HARLOW RESTORATION CORP., WAB No. 81-14 (WAB May 11, 1983)


CCASE: HARLOW RESTORATION DDATE: 19830511 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of HARLOW RESTORATION CORP. WAB Case No. 81-14 Boston, Massachusetts Dated: May 11, 1983 DECISION OF THE WAGE APPEALS BOARD DECISION BY: Stuart Rothman, Member, Thomas X. Dunn, Member Gresham C. Smith, Alternate Member /FN1/ This case is before the Wage Appeals Board on the petition of Harlow Restoration Corp. (hereinafter Harlow) seeking review of the decision of the Assistant Administrator, Wage and Hour Division, dated July 29, 1981, holding Harlow liable for $23,721,11 in back wages for overtime violations of the Contract Work Hours and Safety Standards Act, (CWHSSA) 40 U.S.C. [sec] 327 et seq. Petitioner was awarded two contracts by the General Services Administration (GSA) for masonry repairs to the U.S. Customs House and the McCormack Post Office in Boston, Massachusetts. Both contracts were subject to the labor standards provisions of the Davis-Bacon Act and the overtime provisions of CWHSSA. During the entire construction at the Customs House and through a substantial part of the construction work at the Post Office, petitioner, apparently with the acquiescence of its masonry employees and with the knowledge of GSA, worked /FN1/ ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN1/ Board Chairman Alvin Bramow withdrew from consideration of this appeal and did not participate in the decision of the case.[1] ~2 [2] its crews for four 10-hour days per week, while paying only straight time wages for any hours worked in excess of 8 hours per day. When GSA advised petitioner that its method of payment might be contrary to the CWHSSA requirements, petitioner ceased the practice and indicated that proper restitution would be made. GSA brought the question to the Department of Labor and was advised that Harlow had an overtime wage liability for any hours worked in excess of 8 hours per day. The Wage and Hour investigation of the projects disclosed that the employees worked either 9 or 10-hour days for 4 days per week on the projects and that the certified payrolls submitted to GSA showed that the employees were working S 8-hour days on the construction until the violations were brought to petitioner's attention. The Assistant Administrator of the Wage and Hour Division issued a ruling on July 29, 1981 that Harlow was liable under the two contracts for $23,721.11 in back wages under CWHSSA. Petitioner appealed this ruling to the Board on September 25, 1981. In its petition Harlow does not deny that its employees worked 4 10-hour days at straight time on the two contracts in question. It presents several arguments, however, which it contends should mitigate its liability under CWHSSA. It is argued that Harlow's main concern in working its crews for 4 10-hour days was their safety since they operated from swing [2] ~3 [3] stages which were subject to high wind off of Boston's harbor. Harlow points out that their decision to work this arrangement of hours was agreed to be the business manager of the Bricklayers' local union. Furthermore, Harlow points to the fact that GSA was fully aware of the arrangement and that they did not object to the fact that the employees were not paid overtime, since the employees had agreed to it. Also, GSA did not notify Harlow that the compensa- tion for the rearranged working hours was contrary to CWHSSA provisions until one of the contracts was completed, and the other was approximately half completed and it was too late for Harlow to reduce its liability or rectify its mistake. Petitioner argues that GSA is as responsible for its liability as petitioner. Harlow finally requests the Board to declare that Harlow did not commit the overtime violations alleged, or, alternatively, Harlow calls the Board's attention to 29 CFR Part 5, [sec] 5.14 which permits the Secretary of Labor to grant variations, tolerances or exemptions to provisions of CWHSSA when he finds circumstances warrant such relief. The Wage and Hour Division relies on the fact that petitioner is obligated under CWHSSA to pay overtime wage rates for all hours worked in excess of eight hours per day. Furthermore, it is pointed out that CWHSSA also specifies that a contractor may neither require nor permit any laborer or mechanic to exceed the eight hour standard per day or forty hour standard [3] ~4 [4] per workweek at the straight time rate of pay. Wage and Hour also asserts that no mitigating circumstances can relieve Harlow of its obligation to pay overtime for all hours worked over eight hours per day. The fact that Harlow submitted certified payrolls to GSA which showed that its employees were working 5 8-hour days instead of 4 10-hour days indicates to Wage and Hour that petitioner was aware what its contractu[]al obligations were under the Act. The Assistant Administrator relies on U.S. ex rel. Johnson v. Morley Construction Co., 17 F.Supp. 378, 391 [----], to the effect that the employee cannot waive or bargain away the payment of wages and rights secured to him by law. In this case the court held that the right of employees on public works to receive required wages was enforceable even in the face of employees' waivers purporting to release the contractor from statutory wage liab[]ility. It is Wage and Hour's position that Harlow's request for a variation, tolerance or exemption from the 8-hour day provision of the Act is not properly before the Board because petitioner did not assert this defense below, and since an appeal to the Board can lie only from a final agency action, the Board lacks jurisdiction over the question at this time. The Wage Appeals Board considered this appeal on the basis of the Petition for Review and two subsequent responses filed by Harlow, the Statement on behalf of the Assistant Administrator [4] ~5 [5] and a response, and the record of the case in the Wage and Hour Division filed by the Solicitor of Labor. No request for oral argument was made. * * * Upon a review of the arguments presented to it in this appeal the Board cannot accept petitioner's position that it would be safer for its laborers and mechanics to work 4 10-hour days than 5 8-hour days. Petitioner has not sustained its position in this regard. Furthermore, in view of the language in CWHSSA, [sec] 102(b)(1): No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or [*] permit [*] any laborer or mechanic, in any workweek in which he is employed on such work, to work in excess of eight hours in any calendar day . . . except in accordance with the provisions of this Act. [40 U.S.C. [sec] 329(b)(1), [*] Emphasis added. [*]][,] it appears to the Board that the prohibition of requiring or permitting employees to work in excess of 8 hours per day at a straight time rate of pay is obligatory and since petitioner did not pay time and one/half for the excess hours per day, that neither the fact that a union official agreed to the arrangement on behalf of petitioner's employees or that the contracting officer of GSA may have been aware of petitioner's practices and permitted them to proceed until one project was completed and the other project was half completed can excuse petitioner for the breach of this statutory [5] ~6 [6] provision. It is Harlow Restoration Corporation, after all, who made the contract with the contracting agency, and the provision is very clear that Harlow was engaging in prohibited conduct and violating its employees' rights. Although the Board does not believe it would make any difference if petitioner had permitted this employment arrangement through ignorance of its obligations under CWHSSA, the fact that the certified payrolls submitted to GSA were falsified to show that the employees were working 5 8-hour days, when they were not, indicates that petitioner knew what its obligations were under the Act. For the foregoing reasons the Board does not agree that any of these circumstances mitigates or lessens petitioner's obligation to pay its employees time and one/half for any hours worked in excess of 8 hours per day. In addition, the Board cannot respond to petitioner's request that a variation, tolerance or exemption be granted pursuant to [sec] 105 of CWHSSA since this request was not made previously to the Administrator and has not been the subject of a final agency action. The Board cannot have jurisdiction over the matter at this time. Therefore, the decision of the Assistant Administrator is hereby affirmed. Petitioner's employees are entitled to time and one/half for all hours worked in excess of eight ~7 hours per day on both the U.S. Customs House and the McCormack Post Office projects in Boston, Massachusetts. The petition of Harlow Restoration Corporation is hereby denied. BY ORDER OF THE BOARD Craig Bulger, Executive Secretary



Phone Numbers