skip navigational linksDOL Seal - Link to DOL Home Page
Images of lawyers, judges, courthouse, gavel
September 23, 2008         DOL Home > OALJ Home > USDOL/OALJ Reporter
USDOL/OALJ Reporter

GREAT LAKES CONSTRUCTION CORP., WAB No. 78-08 (WAB Jan. 16, 1980)


CCASE: GREAT LAKES CONSTRUCTION DDATE: 19800116 TTEXT: ~1 [1] WAGE APPEALS BOARD UNITED STATES DEPARTMENT OF LABOR WASHINGTON, D.C. In the Matter of GREAT LAKES CONSTRUCTION CORP. WAB Case No. 78-08 Wage Rates for HUD Proj. No. WI-39-H200-028 Dated: January 16, 1980 La Crosse County, Wisconsin DECISION BY: Alfred L. Ganna, Chairman, William T. Evans, Member, Thomas M. Phelan, Member DECISION OF THE WAGE APPEALS BOARD This case is before the Wage Appeals Board on the petition of Great Lakes Construction Corp. to review the decision of the Acting Assistant Administrator holding that the wage rates contained in wage decision No. AR-3160 and included in Petitioner's contract for construction of a LaCrosse County housing project are those which must be paid to laborers and mechanics that were employed on the project. In September, 1976 Petitioner bid on the subject DHUD housing project on the basis of a Project Manual provided by DHUD. This manual contained the bid specifications for the housing project including the Federal wage determination noted above, dated October 11, 1974, a modification to the same wage determination dated April 25, 1975, and a State of Wisconsin prevailing wage determination dated June 10, 1976. The State rates were [1] ~2 [2] different from and lower than the Federal wage rates and it is because of this that Petitioner secured the negotiated union wage rates for residential construction in LaCrosse County to use as the basis for its bid on the project. On November 1, 1976 the contract was awarded to Petitioner and a preconstruction conference was held. Construction began the next day. In May, 1977 the LaCrosse County Housing Authority was informed that the Petitioner was paying its laborers and mech[an]ics less than the predetermined prevailing wage rates contained in the Federal wage determination applicable to the project (AR-3160). By the time the project was completed a DHUD audit of Petitioner's certified payrolls indicated the Petitioner had underpaid its laborers and mechanics by $21,706.83, and that subcontractors were similarly in arrears in the amount of $2,101.36, for a total of $23,808.19. In April, 1978 Petitioner requested reconsideration by the Wage and Hour Division of the assessment of the underpayment by DHUD. And in June, 1978 the Acting Assistant Administrator, Wage and Hour Division, sent a letter to Petitioner concurring in DHUD's decision that the wage rates contained in wage determination No. AR-3160 were applicable to the project and that any protest of such [2] ~3 [3] rates should have been filed prior to starting construction. Petitioner then sought review by the Wage Appeals Board of the Acting Assistant Administrator's decision. It is Petitioner's position before the Board that it is unfair to compel Petitioner to pay the assessed underpayment. Petitioner claims the Project Manual contained a patent ambiguity in that the Federal wage determinations were partially cancelled by cross-marks being drawn over portions of the determinations. The lower State of Wisconsin wage rates which applied specifically to the project were more currently dated than the Federal rates and were placed immediately beneath the Federal rates and were also included in the final signed contract which, it is claimed, resulted in Petitioner's confusion. Petitioner defends as reasonable and in good faith its turning to the negotiated union schedules for residential construction on which it based its bid and subsequently paid its employees. Petitioner also relies on its inexperience to justify it paying its employees in the way that it did. It claims that to require it to pay the employees the underpayment would result in undue hardship on Petitioner and unjustly enrich its employees. Finally, Petitioner argues that the mistake of fact was not the basis for awarding the contract since its bid would still have been $60,000 lower than the next lowest bid, and therefore [3] ~4 [4] the contract should be reformed by changing the wage rates to those in the negotiated agreements that it used to prepare its bids. The Wage and Hour Division argues that if the Project Manual contains the patent ambiguity Petitioner claims it did, then Petitioner had an obligation to seek clarification of the ambiguity from HUD upon receipt of the wage determination or at the preconstruction conference. Wage and Hour does not consider that the Project Manual contains an ambiguity and cites various sections of the Supplementary General Conditions of the Contract which, it is claimed, would have explained or resolved any questions Petitioner may have had. Finally, the Solicitor argues on behalf of Wage and Hour that Petitioner by its appeal is trying to protest the determination of the prevailing wage rates after the award of the contract. Wage and Hour asserts that this question should have been resolved prior to contract award and start of construction. The Solicitor cites several decisions of the Board that have held that an appeal to challenge the wage rates after award and start of construction has not been considered timely. The Board considered this appeal in executive session on the basis of the petition with attachments filed by Petitioner, and a Statement on behalf of the Wage and Hour Division and the record of the case before [4] ~5 [5] Wage and Hour filed by the Solicitor of Labor. It was determined that a hearing by the Board would not be required to decide the case since the factual situation was not contested. Peti[ti]oner has argued that its petition is timely because it promptly forwarded the union rates it believed were in force to the Wisconsin Housing Finance Authority and that it pursued its appeal to the Board immediately following DHUD's denial of reconsideration of the wage rates. Although Petitioner has proceeded with its appeal to this Board promptly, this is not the timliness that is at question in this case. Petitioner was not timely in questioning the Federal wage rates predetermined for the housing project, if in fact it felt that those wage rates were erroneous. This Board has held in a line of cases that challenges to wage rates must be made before the contract is awarded and construction started, or prior to initial endorsement of the mortgage for contracts entered into pursuant to the National Housing Act. See Southeastern Capital Corp., WAB 78-12 (January 16, 1979), Espana Gardens, WAB 76-15 (May 4, 1977), Gananda Development Corp., WAB 73-13 & 74-01 (May 14, 1974) Huntsville-Madison County Airport WAB 64-01 (August 31, 1974). In Espana Gardens, supra, the Board found: It is apparent here that the petitioner is still trying to raise the question of what was [5] ~6 [6] the prevailing rate for the craft in question before the project was started. Petitioner had at the time the question first arose in 1972 the options of appearing before the Wage Appeals Board to protest the prevailing wage rates in contention prior to the start of construction . . .; or he could have chosen not to proceed with the construction of the project until such time as the question of the wages was finally settled. Following neither of these options he chose to proceed with construction. He cannot be allowed to question the wage rates in the wage determination provided to him. As to Petitioner's argument that there was a patent ambiguity in the Project Manual and that it therefore made a mistake, the Board finds that there was no mutuality of mistake. If anything, it was a unilateral mistake on Petitioner's part. It has not been shown that the rates contained in the Department's wage determination were in error. The format of the wage schedules published in the Project Manual was identical to those used by all other contractors without the problems claimed to exist here. The Supplementary General Conditions of the contract cited in the Statement for Wage and Hour contemplate that there may be a variation between the Federal and State wage determinations and clearly explain how this is to be resolved. There appears to be no justification whatever for Petitioner taking recourse to the negotiated union agreements or any other wage rates which it may choose to use. The Board readily concurs in the Solicitor's observation that if Petitioner was uncertain about the wage [6] ~7 [7] rates to be used on the project, it could have requested clarification from HUD after receipt of the wage determination or at the preconstruction conference. As in Espana Gardens, supra, Petitioner by this appeal is trying to change the deter- mination of wage rates for laborers and mechanics after the contract has been awarded to it and construction begun. This is not permissible under the Regulations and decisions of this Board. In view of these considerations, the decision of the Acting Assistant Administrator is hereby affirmed and the Petition is dismissed. BY ORDER OF THE BOARD Craig Bulger, Executive Secretary [] [7]



Phone Numbers