the [Davis-]Bacon Act, or has used a wage determination which by its terms or the provisions of this part clearly does not apply to the contract. Further, the Administrator may issue a wage determination which shall be applicable to a contract after contract award or after the beginning of construction when it is found that the wrong wage determination has been incorporated in the contract because of an inaccurate description of the project or its location in the agency's request for the wage determination. Under any of the above circumstances, the agency shall either terminate and resolicit the contract with the valid wage determination, or incorporate the valid wage determination retroactive the beginning of construction through supplemental agreement or through change order, Provided that the contractor is compensated for any increases in wages resulting from such change. The method of of the valid wage determination, and adjustment in contract price, where appropriate, should be in accordance with applicable procurement law. Therefore, the ruling herein and in those Wage Appeals Board cases cited above may not be controlling under certain factual situations for contracts awarded after the effective date of this regulation. [END FN1] [7] ~7 [7] The remaining question before the Board is whether the Assistant Administrator's action in ruling that the appropriate wage rate for lawn sprinkler installers is $8.29 per hour and denying the additional classification of landscape laborer was proper. [7] ~8 [8] The petitioner contends that the Assistant Administrator must have some basis in fact (evidence) showing the rate actually prevailing for lawn sprinkler installers and that the classification of building laborers actually perform landscape work. This contention has no merit in the situation at hand. As the Board stated above, the prevailing rate argument is untimely. Also, this is not a question of area practice as to what classification in an existing wage determination performs the work. The petitioner has requested two new classifications to be employed on the project. Once a contract has been awarded, there is only one method by which a contracting agency or Wage and Hour can provide additional classifications which have not been listed in the wage determination made applicable to the contract and which the contractor needs to perform the contract. That method is provided for in the Department of Labor's Regulations at 29 CFR 5.5(a)(1)(ii) which read as follows: The contracting officer shall require that any class of laborers or mechanics, including apprentices and trainees, which is not listed in the wage determination and which is to be employed under the contract, shall be classified or reclassified [*] conformably [*] to the wage determination and a report of the action taken shall be sent by the Federal agency to the Secretary of Labor. In the event the interested parties cannot agree on the proper classification or reclassification of a particular class of laborers and mechanics, including apprentices and trainees, to be used, the question accompanied by the recommendation of the contracting officer shall be referred to the Secretary for final determination. [*] (Emphasis added). [*] [8] ~9 [9] To give any meaning to the words "shall be classified or reclassified [*] conformably [*] to the wage determination" in 29 CFR 5.5(a)(1)(ii), the proposed wage rates must bear some reasonable relationship to the wage rates contained in the wage determination. [[*] [EMPHASIS IN ORIGINAL] [*] This does not mean that the rate must be an identical rate to one in the wage determination. In fact, it could even be lower than any rate in the wage determination. But certainly it must be within close proximity to those contained in the contract specifications. Here, the rate of $4.50 per hour as requested by petitioner does not meet the criterion of "reasonable relationship" to the other wage rates contained in the contract. With respect to the landscape laborer's classification, the Board is not entirely convinced that a laborer performing landscape work can be fitted into the duties of a building construction laborer. However, the Board finds it unnecessary to determine whether the Assistant Administrator correctly denied the additional classification as the wage rate from the facts in the record would not differ by using the method described in 29 CFR 5.5(a)(1)(ii). In view of these considerations the Wage Appeals Board affirms the ruling of the Assistant Administrator and dismisses the petition. * * * [9] ~10 [10] Member Rothman, dissenting: I dissent. I would remand the case to the Wage and Hour Administrator with the following instructions: 1. The Wage and Hour Division should undertake a locality factual investigation. The purpose of the survey would be to determine whether in that part of Colorado the structure of the construction industry is such that the work in question is considered by the industry under accepted usage and practice to be building, heavy or highway work. The work to which I am referring is landscape work awarded independently of any building construction, which is the case here. In short, the preparation of lawns and underground water sprinkling systems awarded separately such as for general landscaping or the preparation and care of golf courses, parks or public areas must be factually established to be within the three classifications for which wage rates were predetermined -- building, heavy or highway. There are locality situations where there are classifications of construction work not performed under any of these schedules as a matter of local usage and custom. Examples include local paving and local public utility contracts performed independently of building or other commercial construction. 2. If such a survey establishes that this kind of work has not normally been considered to be within building construction [10] ~11 [11] work and is not normally considered covered by the prevailing negotiated wage rates which were applied by the administering agency to this work, the Wage and Hour Administrator erred. 3. If the survey discloses that the work in question has been normally and customarily considered outside of any of the foregoing three categories, the Administrator's survey should determine what was the appropriate wage rate for the two disputed classifications. This is the rate to which the employer should be held in this case. I reach the foregoing conclusions for the following reasons: 1. There are procedures for rectifying an error of this kind (if, in fact, an error has been made). These procedures are within the provisions and limitations of the then applicable Secretary's rules and regulations. Within these applicable rules it is the purpose of this Board to work out anomalies created by numerous governmental agencies with different degrees of experience in the administration of the Act. That is one of the reasons Congress in 1950 promulgated Reorganization Plan No. 14. 2. The petitioner has made a very strong prima facie case that landscape work is not normally performed by the [11] ~12 [12] same crafts or by the same laborers and mechanics who work on or around building construction as part of such construction. 3. The petitioner brought this problem to the administering agency before work commenced. This would not save it if there had simply been an error or other inadvertence in an appropriately applicable wage within the building rate schedule. In this case, however, if the work in question was not the appropriate subject matter of any of the three published rates, then it is the same (at least for the resolution of this case), as though there was not a properly published wage predetermination in the bid documents at all. 4. This case is distinguishable from the recently decided case of Jordan & Nobles and W.R. Pierce, WAB Case No. 81-18, August 19, 1983. In that case, the petitioning contractors paid pipefitters on building construction at the laborers' rate. It was simply a question of misclassification. The petitioners in Jordan & Nobles did not contend that the work in question was not building construction but that the Wage and Hour Administrator had not followed its own regulations in arriving at the appropriately specified wage predetermination for pipefitters on building construction. For the foregoing reasons, I dissent from the decision [12] ~13 [13] reached by the majority and would remand the case to the Administrator with the foregoing instructions. BY ORDER OF THE BOARD Craig Bulger, Executive Secretary Wage Appeals Board [13]



Phone Numbers