skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

ALMEDA-SIMS SLUDGE DISPOSAL, WAB No. 78-13 (WAB Apr. 30, 1979)


CCASE: ALMEDA-SIMS SLUDGE DISPOSAL DDATE: 19790430 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D. C. In the Matter of ALMEDA-SIMS SLUDGE DISPOSAL WAB Case No. 78-13 Plant, Harris County, TX [Dated: April 30, 1979] NOTICE OF CLARIFICATION The Wage Appeals Board has received a Motion for Reconsideration or, in the alternative, for clarification from the Houston-Gulf Coast Building and Construction Trades Council and the Building and Construction Trades Department, AFL-CIO, (hereinafter Intervenors). The City of Houston has filed a Memorandum in Opposition to the Intervenor's Motion. The Intervenors claim that the Board's direction that wage rates incorporated in the contract for Almeda-Sims Sludge Disposal Plant project need not be changed to reflect the Assistant Administrator's characterization of the project as building construction, despite the fact that the Board found that the Environmental Protection Agency (EPA) erred in substituting its judgment for that of the Assistant Administrator, is contrary to the principles of the Davis-Bacon Act. Also, Intervenors [1] ~2 [2] state that the Board lacks the authority to direct that wage rates incorporated in federally-funded contracts be altered in any way. In its Motion Intervenors assume that delays occurring between the time when the wage rates were first questioned and the ultimate decision by the Board were relied on by the Board as a basis for not changing the wage rates. Intervenor argues that the various delays were caused by the Department of Labor and particularly by EPA and that this should not work to the detriment of the employees working on the project. The Board does not agree with the Intervenors' assumption. Even if the Board had the authority to change the rates in the contract after award it was testimony at the hearing which tended to create questions as to which of the two schedules, building or heavy, was properly applicable to the Almeda-Sims Sludge Disposal plant, not the lapse of time, that moved the Board to state that it would not direct that the wage rates be changed. In its statement that the construction contract had been awarded for some time and therefore the Board would not direct that the wage rates be changed, the significant language is that the contract has been [*] awarded [*] [Emphasis in original]. The Board agrees with the Intervenors' contention that the Board cannot direct that the wage rates included in a contract be changed after contract award. [2] ~3 [3] The Board has relied on this proposition in two recent Wage Appeals Board decisions: Mobile Bay Bridge (WAB 77-22, October 21, 1977) where the Board ordered the Wage and Hour Division to provide the petitioner with a corrected wage decision for possible use in renegotiation of the contract, but where the Board expressly stated that it was without authority to take any action with respect to the contract in question, and that it could not order that a corrected wage determination be substituted for the one already in the contract. (Notice of Clarification, March 6, 1978), and Installation of Conveyor System, WAB 78-24 (April 6, 1979). The Board does not find the present decision to be inconsistent with cases cited above. In view of these considerations, the Intervenors' Motion for Reconsideration [is] hereby dismissed. BY ORDER OF THE BOARD Craig Bulger, Executive Secretary Wage Appeals Board [3]



Phone Numbers