skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

CTL ENGINEERING, WAB No. 80-07 (WAB July 22, 1983)


CCASE: CTL ENGINEERING DDATE: 19830722 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of CTL ENGINEERING WAB Case No. 80-07 Construction of Relief Well System Clendening Dam Dated: July 22, 1983 Stillwater Creek, Ohio APPEARANCES: William L. Farrar, Jr., Esquire For CTL Engineering Jill A. Griffin, Esquire, Douglas J. Davidson, Esquire for the Wage and Hour Division, U.S. Department of Labor BEFORE: Stuart Rothman, Acting Chairman, Thomas X. Dunn, Member Gresham C. Smith, Alternate Member /FN1/ DECISION OF THE WAGE APPEALS BOARD This case is before the Wage Appeals Board on the petition of CTL Engineering (hereinafter CTL) which seeks review ruling by the Assistant Administrator, dated February 8, 1980. This ruling held that employees engaged in drilling pilot holes for subsequent construction of a relief well system at the Clendening Dam on Stillwater Creek in Ohio were subject to the labor standards provisions of the Davis-Bacon Act and the Contract Work Hours and Safety Standards Act (CWHSSA). [1] ÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄÄ /FN1/ Board Chairman Alvin Bramow withdrew from consideration of this appeal prior to the hearing and did not participate in the decision. [1] ~2 [2] The relief well system was required because water pressure behind the earth-filled Clendening Dam was forcing seepage through the dam's foundations and undermining the dam. The relief well system proposed by the Army Corps of Engineers would consist of twelve holes two feet in diameter and approximately 100 feet deep. The holes would be lined with filters to prevent sand and sediment from being forced out with the seepage. The water rising in these holes (or wells) would ultimately be piped safely downstream away from the dam thereby preserving the foundations. The contract for the relief well system was awarded to the prime contractor, Needles and Associates, Inc., by the Corps of Engineers. Although the specifications indicated the total number of wells, depth of wells, spacing between the wells and well hardware, the contract called for the drilling of a pilot hole at each well location to further develop and refine the design. CTL received the subcontract to drill the pilot holes, collect core samples, analyse the soil and the submission of data. The labor standards provis[i]ons of the Davis-Bacon Act and CWHSSA and the appropriate wage determinations were included in the prime contract and CTL's subcontract. Certified payrolls submitted by CTL to the Corps of Engineers indicated the wages paid to C[TL]'s employees were lower than the [2] ~3 [3] wage rates specified in the wage determination. The Corps of Engineers withheld the sum of $2680.25 to cover back wages due under the Davis-Bacon Act and the underpayments and liquidated damages due under CWHSSA. CTL objected to the Corps of Engineer's assessment of back wages and liquidated damages due and requested a ruling from the Secretary of Labor. On February 8, 1980 the Assistant Administrator, Wage and Hour Division, affirmed the contracting officer's assessment, stating that the pilot holes were "... directly related and incidental to, and an integral part of the actual construction of a public work ..." CTL appealed the ruling to the Wage Appeals Board on April 28, 1980. CTL contends that the purpose of the pilot holes is to obtain soil data in order to design screens and other items to be used in the relief wells. CTL relies on an Opinion Letter dated June 25, 1963 from Charles Donahue, Solicitor of Labor, to Harold Blasky, Deputy General Counsel, Office of the Chief of Engineers, which distinguishes various examples of exploratory drilling situations, some of which have been determined to be covered by the labor standards provisions of the Davis-Bacon Act, and some of which are not. CTL claims their activities are akin to the drilling example in the Solicitor's letter where the drilling is for formulation of engineering plans and specifications, designs and the [3] ~4 [4] conduct of site investigations. Petitioner claims that the pilot holes are merely preliminary work for the general contract to provide engineering data for the final design of the system. Petitioner states that the timing of the drilling, i.e.: whether before the prime contract is let, or after, should not turn work that is not subject to the Davis-Bacon Act and CWHSSA into covered work. It is petitioner's position that the drilling of cores is not a covered activity whenever it is done. The Wage and Hour Division argues that the relief well system is a public work within the meaning of the Davis- Bacon Act and that the pilot holes are an essential, integral part of the system. Wage and Hour states that the precise location of the relief wells had been determined in advance of the pilot hole drilling and that the core drilling samples were used to determine the hardware to be ordered for the wells. The drilling of the pilot holes is therefore an activity covered by the Act. Counsel for Wage and Hour attempts to distinguish the example in the Solicitor of Labor's Opinion Letter. It is argued that CTL's activities are more similar to other examples listed by the Solicitor which were ruled as covered activities in the Opinion Letter. Wage and Hour also asserts that the pilot holes were not drilled prior to the development of plans for the relief well system. Wage and Hour concedes that if this had been the case, there could be validity to petitioner's argument against coverage. [4] ~5 [5] Here, however, according to Wage and Hour, the plans were fully developed (except for certain hardware) prior to the award of the prime contract. Wage and Hour's position is that the situation is totally different from a situation where exploratory drilling is performed to determine the proper location of construction and must be undertaken before the actual plans can be drawn. The Wage Appeals Board considered this appeal on the basis of the petition for review filed on behalf of CTL, a statement for the Assistant Administrator, the record of the case on file in the Wage and Hour Division and a statement on behalf of the Building and Construction Trades' Department. A hearing was held before the Board on May 18, 1983 at which the parties were present and participated. At the hearing it was made clear to the Board that petitioner considered the drilling of the pilot holes to be preliminary work necessary for the development of the plans for the project. Counsel for petitioner reduced his argument to the clear cut position that if the drilling of pilot holes was considered to be preliminary to the construction of the relief wells then it should not be subject to the labor standards provisions of the Davis Bacon Act or CWHSSA, but that if the drilling of the pilot holes was not judged to be preliminary to the construction of the relief wells, then it should be looked upon as covered work. [5] ~6 [6] The problem in this case is not the way CTL Engineering staffed the work according to its normal operations, but in the way the Corps of Engineers awarded the work. It appears to the Board that it was within the power of the Corps of Engineers, had it elected to do so, to separately award a contract for borings to be completed before the prime contract was awarded. If that could have been done and had been done, a different and stronger case could be made that the disputed work was of a character similar to exploratory and test borings not classified as construction. In this case there appear to have been emergent conditions which inclined the Corps of Engineers to move the prime contract ahead of test borings which necessarily became auxiliary to the main work. The two progressed together so that the subcontract lost the characteristic of being a study of site conditions upon which plans could be based. CTL performed its work along side the prime contractor's construction of the relief wells, each within a few feet of the other. The pilot holes were in a subcontract and the results would be given to the prime contractor to report to the Corps of Engineers under the prime contractor's responsibility to get appropriate further direction. These circumstances make the disputed work an essential, integral part of the work covered by the basic award. The subcontract contained the appropriate Davis-Bacon Act and CWHSSA labor standards provisions without qualification. [6] ~7 [7] The facts disclosed that the employers in the area who perform the kind of boring work that CTL performs use employees who may not work at the prevailing on-site building and construction trades' rates. Any such aspect of the case cannot be raised here because if it were to be raised at all, it should have been raised prior to the time of the award. The Corps of Engineers, through careful scheduling of their contracts, can undoubtedly avoid the problem which arose in this case. CTL, if it does not wish to be subject to the Davis-Bacon labor standards provisions in the future, can likewise avoid the problem which arose at Clendening Dam by refusing to bid on contracts for test borings where the boring is performed as an integral and essential part of the construction contract. But as far as this case is concerned, it cannot be distinguished from normal work at a construction site. The work in question should have been performed at the appropriate Davis-Bacon prevailing rates. In view of these considerations the decision of the Assistant Administrator is affirmed and the petition herein is dismissed. BY ORDER OF THE BOARD Craig Bulger, Executive Secretary Wage Appeals Board



Phone Numbers